PARLIAMENTARY WRITTEN QUESTION
(13 May 2026)
Question Asked
Asked by:
Rebecca Smith (Conservative)
Answer
The most recent appraisal was undertaken in 2014 as part of the Blackburn to Manchester Rail Scheme, which assessed options to double the single-track sections between Blackburn and Bolton.
The preferred option was to extend the Darwen passing loop, which presented a core BCR of 1.67. The £13.8 million scheme was funded by Blackburn & Darwen Council and the Local Growth Fund. It was delivered by Network Rail in 2015 and the half hourly rail service between Blackburn and Manchester Victoria commenced in December 2017.
The Department has no plans to undertake further economic analysis or development work on this corridor, but would welcome discussions with Lancashire County Combined Authority, should they wish to prioritise any such analysis locally.