Question Asked

To ask the Secretary of State for Transport, pursuant to the Answer of 1 July 2026 to Question 12229 on Railways: Infrastructure, what the total number is of rail infrastructure projects in England with an anticipated capital cost of less than £50 million that are currently delivering on site; and what proportion of those projects are forecasting completion after their original baseline completion date.

Asked by:
Mr Richard Holden (Conservative)

Answer

Of the rail infrastructure projects in England currently delivering on site with an anticipated capital cost of less than £50 million, 144 projects are forecasting completion after their original baseline completion date, out of a total of approximately 500 projects.