PARLIAMENTARY WRITTEN QUESTION
Crossrail Line: Railway Stations (7 May 2019)

Question Asked

To ask the Secretary of State for Transport, what discussions he has had with (a) Network Rail and (b) Crossrail Ltd on the transfer of funding from Control Period 5 to Control Period 6 for station upgrades at (i) West Ealing, (ii) Ealing Broadway and (iii) Acton Main Line.

Asked by:
Dr Rupa Huq (Labour)

Answer

All of the funding required is in place for the remaining work at West Ealing, Ealing Broadway and Acton Main Line. The Department for Transport has regular discussions with Network Rail and Crossrail Limited regarding the Network Rail works. Network Rail closely monitors its finances through monthly reporting to Crossrail Limited.

In Control Period 5, £16.6m of funding was allocated to the build elements of the Crossrail station upgrade works at West Ealing, Ealing Broadway and Acton Main Line. Of this funding £16.6m has been spent.

In Control Period 6, £64.4m of funding has been allocated to the Crossrail station upgrade works at West Ealing, Ealing Broadway and Acton Main Line.


Answered by:
Andrew Jones (Conservative)
15 May 2019