PARLIAMENTARY WRITTEN QUESTION
Twentyshilling Hill Wind Farm (20 October 2020)
Question Asked
Asked by:
David Mundell (Conservative)
Answer
Ministry of Defence (MOD) officials are working collaboratively with the developer to see if a Mitigation Scheme could be devised to allow the Twenty Shilling windfarm to be built whilst protecting the nearby Eskdalemuir Seismological Array. The scheme is complex and covers noise monitoring, testing, reporting, compliance, and curtailment.
A legal agreement would need to be reached by all parties, that legal agreement is progressing. If a mitigation scheme is achievable MOD officials aim to be in a position to conclude the legal agreement in the next few months, subject to negotiation.
Answered by:
Sir Jeremy Quin (Conservative)
27 October 2020
Contains Parliamentary information licensed under the Open Parliament Licence v3.0.