PARLIAMENTARY WRITTEN QUESTION
Incinerators: Carbon Capture and Storage (13 February 2020)
Question Asked
Asked by:
Caroline Nokes (Conservative)
Answer
The requirement to demonstrate carbon capture readiness applies to applications for power stations with an electrical generating capacity at or over 300 MW and of a type covered by the EU Large Combustion Plant Directive (LCPD). Energy from waste generating stations are not covered by the LCPD. Therefore energy from waste generating stations of any capacity do not have to demonstrate carbon capture readiness.
Answered by:
Kwasi Kwarteng (Conservative)
28 February 2020
Contains Parliamentary information licensed under the Open Parliament Licence v3.0.