PARLIAMENTARY WRITTEN QUESTION
(10 October 2025)
Question Asked
Asked by:
Mr Joshua Reynolds (Liberal Democrat)
Answer
Full navigation access at Temple Footbridge will be reinstated once the central section of the bridge is removed and taken off site for inspection and secure storage. This is now expected to take place in November 2025, at a cost of approximately £450,000. Public pedestrian access will be reinstated once the bridge is either refurbished or replaced. The costs of this will be known once the outline design is completed in March 2026 and the removed central section in fully inspected.
Answered by:
()
Contains Parliamentary information licensed under the Open Parliament Licence v3.0.