Question Asked
Asked by:
Andrew Griffith (Conservative)
Answer
Approximately 6,490 premises in the Arundel and South Downs constituency were included in the initial scope of the Project Gigabit contract for East and West Sussex, which is being delivered by CityFibre.
Building Digital UK (BDUK) and CityFibre have since agreed not to progress with the later stages of the contract which are not yet in delivery. This is due to commercial coverage extending further than suppliers had previously indicated, meaning fewer premises now require public subsidy and therefore, the contract was redesigned to minimise overlap with commercial plans and ensure best use of public money.
Following this decision, approximately 5,890 premises in Arundel and South Downs have been descoped from the contract. Of the descoped premises, approximately 850 already have access to a gigabit-capable broadband connection and around 890 are currently included in future commercial delivery plans.
As with other areas, BDUK is working to put in place alternative coverage solutions as soon as possible for the remaining premises which still require support. A market engagement consultation for suppliers was published on 1 June to confirm supplier interest in relation to the premises that still need coverage in the affected areas.