PARLIAMENTARY WRITTEN QUESTION
(16 January 2025)
Question Asked
Asked by:
Llinos Medi (Plaid Cymru)
Answer
Grid connections for individual projects are a matter for the National Energy System Operator (NESO) and the network companies.
The short pause on connection applications for generation customers is a necessary transitional step in delivering fundamental connections reforms that, if approved by Ofgem, could reduce the connections queue by up to half and will enable accelerated connections for many generation and demand projects. The pause does not apply to demand projects or to projects connecting to the distribution network which do not require Transmission Impact Assessment.
Answered by:
()