To ask the Secretary of State for Transport, what estimate her Department has made of the cost of constructing East-West Rail in 2024 prices.

Asked by:
Blake Stephenson (Conservative)

Answer

£1.3bn has been provided towards the delivery of East West Rail Connection Stage 1 (CS1) which will provide services from Oxford to Bletchley and Milton Keynes.

The capital cost estimate for Connection Stages 2 (Oxford-Bedford) and 3 (Oxford-Cambridge) is £5bn-£6bn in 2021 prices. Final costs for the project will be driven by scope and design choices.