PARLIAMENTARY WRITTEN QUESTION
High Speed 2 Line (13 July 2020)
Question Asked
Asked by:
Dr Kieran Mullan (Conservative)
Answer
229 sites out of a possible 244 sites are open, meaning that 94% of sites that could be open are open. All Construction sites for Main Works Civils on the Phase One route are open. A small number of enabling works construction sites remain closed/paused, primarily due to work requiring access to residents’ homes.
Answered by:
Andrew Stephenson (Conservative)
16 July 2020
Contains Parliamentary information licensed under the Open Parliament Licence v3.0.