PARLIAMENTARY WRITTEN QUESTION
(2 July 2025)

Question Asked

To ask the Secretary of State for Energy Security and Net Zero, what steps he is taking to accelerate grid connection times for small and medium-sized enterprises and manufacturers participating in grid-balancing schemes.

Asked by:
Gregor Poynton (Labour)

Answer

The National Energy System Operator (NESO) is implementing fundamental reforms to the connections process that will free up capacity and accelerate connections, including for small and medium-sized enterprises and manufacturers. But we recognise that further action is needed and that is why we announced plans in the Industrial Strategy to launch a Connections Accelerator Service and use new legal powers to accelerate grid connection timelines for demand projects.


Answered by:
()

Contains Parliamentary information licensed under the Open Parliament Licence v3.0.