The projects and mileages are:

Southampton Port to Basingstoke34 miles
Basingstoke to Southcote Junction (Reading)14 miles
Oxford to Leamington Spa43 miles
Leamington Spa to Coventry9 miles
Coventry to Nuneaton9 miles
Oxford to Bedford46 miles