PARLIAMENTARY WRITTEN QUESTION
(16 December 2024)
Question Asked
Asked by:
Emily Thornberry (Labour)
Answer
The department spent £608,685 on the refurbishment of Ministerial offices during the period 4 July 2022 to 4 July 2024 on new furniture and fittings and other refurbishment. This is broken down as follows:
- Furniture and Fittings - £127,385
- Refurbishment of Ministerial Offices - £481,300
The department has been undertaking a refurbishment project at Sanctuary Buildings to transform the building from its previous use as the department head office into a Government Property Agency (GPA) hub with multiple government occupants. This is part of the consolidation of buildings in and around Whitehall and will generate cost savings.
This project refurbished all relevant floors that the department occupies including where the Ministerial offices are located. As a result of this wider project, during the timeframe referenced, all Ministerial offices were rebuilt, and furniture replaced. As part of the renovation, the direct costs to create Ministerial rooms (excluding mechanical and engineering plant systems) includes costs for purchase and installation of carpets, wood panelling, paint upgrades and glass partitions.
A list of furniture and fittings purchased are available in the attached document.
Answered by:
()
1 January 1970
Contains Parliamentary information licensed under the Open Parliament Licence v3.0.