PARLIAMENTARY WRITTEN QUESTION
(5 February 2025)

Question Asked

To ask the Secretary of State for Defence, with reference to the Infrastructure and Projects Authority Annual Report on Major Projects 2023-24, published on 16 January 2025, what progress has been made with the Core Production Capability programme since 31 March 2024.

Asked by:
Mr Calvin Bailey (Labour)

Answer

The Department is working closely with Rolls-Royce Submarines (RRS) to improve delivery confidence for the Core Production Capability programme. This has included increasing production rates and improving manufacturing resilience. The Infrastructure and Projects Authority has confirmed these ongoing actions are appropriate.


Answered by:
()

Contains Parliamentary information licensed under the Open Parliament Licence v3.0.