National Energy System Operator (NESO) recommended the transmission infrastructure required to connect Morgan and Morecambe offshore wind projects to the grid as part of its Holistic Network Design (HND). In producing the HND, NESO assessed multiple onshore and offshore design options against future generation and demand scenarios, existing infrastructure in the National Electricity Transmission System, and total capital and operational costs. NESO then used an economic optimiser to determine the optimal economic design from the options.