Housing: Stockport (2 September 2022)

Question Asked

To ask the Secretary of State for Business, Energy and Industrial Strategy, what assessment his Department has made of the impact of capacity issues at the national grid on housebuilding in Stockport.

Asked by:
Navendu Mishra (Labour)

Answer

The Government is aware of lengthy connection timelines currently being offered in parts of the country, particularly where transmission network upgrades are required to accommodate distribution network connections, such as housing developments. Network companies are working with Ofgem to release capacity including through improved modelling of network impacts of new connections and streamlining of connection procedures.


Answered by:
Graham Stuart (Conservative)
20 September 2022