PARLIAMENTARY WRITTEN QUESTION
High Speed 2 Line: Crewe (11 March 2021)

Question Asked

To ask the Secretary of State for Transport, what plans the Government has to include the connection to the high speed line north of Crewe in plans for HS2 Phase 2b.

Asked by:
Dr Kieran Mullan (Conservative)

Answer

Crewe is already a hub on the existing rail network and following a consultation in 2016, the Government confirmed its vision for a ‘Crewe Hub’, with up to 5 to 7 HS2 trains stopping per hour.​ Fully realising the Crewe Hub vision will require a junction north of Crewe back to the HS2 Phase 2b mainline and the design is being developed as part of the Northern Powerhouse Rail Strategic Outline Business Case.


Answered by:
Andrew Stephenson (Conservative)
17 March 2021

Contains Parliamentary information licensed under the Open Parliament Licence v3.0.