Warrior Vehicles (3 March 2020)

Question Asked

To ask the Secretary of State for Defence, what is the (a) original and (b) most recent estimated cost to the public purse of the warrior capability sustainment development programme; and when he expects vehicles produced through that programme to come into service.

Asked by:
Mr Mark Francois (Conservative)

Answer

The Warrior Capability Sustainment Project (WCSP) aims to deliver an operational fleet of upgraded Warrior Infantry Fighting Vehicles, with improved survivability and firepower, until at least 2040.

The original cost of the WCSP demonstration and manufacture phases in 2011 was estimated at £1.319 billion, with the most recent estimated cost being £1.546 billion. Manufacture discussions to confirm a date the vehicles will come into service are ongoing.


Answered by:
Sir Jeremy Quin (Conservative)
9 March 2020