PARLIAMENTARY WRITTEN QUESTION
High Speed 2 Line: Woore (7 February 2022)

Question Asked

To ask the Secretary of State for Transport, what risk assessments were carried out in relation to pedestrian safety when determining the route of HGV traffic for the HS2 construction project through the parish of Woore.

Asked by:
Helen Morgan (Liberal Democrat)

Answer

The Environmental Statements published for HS2 Phase 2a assessed the impacts of construction traffic for the proposed Phase 2a construction routes, including impacts on pedestrians and their safety for the parish of Woore.


Answered by:
Andrew Stephenson (Conservative)
15 February 2022

Contains Parliamentary information licensed under the Open Parliament Licence v3.0.