PARLIAMENTARY WRITTEN QUESTION
(17 April 2025)

Question Asked

To ask the Secretary of State for Energy Security and Net Zero, whether he has made an assessment of the adequacy of the (a) exclusion zones, (b) fire suppression systems, and (c) environmental risk mitigation measures outlined in the revised Battery Safety Management Plan for Cleve Hill Solar Park.

Asked by:
Helen Whately (Conservative)

Answer

The issues raised are matters for Swale Borough Council acting in consultation with the Health and Safety Executive and Kent Fire and Rescue Service as set out in Requirement 3 of the Cleve Hill Solar Park Order 2020. Following an appeal by the developer, on 5 July 2024 the Planning Inspectorate, acting on behalf of the Secretary of State, approved the Battery Safety Management Plan after Swale Borough Council had refused an application for its approval.


Answered by:
()