PARLIAMENTARY WRITTEN QUESTION
(17 April 2025)
Question Asked
Asked by:
Helen Whately (Conservative)
Answer
Requirement 3 of the Cleve Hil Solar Park Order 2020 made Swale Borough Council responsible for approving the Battery Safety Management Plan after consulting with the Health and Safety Executive and Kent Fire and Rescue Service. There is no requirement for Swale Borough Council to consult with the Environment Agency. Following an appeal by the developer, The Battery Safety Management Plan was approved by the Planning Inspectorate on behalf of the Secretary of State on 5 July 2024 after Swale Borough Council refused an application for its approval.
Answered by:
()
Contains Parliamentary information licensed under the Open Parliament Licence v3.0.