PARLIAMENTARY DEBATE
Planning and Infrastructure Bill (Fourth sitting) - 29 April 2025 (Commons/Public Bill Committees)
Debate Detail
Chair(s) Wera Hobhouse, † Derek Twigg
Members† Amos, Gideon (Taunton and Wellington) (LD)
† Caliskan, Nesil (Barking) (Lab)
† Chowns, Ellie (North Herefordshire) (Green)
† Cocking, Lewis (Broxbourne) (Con)
† Dickson, Jim (Dartford) (Lab)
† Ferguson, Mark (Gateshead Central and Whickham) (Lab)
† Glover, Olly (Didcot and Wantage) (LD)
† Grady, John (Glasgow East) (Lab)
† Holmes, Paul (Hamble Valley) (Con)
† Kitchen, Gen (Wellingborough and Rushden) (Lab)
† Martin, Amanda (Portsmouth North) (Lab)
† Murphy, Luke (Basingstoke) (Lab)
† Pennycook, Matthew (Minister for Housing and Planning)
† Pitcher, Lee (Doncaster East and the Isle of Axholme) (Lab)
† Shanks, Michael (Parliamentary Under-Secretary of State for Energy Security and Net Zero)
† Simmonds, David (Ruislip, Northwood and Pinner) (Con)
Taylor, Rachel (North Warwickshire and Bedworth) (Lab)
ClerksDominic Stockbridge, Committee Clerk
† attended the Committee
Public Bill CommitteeTuesday 29 April 2025
(Afternoon)
[Derek Twigg in the Chair]
Planning and Infrastructure BillAmendment proposed (this day): 57, in clause 4, page 8, line 21, leave out subsection (2).—(Matthew Pennycook.)
Question again proposed, That the amendment be made.
Government amendment 58.
Clause stand part.
Government motion to transfer clause 4.
Clause 5 stand part.
Government amendments 60 to 67.
Clauses 6 and 7 stand part.
Government new clause 44—Applications for development consent: removal of certain pre-application requirements.
Government new clause 45—Applications for development consent: changes related to section (Applications for development consent: removal of certain pre-application requirements).
As the Committee is aware, I set out the Government’s position on this matter in considerable detail in my written ministerial statement from 23 April. I therefore intend to focus my remarks on providing useful further points of clarification about the rationale for the proposed reforms and how we see the system operating once they have been made.
In her remarks, the hon. Member for North Herefordshire conceded that the NSIP process can take a long time, but she implied that the problem was merely confined to individual applications. The Government disagree. From our perspective, the problem that these and other changes in this chapter are intended to remedy are systemic. The status quo is not working, and all too often it is burdensome to applicants and consultees alike.
We know that the performance of the NSIP regime as a whole has deteriorated sharply over recent years. We know that pre-application periods have, on average, nearly doubled since 2013, increasing from over 14 months to nearly 28 months in 2021. As much as Labour Members welcome any and every reminder of the chaos unleashed under recent Conservative Administrations, I do not believe that the deterioration we are discussing can be attributed to the uncertainty that the post-2016 period engendered.
The evidence clearly points to the fact that inefficiencies in the NSIP system, both structural and cultural, are driving delays and high costs. We heard examples this morning of the fact that the documentation underpinning consents has been getting longer, and in too many instances now runs to tens of thousands of pages. Part of the reason is that the statutory and prescriptive nature of the pre-application requirements—I again remind the Committee that they are absent from other planning regimes, including those used for applications for new housing—are driving perverse outcomes.
It is precisely because the requirements are statutory that applicants fear that falling short of them will see their project rejected further down the line, or leave them exposed to judicial review. As we have discussed, the result is that projects are slowed down as developers undertake ever more rounds of consultation and produce greater amounts of documentation to ensure that the requirements are met. Sensible improvements are deterred because applicants worry that they will require further rounds of consultation to insulate them from challenge.
In short, as I argued in the previous sitting, the dynamics of the system are actively encouraging risk aversion and gold-plating and are compelling applicants to go above and beyond what may be required in law, rather than merely ensuring that an application is acceptable in planning terms. Because the root of the problem is the statutory nature of the requirements, it is worth noting that the same behavioural incentives would be in play if we reinserted into the Bill precise statutory criteria for what constitutes effective consultation, as the hon. Member for Taunton and Wellington suggested we should.
In his contribution, the shadow Minister argued that we should focus on improving rather than removing the statutory requirements in question. However, he overlooked the fact that the NSIP action plan, published by the previous Government in February 2023, contained a range of reforms designed to drive more effective and proportionate approaches to consultation and engagement, including new cost-recoverable pre-application services for applicants at the Planning Inspectorate, and revised and strengthened pre-application guidance.
While those steps were welcome, and this Government are seeking to embed new services and cost-recovery mechanisms, the feedback we have received from a wide range of stakeholders suggests that they will not deliver the necessary step change needed to tackle risk aversion and gold-plating. It is the dynamic that has arisen as a result of the very existence of the statutory pre-application requirements in question that is hampering their nominal purpose of producing better outcomes, and the present arrangements are driving up costs not only for developers, but for the bill payers and taxpayers we all represent.
The Government are in complete agreement with the hon. Member for North Herefordshire that early, meaningful and constructive engagement with those affected, including local authorities, statutory consultees, landowners and local communities, often leads to better schemes, greater local benefits and improved mitigation. We still want and expect the NSIP regime to function on the basis of a front-loaded approach in which development proposals are thoroughly scoped and refined prior to being submitted to the Planning Inspectorate. As part of that process, we still want and expect high-quality, early, meaningful and constructive engagement to take place and for positive changes to be made to applications. However, we want and expect it to take place without the downsides that the current statutory requirements are causing.
Removing the statutory requirements in question does not signify that pre-submission consultation and high-quality engagement is no longer important. Statutory guidance that the Government will be required to produce will encourage such pre-application engagement and consultation, but with applicants given the flexibility to carry it out in the way that they consider best for their proposed development, in accordance with that guidance.
Equally as importantly, the system will still reward high-quality engagement and consultation. The Planning Inspectorate will continue to assess whether applications are suitable to proceed to examination. We expect guidance to emphasise that without adequate engagement and consultation, applications are unlikely to be able to do so. Guidance and advice from the Planning Inspectorate will be aimed at helping applicants demonstrate that they are of a satisfactory standard in terms of meeting that process.
Ultimately, all communities will still be able to have their voices heard, whether that is through objecting outright to applications or providing evidence of adverse impacts through the post-submission examination process, which all applications obviously still need to go through.
The regime, which began as one in which every section of it respected the deadlines, became one in which every section respected the deadlines with the exception of the Secretary of State. The intention of those drafting the Planning Act 2008 was that, in such circumstances, a report to Parliament by the Secretary of State when delaying the decision would serve as a disincentive on the Secretary of State for doing so. That clearly has not happened. Will the Minister reflect on whether any other measures could be taken to eliminate the delays caused by Secretaries of State making decisions on NSIPs in future?
To conclude, the changes proposed will make a significant contribution to speeding up and streamlining the consenting process for critical infrastructure, and we are convinced that in many cases they will produce better outcomes than the status quo. I therefore urge the Committee to support them.
Amendment 57 agreed to.
Amendment made: 58, in clause 4, page 8, line 32, leave out subsection (3).—(Matthew Pennycook.)
This amendment is consequential on NC44.
Clause 4, as amended, ordered to stand part of the Bill.
Ordered,
That clause 4 be transferred to the end of line 32 on page 12. —(Matthew Pennycook.)
Clause 5 disagreed to.
Clause 6
Applications for development consent: acceptance stage
Amendments made: 60, in clause 6, page 10, line 4, leave out “follows” and insert
“set out in subsections (2) to (13)”.
This amendment is consequential on Amendment 68.
Amendment 61, in clause 6, page 10, line 25, after “Secretary of State” insert “and others”.
This amendment is consequential on subsection (5)(d) of NC45.
Amendment 62, in clause 6, page 11, line 4, leave out from “satisfying” to “and” in line 6 and insert
“section 48 (duty to publicise),”.
This amendment is consequential on NC44.
Amendment 63, in clause 6, page 11, leave out lines 12 to 14.
This amendment is consequential on NC44.
Amendment 64, in clause 6, page 11, line 16, leave out “50” and insert “50(1)”.
This amendment is consequential on Amendment 63.
Amendment 65, in clause 6, page 11, leave out lines 17 to 20.
This amendment is consequential on Amendment 63.
Amendment 66, in clause 6, page 11, line 21, leave out subsection (9) and insert—
“(9) Omit subsection (5).”
This amendment is consequential on Amendment 64.
Amendment 67, in clause 6, page 12, line 32, at end insert—
“(14) In consequence of the amendments in subsections (7)(c) and (10), omit section 137(3) and (4) of the Localism Act 2011.”—(Matthew Pennycook.)
This technical amendment omits provisions of the Localism Act 2011 that are no longer required (because of changes made by clause 6 of the Bill).
Clause 6, as amended, ordered to stand part of the Bill.
Clause 7 ordered to stand part of the Bill.
Clause 8
Planning Act 2008: legal challenges
Question proposed, That the clause stand part of the Bill.
The clause will remove the paper permission stage, meaning that applications for judicial review will go straight to an oral hearing in the High Court. The clause will also remove the right to appeal for cases that are deemed totally without merit at the oral hearing, which becomes the only attempt for these cases. The Government are committed to maintaining access to justice, which is why the right of appeal will remain for cases that are refused permission at the oral hearing, but that are not deemed totally without merit. The changes are a necessary means of preventing meritless claims from holding up development by exhausting the appeals process and of ensuring that legitimate legal challenges are heard promptly. I commend the clause to the Committee.
We are well aware of issues relating to air quality, but there are also organisations such as ClientEarth, which many of us will have heard of. Essentially, their stock in trade is to look for opportunities to address broader issues around, for example, climate change and environmental impact by using what, in some cases, are arguably loopholes, but in many cases, are essentially contradictions in legislation.
The Minister talked earlier about a shift from having statutory pre-application processes to having guidance that would need to be followed. Clearly, one of the issues is that guidance can be challenged, and bodies that have a responsibility to follow the guidance can be challenged as to whether they have fulfilled their obligation to the letter.
Opposition Members certainly have concerns about the implications of removing the right to judicial review. We share the view that we need to ensure that those processes—those applications—are not frivolous and that they are not being used simply because the cost of responding to judicial review, and the delay that is involved, is a tool to create delay, impose costs and therefore deter development, which we all agree should take place. Conversely, however, we do not wish to see a situation where a public body or a local resident—a constituent—who has a genuine right to be heard and a genuine concern arising out of law is constrained from bringing the matter forward and seeking a remedy.
We also do not want a situation where, for example, a decision by Government, which is then taken through this process and restricted from judicial review, results in a third party, such as a local authority or NHS body, being judicially reviewed for its failure to stop that from proceeding—for its failure to bring a judicial review under other responsibilities that it has. I would be grateful if the Minister could address that.
Statutory consultees already have many legal obligations and duties relating to issues such as water quality, air quality and nature. They are obliged to go to the utmost of their powers to fulfil those obligations. Clearly, they may well be held in default if a development proceeds by virtue of the fact that they have not had the opportunity to appropriately challenge it in law. It would be helpful if the Minister set out how that will be fully addressed.
On clause 8 specifically, the changes will not affect the ability to challenge the lawfulness of Government decisions in court. They are simply designed to reduce delays. We are not preventing anyone from challenging our planning decisions. Obviously, Government do not control how many of those challenges are made. We are tightening up the process so that if a challenge is judged to be meritless by the court—not by Government—it cannot be dragged on for years through numerous further appeals.
Only cases deemed totally without merit in the oral permission hearing in the High Court will be prevented from appealing to the Court of Appeal. Other cases will continue to be able to appeal the refusal of permission to the Court of Appeal. That will ensure that there is no possibility of meritless claims holding up nationally significant infrastructure projects, while maintaining access to justice in line with our domestic and international obligations.
I hope that the hon. Member is reassured that we are not removing wholesale the ability to mount judicial review challenges. Some have called for us to go further, but we think the proposals strike the right balance between addressing the removal of the paper permission stage and dealing with the issue of meritless claims. On that basis, I hope that he is reassured and may even feel inclined to support the measure.
However, it would be remiss of us as a party not to acknowledge that there are cases where JR is used vexatiously. To use an example from my constituency, I waited for 12 years to get a 300-foot extension to Southampton airport’s runway. It took three judicial reviews before we finally got that through. There was unmitigated support from the local authority and me as the Member of Parliament at the time, and it was taken to JR for what I would say were very dubious reasons, just to try to delay the project.
I understand why the Minister is bringing in the measures, notwithstanding some of the concerns that my hon. Friend mentioned about the balance. However, I am reassured by what the Minister said about not removing the ability to challenge and tightening the process around what can be accepted as being without merit.
I have one question for the Minister, which he may not be able to answer today—I would not necessarily expect him to—but perhaps he could write to me about it. Following Lord Banner’s work, which was a thoughtful examination of how legal challenges could be streamlined, has the Minister made any assessments, through officials or the Department, of how much time or cost on average the changes to clause 8 might mean for the system overall? I am not expecting him to get his abacus out and look at that now, but I wonder whether he could outline to the Committee, through an impact assessment, the effect of some of the changes.
We will not push this clause to a Division. We understand the principled reason why the Minister is bringing it forward, even if we have some concern about the detail of the measure.
I have had the misfortune to be involved in infrastructure projects for many years. From time to time judicial reviews without any merit are brought solely to delay and frustrate projects. It is right and proper that the law is changed to make it clear that, once the High Court has made a decision, following argument—because the right to an oral hearing is retained—further appeals are prevented. Such appeals can lead to significant delays, depending on the business of the Court of the Appeal, which has many pressing priorities.
Some mention was made of costs. I will briefly describe the cost to developers, because the Labour party is a pro-business, pro-environment party. If someone has a development that is subject to a judicial review, they have planned their contracting strategy, and what it will cost to build the development, and their financing. If there is an indeterminate delay, and a series of additional delays of unpredictable length—as a lawyer, I could never tell people how long litigation would take—they are then exposed to significant fluctuations in the financial and commodities markets. There are therefore real costs, so I naturally support clause 8. The clause, along with the rest of the package of reforms to the development consent order regime, will create the opportunity for significant additional employment in Scotland, jobs for our young people, and great net zero and housing projects.
To be clear, this clause does remove the paper permission stage, but only makes changes by removing the right to appeal for cases that are deemed “totally without merit”. Other cases will retain that right of appeal if they are deemed to be with merit and able to be considered. We think these changes will make a difference to the time that projects take to work their way through the system, and we will work with the judiciary to advance a number of other changes to the process for NSIP judicial reviews, such as introducing target timescales for cases that we think will have a beneficial impact. On that basis, I commend the clause to the Committee.
Clause 9
Connections to electricity network: licence and other modifications
“(and such an improvement may include changing the order in which connections are made)”.
This amendment clarifies that the purpose for which the power under clause 9(1) may be exercised may include the making of changes to the order of the queue for connections to a transmission or distribution system.
Government amendments 37 to 40.
Clause stand part.
Clauses 10 and 11 stand part.
New clause 19—Increasing grid capacity—
The Secretary of State must, within three months of the passing of this Act, lay before Parliament a plan to—
(a) reduce the cost of, and time taken to make, connections to the transmission or distribution system;
(b) permit local energy grids.
This new clause would require the Secretary of State to produce a plan to reduce the time and financial cost of connections to the electricity grid and to allow local energy grids.
Amendment 36 clarifies that a modification made under clause 9 may include changes to the order of the queue for connections, which works towards the broader aim of improving the management of connections to the transmission and distribution systems. The purpose of all this work is to reorder the connections queue. That is essential to deal with the extreme level of oversubscription in the queue, and enable a move from the “first come, first served” proposition that we have at the moment to a “first ready and needed, first connected” approach. The amendment is essential to fulfil the intent of the clauses, which is to provide the means to implement connections reform should the current Ofgem and industry-led process face delays or be unable to realise its benefits in full.
Amendment 37 clarifies that the power of the Secretary of State to direct Ofgem to modify a licence or agreement may be exercised only for the purpose of improving the management of connections to the transmission or distribution system, which places an additional safeguard on the use of that power. Amendment 38 clarifies that the Secretary of State or Ofgem may modify an agreement under the powers in clause 9 even where the effect of the modification might amount to a repudiation of the agreement, which provides consistency with the existing wording in clause 12. It is also essential to fulfil the intent of the clauses. Finally, amendments 39 and 40, which are purely consequential on amendment 38, move the definition of “qualifying distribution agreement” within clause 9.
I turn to clause 9 more broadly. As many Members will know, the current first come, first served electricity grid connections regime is causing considerable and unacceptable delays. It is blocking clean power projects from connecting to the grid, and blocking demand projects that are critical to our economic growth as a country. The National Energy System Operator—NESO—and Ofgem are reforming the electricity grid connections process to a strategically aligned first ready, first connected system. The reformed process will require projects to meet readiness, technological and locational criteria to progress.
The reform requires complex amendments to codes and licences. Clause 9 therefore enables the Secretary of State or Ofgem to support the existing connections reforms by directly amending electricity licences, and associated documents or agreements, should that prove necessary. It is intended to be used should the existing processes enacting connections reforms face significant delays, including alignment with strategic energy plans. The Government or Ofgem will then be able to expedite a set of changes outside the standard process to ensure that our clean power mission is delivered at pace. The clause is focused on improving the management of connections to the transmission or distribution system, and follows precedent in being time-limited to three years after commencement of the power on Royal Assent. Similar powers have been taken in the past, including in section 84 of the Energy Act 2008, but they were also time-limited and are therefore no longer in force.
Clause 10 details the scope of the power in clause 9, which enables the Secretary of State or Ofgem to make amendments to electricity licences and associated documents or agreements. The clause first defines the power to modify in clause 9, which includes the ability to amend, add to or remove provisions, and to add or release parties from agreements. It will enable the Secretary of State or Ofgem to support Ofgem and NESO’s existing connections reforms by directly amending electricity licences, and associated documents or agreements, should that prove necessary.
The clause further details how the Secretary of State or Ofgem can exercise the power, which includes allowing for general or specific modifications, incidental changes and provisions that do not necessarily relate to the activities authorised by the licence. It ensures that modifications to standard licence conditions are reflected in future licences, and specifies the conditions under which licences can be revoked. Finally, it allows agreements to include conditions that must be met before the taking of specific steps, or provision about the procedure for varying the agreement. Similar scope and procedure have been outlined previously in legislation, including in the Nuclear Energy (Financing) Act 2022.
Clause 11 details the procedure around the provision in clause 9 to enable the Secretary of State or Ofgem to make amendments to electricity licences and associated documents. It aligns with the precedent established in section 8 of the 2022 Act, which detailed the procedure to modify a generation licence of a relevant licensee nuclear company. The clause obligates the Secretary of State or Ofgem—I am not sure how many more times I will say that in this speech—to consult a list of specified persons, such as the holder of any relevant licences, NESO and any other appropriate individuals, before making modifications. Details of those modifications must be made public as soon as reasonably practicable to ensure transparency with wider stakeholders. However, the Secretary of State or Ofgem can exclude from the publication any information that could harm commercial interests.
I will respond on new clause 19 after it has been spoken to.
Such queues have been a long-standing issue in the electricity industry, as any developer will tell you, and half the time it is absolutely impossible to know when their project will be connected. That is no basis on which to attract the significant investment we need in our industry in this country, because developers can go to other jurisdictions and get much quicker connections.
This reform has been carefully put together by the ministerial team and Ofgem. The Minister for Energy has addressed the issue, and the reform is to be applauded. It may seem a rather arid and dry topic, but ultimately the reform is of significant benefit to industry in the United Kingdom.
The Minister said he keeps mentioning “Ofgem and the Secretary of State”, but if he would like us to helpfully have a word with the Prime Minister to recommend that he becomes the Secretary of State, we are more than happy to do so. The Opposition believe that even he, as the Under-Secretary, could not do as much damage to our energy system networks and future growth as the Secretary of State, the right hon. Member for Doncaster North (Ed Miliband). [Interruption.] It is a policy disagreement.
This is a policy disagreement because, looking at the proposals in these clauses, we are very concerned. We obviously agree that the grid needs to be ready to connect to, because of the demands being placed on the system, and that is the policy of this Government and of the last. However, the focus of the current Secretary of State in really going down the route of the net zero agenda at what we would describe as a very fast speed, sometimes cutting off his nose to spite his face such as by cutting back on some of the energy systems we currently have, has put overwhelming demand on the energy grid.
The Government’s proposed decarbonising of the grid by 2030 will add at least £25 billion per year to the cost of the electricity system. The brunt of this increase will be felt by the people out there, who will see their household energy bill shoot up by over £900. Professor Gordon Hughes, the leading energy system expert, has found that these plans will increase power generation costs, grid balancing and capacity levels, thereby passing on those costs to our constituents.
The costs of balancing the grid alone are set to rise by £4 billion. Despite that, the Government have scrapped the full system cost review commissioned by the last Government. The current Administration are steaming ahead without a clear understanding of the impact on the energy bills of hard-working people—the energy bills they promised to freeze—on their families and on the industry’s competitiveness. Decarbonising the grid requires transparency on costs, not just soundbites about renewables, which I believe is what we have seen.
The Government have also watered down the proposed community benefits of new energy infrastructure, which they lauded before the press a couple of weeks ago, to just £750 per person.
Furthermore, the Government have abandoned a number of reforms, including a review of the presumption in favour of overhead lines, stronger protection for prime agricultural land against large solar developments, and enhanced safety measures for battery storage facilities. Expanding and improving the electricity system is necessary, but it must be done in a way that balances affordability, reliability and community concerns. We are concerned that the clauses in the Bill remove this transparency and add costs, but will not deliver the streamlined or more rapid benefits to the system that the Minister outlined.
It is much to the UK’s credit that we are making good progress in efforts to decarbonise our electricity generation. Wind and solar in particular account for a growing share of our power generation. However, the transition from one-way transmission of electricity from a small number of very large power stations to a more distributed and multi-directional movement of power creates some challenges. We are going to need major upgrades of our electricity grid to accommodate the growing number of solar installations, as an example, more of which my hon. Friends and I would like to see on new and existing buildings. Making further progress will help our national energy security and reduce consumer bills at a time when energy inflation and the cost of living are still significant problems.
There are examples where cost and/or process have acted as barriers to the ability to feed surplus solar energy into the grid, or to the commissioning of new clean and renewable electricity production. Local energy grids have the potential to benefit communities and use the energy much closer to its source of generation. Therefore our proposed new clause would go further than the Government in the current Bill. It requires the Secretary of State to, within three months of the passing of this Bill, lay before Parliament a plan for how the Government will facilitate the creation of local energy grids and deal with the cost and time of grid connections. I hope the Minister and hon. Members on the Government Benches will embrace this amendment as a way to help continue our country’s journey towards becoming a clean, renewable energy superpower.
We think we need to go even further. The shadow Minister, in a ray of honesty, said he was glad he was not the shadow Energy Minister. Based on the script on net zero, I think we are all fortunate that he is not the shadow Energy Minister, frankly, but it is the same script we are hearing from everyone at the moment.
“I will conclude—many will be pleased to hear—by reaffirming the Conservative party’s strong commitment to the UK’s target of reaching net zero by 2050”—[Official Report, 17 January 2025; Vol. 760, c. 650.]—
only for that to be scrapped by his leader exactly two months later.
The hon. Member for Taunton and Wellington made a helpful speech, although I will resist his new clause. We are in agreement about the issue of connection delays and the first come, first served process not working, and it is important that we reform that. We are of the view that our proposals do that, and the National Energy System Operator has worked with Ofgem and is of the view they are sufficient to do that.
The question of local power and local grids is an interesting approach that we are looking at. We take seriously the role of community-owned power—it is in the Great British Energy Bill, recognising our commitment to it—but we do not see it in itself as a barrier to what we are trying to do here. The infrastructure, including for local networks, that incorporates generation and demand is already permitted under the existing system. It can be constructed and operated by distribution network operators, by independent network operators or by a private wire under a statutory licence exemption provision.
We agree about the importance of community energy and are looking at a range of things, in particular at how communities might to sell power locally. They are all important points, and all this is how we will unlock the social and economic benefits of the clean power transition. For the reasons I have outlined, and because we think it is already entirely possible, we will resist new clause 19.
Amendment 36 agreed to.
Amendments made: 37, in clause 9, page 14, line 8, at end insert—
“(3A) The Secretary of State may exercise the power under subsection (3) only for the purpose mentioned in subsection (2).”
The amendment makes it clear that the power of the Secretary of State to direct the GEMA to modify a licence or agreement may only be exercised for the purpose of improving the purpose of managing connections to the transmission or distribution system.
Amendment 38, in clause 9, page 14, line 15, at end insert—
“(5A) A relevant authority may under subsection (1) modify an agreement mentioned in subsection (1)(e) or a qualifying distribution agreement even if the effect of the modification might amount to a repudiation of the agreement.”
This amendment ensures consistency with clause 12(8) in clarifying that modifications made to a particular connection or distribution agreement under clause 9(1) may be made even if the effect of the modification might amount to the repudiation of that agreement.
Amendment 39, in clause 9, page 14, line 16, leave out subsection (6).
This amendment, together with amendment 40 moves the definition of “qualifying distribution agreement” into subsection (7); this change is consequential on amendment 38.
Amendment 40, in clause 9, page 14, line 27, at end insert—
“‘qualifying distribution agreement’ means—
(a) the terms subject to which a connection is made by an electricity distributor in pursuance of section 16(1) of the Electricity Act 1989, or
(b) a special connection agreement as defined by section 22(1) of that Act;”.—(Michael Shanks.)
See the explanatory statement for amendment 39.
Clause 9, as amended, ordered to stand part of the Bill.
Clauses 10 and 11 ordered to stand part of the Bill.
Clause 12
Directions to modify connection agreements
The effect of this amendment is that a relevant authority may give a direction under clause 12 without first having exercised its powers under clause 9(1) to modify an electricity licence or an electricity industry code.
Government amendments 42 to 47.
Clause stand part.
An example of where the amendment would be needed is if an Ofgem and NESO-led process to amend licences and codes under the framework is successful, meaning that the powers in clause 9 do not need to be used, but the NESO or DNO has not accordingly amended its agreements with customers connecting to the electricity network. The directive powers could be used to ensure that the implementation of connections reform is successful.
Amendment 43 mirrors Government amendment 36 in clarifying that a direction given under clause 12 may include changes to the order of the queue for connections, within the broader aim of improving the management of connections to the transmission or distribution system. Reordering the queue is essential to deal with the extreme level of oversubscription in the queue, enabling the move, as I have already said, to a “first ready, first connected”, strategically aligned approach. The amendment is essential to fulfil the full aim of the clauses.
Amendment 44 reflects the possibility that the power to direct the NESO and the DNO will be used independently of the power in clause 9 to amend codes and licences, in line with amendment 41. In this scenario, it would be necessary for the Secretary of State or Ofgem to describe the kinds of modifications that the NESO and the DNOs are required to make. Should the power to direct the NESO or the DNOs be used following the exercise of powers in clause 9, the Secretary of State or Ofgem may simply describe the way in which the NESO and the DNOs should amend agreements to give effect to the changes made under the clause 9 power.
On amendment 45, it is right that relevant parties are consulted ahead of the exercise of the power in clause 12(2). The amendment would insert an obligation for the Secretary of State or Ofgem to consult the person to whom they propose to give the direction, and any other appropriate individuals, before making the direction to modify connection agreements. Amendment 46 would ensure appropriate safeguards on the use of that power, limiting its use to three years after commencement on Royal Assent.
On amendment 47, where a body such as the NESO or a DNO is directed to take an action, there is an expectation that it must comply and that that should be enforceable. Such a direction should therefore be accompanied by a mechanism for enforcement. The amendment modifies the Electricity Act 1989 to allow for the enforcement of compliance with any direction given. This reflects the importance of connections reform and the compliance of the NESO and DNOs with this legislation.
Clause 12 empowers the Secretary of State or Ofgem to direct the NESO or a DNO to amend connection agreements. This power is restricted to agreements entered into by the NESO under an electricity licence or a qualifying distribution agreement for DNOs. This would cover current and future agreements or contracts with a party seeking to connect to the electricity network.
Like clause 9, clause 12 aims to enhance the process for managing connections to transmission or distribution systems. If amended, it will clarify that such improvements may include changing the order in which connections are made. Without the clause, it would not be possible for the Secretary of State or Ofgem to amend the specific agreements as they are not party to them. The clause says that the NESO or the DNO can modify agreements only as directed by the Secretary of State or Ofgem.
If amended, clause 12 will follow the procedure in clause 11 by obligating the Secretary of State or Ofgem to consult a list of specified persons, such as the person to whom the direction is given, and any other appropriate individuals. If amended, the clause will also be time-limited to three years after commencement of the power on Royal Assent. The clause obligates the NESO and the distribution network operators to comply with the direction given and, if amended, will modify the Electricity Act 1989 to allow for the enforcement of compliance with any direction given. I commend Government amendments 41 to 47 and clause 12 to the Committee.
One of the things we are all conscious of with the move to renewables being the main source of power in the grid—something that the UK has achieved faster than most other countries, with a bigger drop compared with the 1990 baseline than any other developed economy —is that it makes the grid more complex. Unlike oil, gas and nuclear, which can be delivered in an entirely predictable manner, renewables are generally much less predictable. There are times when the wind does not blow and the sun does not shine, and we cannot therefore put that element into the grid. We need to find alternative methods so we need to be able to shift greater amounts of power around to meet the growing energy needs.
As the Minister has outlined, the regime that is envisaged will, for a limited period of time, give greater powers to the Government to determine who gets connected and in which order. First, will the Minister set out how he and the Government intend to feed back to Parliament what we learn from that process, to inform the future shape of our energy grid?
Secondly, what recourse will there be for those at a certain point in the queue who anticipate that their development, whatever it may be, will be served by a particular project and connected at a particular point, if the Government decide otherwise because the reordering of the queue is, in the Minister’s view, necessary? We all understand why that may happen, but if someone is about to invest in a major new carbon capture and storage facility—the sort of major infrastructure project that the Bill is designed to support—and they expect it to be powered by a wind farm but are then told they have been moved much further down the queue than they expected, that will affect the delivery of that project. It would be helpful to understand the process whereby those affected by the reordering of the queue are able to challenge the decision, if necessary, and certainly to engage with the Government, or with constituency MPs, who may seek to advocate for them, so that the reordering can be revisited if necessary.
The hon. Gentleman is right to say that the process of prioritising projects will mean that some will be deprioritised. We have looked at the projects that already have a connection date, and in many cases they will proceed. Viable generation projects above the capacity ranges outlined in the clean power action plan—the first strategic document that will be used to guide projects—might still be able to connect if there is capacity in that particular bit of the DNO after the prioritised projects have been assessed. If there is no space in the pre-2030 queue, they will be offered dates in the 2031-35 process.
We have been clear throughout that the process has not been arbitrary or theoretical. Ofgem and NESO have gone through individual applications that are currently in the process to make sure not only that they fit with the requirements of the clean power action plan but that projects are not unnecessarily disadvantaged. Some projects will go ahead even though they are not in the strategic plan, because where they already are in the grid will make it possible for them to go ahead.
The question of transparency is really important. I will come back to the Committee with details on how we might make the information public, but throughout the process Ofgem and NESO have made public as much information as possible about how they have gone about things, and there was a full public consultation as well. The point about how individual MPs can see whether projects in their constituency are affected is well made and I will take that away and reflect on it.
The critical fact, as the previous Government rightly recognised, is that 750-plus GW is simply unmanageable. Really good projects are sitting with dates long into the future but cannot connect because of what are often phantom projects that are never going to come to fruition and are holding up spaces in the queue. For all the reasons that the hon. Gentleman outlined in terms of the importance of energy security, and the importance of prioritising the queue, we think that the Government amendments and the clause are essential.
Amendment 41 agreed to.
Amendments made: 42, in clause 12, page 16, line 17, leave out
“as mentioned in subsection (1)(c)”
and insert
“in accordance with the conditions of an electricity licence”.
This amendment is consequential on amendment 41.
Amendment 43, in clause 12, page 16, line 22, after “distribution system” insert
“(and such an improvement may include changing the order in which connections are made)”.
This amendment clarifies that the purpose for which a direction may be given under clause 12 may include the making of changes to the order of the queue for connections to a transmission or distribution system.
Amendment 44, in clause 12, page 16, line 23, leave out subsections (4) and (5) and insert—
“( ) A direction under subsection (2) must describe the kinds of modification to be made by the person to whom it is given.”
This amendment inserts a new subsection which would mean that a direction made by the Secretary of State or the GEMA to the ISOP or an electricity distributor to modify an agreement must describe the kinds of modification required.
Amendment 45, in clause 12, page 16, line 38, at end insert—
“(7A) Before giving a direction under subsection (2), the relevant authority must consult—
(a) the person to whom it proposes to give the direction, and
(b) such other persons as the relevant authority considers appropriate.
(7B) Subsection (7A) may be satisfied by consultation carried out before the passing of this Act (as well as by consultation carried out after that time).
(7C) A relevant authority must publish details of any direction it gives under subsection (2) as soon as reasonably practicable after the direction is given.
(7D) A relevant authority may exclude from publication under subsection (7C) any information the publication of which would be likely to prejudice the commercial interests of any person.”
This amendment requires a relevant authority to carry out consultation before giving a direction under clause 12. It also requires a relevant authority to publish any direction it gives under the clause.
Amendment 46, in clause 12, page 16, line 41, at end insert—
“(8A) The power to give a direction under subsection (2) may not be exercised after the end of the period of three years beginning with the day on which this section comes into force.”
This amendment ensures that the power to give a direction under clause 12 is time-limited in the same way as the power to make modifications to licences and other documents under clause 9.
Amendment 47, in clause 12, page 17, line 10, at end insert—
“(11) In Schedule 6A to the Electricity Act 1989 (provisions imposing obligations enforceable as relevant requirements)—
(a) in paragraph 4A (electricity system operator), after sub-paragraph (c) insert—
‘(d) section 12(8) of the Planning and Infrastructure Act 2025 (duty to comply with direction under section 12 of that Act).’;
(b) in paragraph 5 (distribution licence holders), after sub-paragraph (g) insert—
‘(h) section 12(8) of the Planning and Infrastructure Act 2025 (duty to comply with direction under section 12 of that Act).’”—(Michael Shanks.)
This amendment amends Schedule 6A to the Electricity Act 1989 in order to provide for enforcement of the duty to comply with a direction given under clause 12.
Clause 12, as amended, ordered to stand part of the Bill.
Clause 13
Managing connections to the network: strategic plans etc
Question proposed, That the clause stand part of the Bill.
Let me turn to the detail of the objects set out in the clause. It amends part 5 of the Energy Act 2023 to include a duty for NESO to have regard to designated strategic plans. It also amends the Electricity Act 1989 to place a duty on DNOs to have regard to any designated strategic plan, and adds a further exception to the duty on DNOs to connect in cases where it would not be in accordance with the designated strategic plans. The clause will support the implementation of ongoing connections reforms led by NESO and Ofgem, and will provide guidance and support for NESO and DNOs in making decisions on issuing new connection offers. I commend the clause to the Committee.
Question put and agreed to.
Clause 13 accordingly ordered to stand part of the Bill.
Clause 14
Consents for generating stations and overhead lines: applications
“(4) Any fees received by the Scottish Ministers under sub-paragraph (2)(d) may only be used to fund—
(a) consumer benefits packages, or
(b) local planning authorities.”
This amendment would ensure that fees collected by Scottish Ministers through applications can only be used for connected purposes, namely for consumer benefits or to support local authority planning departments.
The amendment was tabled in the name of the shadow Scotland Secretary, my hon. Friend the Member for West Aberdeenshire and Kincardine (Andrew Bowie). The Opposition absolutely understand the provisions of clause 14, and we broadly agree with it, but we think it could be strengthened to allow added scrutiny and consultation among those who will be most affected by some of the changes in the Bill, including members of the public and interested parties who will be affected by applications that go forward.
I have had a number of interactions with the Minister for Housing and Planning in Delegated Legislation Committees and on the Floor of the House about the Government’s moves towards planning fee reform. I know we are currently scrutinising the Minister from the Department for Energy Security and Net Zero, but we support planning fee reform and the Government’s move to ringfence fees within local authorities. Amendment 80 seeks to do something along those lines with regard to the Department for Energy Security and Net Zero and Scottish Ministers.
The amendment also refers to consumer benefits packages. We have been so prescriptive on that because of what I said at the beginning: those who are most affected by infrastructure projects are often those who live closest to them. I think the Minister accepted that when we discussed direct consumer benefits in other sections of the Bill. We heard evidence from Energy UK that it is absolutely committed to making sure that people who are affected by large-scale infrastructure projects should have greater benefit.
We have tabled the amendment to make sure that residents get that benefit, and to make sure that when fees come in, they are not kept by Scottish Ministers but are redistributed to local planning authorities, so that decisions can be made in a more streamlined, quicker way. That is what this Bill, and particularly this clause, could do for people living within those communities.
On the point about community benefits, the Scottish Government already have an established process. The 10-year onshore wind ban in England was not in place in Scotland, and the process of good practice for community benefits for onshore wind, for example, is already quite well developed. Processes are in place. Over the past 12 months, developers have offered more than £30 million in community benefits.
We are, of course, exploring all options and the Bill includes bill discounts for network infrastructure—we will come to that shortly—but we are open to much more on community benefits generally, because we agree that if communities are hosting nationally important infrastructure, they should benefit, as the hon. Member for Hamble Valley rightly said. However, for the reasons I have outlined—this is a devolved competence and not a matter for me as a UK Government Minister—we hope the hon. Gentleman will withdraw the amendment.
It is not just that the Government could be taking money from Scottish Ministers and giving it to local authorities under proposed new subsection (4)(a), but there is scope in the amendment for Scottish Ministers—the devolved Ministers—to be given the power to allocate consumer benefits packages where they think fit. That is strengthening the hand of devolved Ministers, not taking anything away from them. [Interruption.] The Minister says, “It doesn’t stop them.” No, but this would strengthen their hand. I think that giving devolved Ministers the power to give consumer benefits packages to Scottish people who are affected by infrastructure is a good thing.
I am not the intellectual powerhouse of the House of Commons, but even I can calculate that we would not win if we pushed this to a vote, so I beg to ask leave to withdraw the amendment.
Amendment, by leave, withdrawn.
“Consultation requirements (Scotland)
1B (1) Where an application is made to the Scottish Ministers for consent under section 36 or 37, the Scottish Ministers must provide for the holding of a public consultation.
(2) The Scottish Ministers may by regulations make provision about the holding of consultations.
(3) Regulations may include—
(a) the length of consultation periods in urban and rural areas;
(b) requirements on applicants to publish the projected local economic benefits and other specified information in advance of a consultation;
(c) requirements on applicants to respond to or demonstrate consideration of submissions to consultations.”
The amendment stands in the name of my hon. Friend for—
This simple amendment would introduce additional consultation requirements. It is in a similar vein to amendment 81, which, with your permission, Mr Twigg, I intend to move later. It would enable community and public consultations when an application goes forward. As I said in the last debate, I do not think it is unreasonable that, when an application is put forward, members of the public should have a public consultation to hear about the perceived benefits and to challenge the organisations trying to bring forward infrastructure projects. We must also accept that consultations can take effect in a number of ways, based on whether the infrastructure is being built in rural or urban areas.
This is a simple amendment that seeks to make sure that, when an application goes forward, Scottish Ministers have the powers that the Minister has outlined to ensure there is a public consultation, so that the people on the ground who are genuinely affected by such infrastructure projects have a say and see the transparency that we hope the Bill will put in place.
The 1989 Act—which we will come to shortly, in relation to the necessary updates to consents more widely—provides for the process of notification and objection at the application stage. This is very different from aspects of the planning regulations in England and Wales, in that there are already opportunities for consultations, but clause 14 creates a further power to make regulations to set out such matters relating to applications for consent, including a pre-application consultation requirement. That requirement will be set out in regulations rather than in primary legislation, but its purpose is to ensure that the application is proportionate, adaptable and future-proofed.
As much as I politically disagree with the incumbent Scottish Government, we have been working together incredibly effectively, since we came into government, on some key aspects. The reforms of the 1989 Act are a good example. To take the earlier point about the changing energy system, that Act was legislation for a different time, and the planning system in Scotland has not kept pace with the reforms in the rest of the United Kingdom. The reforms that we are proposing give Scottish Ministers a framework to introduce regulations to allow for a pre-application consultation process, and to give both communities and statutory consultees meaningful opportunities to influence applications and have a voice early in the process. For that reason, I see much of amendment 84 as replicating provisions already in the Bills, so I hope the hon. Member for Hamble Valley will withdraw it.
Amendment, by leave, withdrawn.
“(b) consider the objection and the reporter’s final report,
(c) hold a public hearing, and
(d) allow a period of one month to elapse
before determining whether to give their consent.”
This amendment would require the Scottish Ministers to hold a public hearing and allow one month to elapse before determining whether to give consent to an application for new generating stations or overhead lines under sections 36 or 37 of the Electricity Act 1989.
The amendment is in the name of the shadow Scottish Secretary and acting shadow Energy Secretary, my hon. Friend the Member for West Aberdeenshire and Kincardine, who I know the Minister would be delighted to hear from—[Interruption.] I heard the “boo”. Amendment 81 is similar to amendment 84 but more specific. I suspect that the Minister will come back with the same argument, so I will take only a short time on this. The amendment would require Scottish Ministers to hold a public hearing, and allow one month to elapse before determining whether to give consent to an application for new generating stations or overhead lines under sections 36 or 37 of the Electricity Act 1989.
Put simply, that would allow local residents the right to provide feedback on proposed infrastructure. I am sure that hon. Members from both sides of the House will agree that it is right that people can have their voices listened to by Scottish Ministers and the Scottish Government. The amendment would create one mechanism to ensure fairness in the planning system, by allowing not only the pre-application consultation but people to generally give feedback and a say, as they currently can in the English planning system. If the Minister is not minded to accept the amendment, I would be grateful if he wrote to me and the shadow Scottish Secretary, or acting shadow Energy Secretary.
I understand the point that the shadow Minister is making. For hon. Members who are not familiar with the Scottish system, a public inquiry can be triggered with one objection into the planning system. The public inquiry can take years to conclude and often is not reflective of actual community sentiment on a particular project. This system does not exist in any form anywhere else in the UK. The purpose of these consenting reforms is to deliver significant efficiencies in the consenting process, and to make decisions faster—not necessarily to make positive decisions faster, just to make decisions faster. Introducing another element that feels like the element that we are removing takes away from that.
As I have said previously, there are still significant opportunities for communities to participate in the process. One of the key aspects that we are introducing is the right of a reporter, who is an experienced specialist in planning and consenting, to consider representations about whether there should be a public hearing on a particular process. That reporter will then make the decision about whether it should go forward into a hearing session or a public inquiry. That is rather than what we have at the moment, which is an automatic trigger that holds up projects for a significant length of time.
I am always happy to meet with the shadow Scottish Secretary on a range of things. I am happy to engage with him, because I appreciate that his part of Scotland has a significant amount of network infrastructure being built; but for the reasons I have outlined, this amendment goes counter to our objectives, and does not sit with the reforms we are making to the Scottish planning system, as distinct from the planning system in England and Wales.
These provisions will help to unlock significant investment in Scotland. We heard last week how SSE’s programme of projects, which these provisions help to unlock, will lead to £22 billion of investment by 2030. That is the biggest investment we have seen in the north of Scotland since the second world war. Just think what we could achieve if we had a Labour Government in Scotland as well as in England.
The Minister is right to have worked closely with the Scottish Government on reforming the provisions, which in many cases predate 1989, because the 1989 Act was a consolidation. He is right to have worked productively with the Scottish Government, putting Scotland first, because that will give rise to significant investment and jobs—jobs for our young people and high-quality jobs—as well as access for the people of Great Britain to greater volumes of fixed-price electricity that is not subject to fluctuations in wholesale markets, as we have seen over the last few years.
Amendment, by leave, withdrawn.
Question proposed, That the clause stand part of the Bill.
Clause 15 stand part.
New clause 53—Reforms to consenting process for electricity infrastructure in Scotland—
“Where any reforms to the consenting process for electricity infrastructure in Scotland are proposed, the Secretary of State must ensure that such reforms—
(a) do not reduce requirements for community engagement or public consultation;
(b) include measures to address local concerns, environmental impacts, and impacts on all key sectors including but not limited to agriculture and tourism.”
New clause 54—Annual report on consents for electricity infrastructure in Scotland—
“(1) The Secretary of State must annually lay before Parliament a report on applications for consent for electricity infrastructure in Scotland.
(2) A report under this section must include—
(a) the outcomes of each application for consent relating to an energy infrastructure project in Scotland;
(b) evidence of community consultation undertaken in relation to each application and, where applicable, how consultation has influenced the design of the infrastructure to which the application relates; and
(c) estimates of economic benefits to local communities from the relevant project.”
I thank officials in my Department and in the Scottish Government for working closely and at speed, with a similar set of objectives and an open-book approach to making this work, to draft the measures in a way that works for all of us. It is a reset of the tone of how we work as two Governments.
On enabling the introduction of pre-application requirements, as the hon. Member for Hamble Valley referenced, in the Scottish legislation there are currently no steps to give the public an opportunity to engage as there are in the NSIP regime in England and Wales. This is about improving the quality and readiness of applications at the submission stage. It is important to say that this was driven by the views of Scottish Ministers, who said that they thought it was a useful process, but it will be directed in detail in regulations so that it can be updated and adapted to situations, unlike the process that we have in England and Wales at the moment, which has been held back and has added time and complexity to projects and not delivered what it was intended to do. It will give Scottish Ministers the powers to charge fees for pre-application services, enabling them to better support applicants in developing good-quality applications.
Secondly, the clause establishes a power to set time limits through regulations for key stages of the consenting process, which will support the timely determination of applications and bring down overall processing times. Thirdly, it will establish a proportionate process for responding to objections by relevant planning authorities through a reporter-led examination process. The reporter will choose the most appropriate procedure for gathering any further information they need to provide recommendations in a final report to Scottish Ministers. That may include inquiry sessions, where the reporter considers that that is the best approach to take to address particular issues. Such an approach is similar to the well-established process in which appeals in the town and country planning decisions are currently addressed.
Clause 15 enables regulations to be made that prescribe new processes to vary electricity infrastructure consents in Scotland after they have been granted. The clause addresses the current anomaly that there is no prescribed procedure for holders of overhead line consents to apply to Scottish Ministers for a variation to their consents. The current position forces consent holders to make full consent applications in order to authorise often very modest variations. The clause also allows Scottish Ministers to vary an existing generating station or overhead lines consent due to changes in environmental circumstances or technological changes. Such variations will be made with the agreement of the consent holder. Finally, the clause allows Scottish Ministers to correct any errors or omissions made in consents for generating stations or overhead lines.
I will come back to the new clauses later, but I want first to underline the importance of the consenting process. In Scotland, we generate a significant amount of electricity, and there are further projects in the pipeline, including both floating offshore wind and onshore wind. It is critical that there is an off-taker for that power in the rest of the UK, and that requires us to build significantly more network infrastructure to bring that clean power to where it is required. Although these changes to consenting relate to Scotland, they are of critical importance for the energy security of the whole United Kingdom.
As hon. Members will be aware, responsibility for the consenting process for electricity infrastructure in Scotland is devolved to Scottish Government Ministers. The Scottish Government are accountable to the Scottish Parliament—not the UK Parliament—for the decisions that they make, for the rationale behind them and for what information they choose to provide on consenting decisions. I am aware that the Scottish Government publish all their decisions, which includes information about what public consultations have taken place and consultations with community councils, for example.
It would be inappropriate and potentially duplicative for the Secretary of State to have such an obligation, but fundamentally, to come back to the point I made earlier, there is a particular concern about putting a statutory obligation on what is a devolved power when there is a democratic link between Scottish Ministers and their democratically accountable Parliament, which is the Scottish Parliament and not this Parliament.
I thank the Minister for Energy for being very gentle with me as well when discussing Scottish energy connectivity and Scottish planning. He will understand that beggars cannot be choosers on the number of MPs that we have, but being a Member for what is possibly the most southern part of the south coast that one can get bar the Isle of Wight, I am doing my best to discuss the Scottish planning system. I am grateful for the spirit in which he is responding to our new clauses and amendments. I am also grateful to his officials for their work, too.
I understand what the Minister is saying, and I know his reasons for refusing to accept previous amendments under clause 14, but these new clauses create a parallel system. He is absolutely right that Scottish Ministers are accountable to Scottish people and the Scottish Parliament, but Scottish Members of Parliament here are accountable to their constituents. The Secretary of State also has a role within this Parliament and within this UK Government. On new clause 54, the Minister is quite right to say that the Scottish Parliament already has that reporting mechanism, but I do not think that it is unreasonable that the Secretary of State should be able to do that for Scottish MPs here too; when we have questions to the Secretary of State for Scotland, we discuss UK legislation relating to Scotland.
Clearly, we are going to disagree on our approach to these two new clauses, but the reason for new clause 53 is exactly the same. I am surprised by the Minister’s reticence in allowing his Scottish colleagues to be able to have the same rights of scrutiny as Scottish MSPs. It is not an arduous new clause. It would not be arduous on the Government or the Scotland Office to produce those outcomes or statistics. It would not be arduous on the Scotland Office or the Department for Energy Security and Net Zero to provide evidence of community consultation, particularly when we have just discussed some of the amendments that the Opposition have tabled on community consultation.
It would also not be arduous for the Scotland Office—or whatever Department would be answering—to provide estimates of economic benefits to local communities. That is exactly why many members of this Committee who represent Scottish constituencies are here in this UK Parliament: to develop policy that brings economic benefits to local communities. The Minister needs to think outside the box and allow Scottish MPs from all parties in this House to have those rights to scrutinise, to develop the economic benefits to local communities. He should not feel so constrained by the Scottish devolved Administration; he should branch out, improve and increase the power of the Scotland Office or his Department, and allow Scottish MPs to have their say in this area of legislation.
It would ride roughshod over this Parliament’s fairly consistent support of devolution in the UK for us to now suddenly say that those Scottish Ministers are also accountable to another Parliament. I think that we agree on the nature of devolution in this country, although we may strongly disagree on the actions that devolved Governments take, but we cannot support the new clauses, for the reasons I have outlined. This is not about thinking outside the box; it is about recognising the role that the devolved system plays in our constitution. For those reasons, I will resist the new clauses.
Clause 14 accordingly ordered to stand part of the Bill.
Clause 15 ordered to stand part of the Bill.
Question proposed, That the clause stand part of the Bill.
The clause will create consistency in Scotland by making the challenge process the same for both onshore and offshore consents, and ensuring they are brought in a timely manner. A challenge will have to be brought within six weeks for onshore consents, as is already the case for offshore consents. This will bring the timescale for challenging large electricity infrastructure decisions into alignment right across Great Britain.
Clause 16 also amends the Electricity Act so that the six-week timescale for bringing a challenge commences from the publication of the decision by the Scottish Minister, instead of the date on which the decision was taken. This is a new requirement for both onshore and offshore, and is compliant with the Aarhus convention compliance committee’s recommendations relating to the timescale for challenging planning decisions. There is also a consequential amendment to the Town and Country Planning (Scotland) Act 1997 in respect of directions relating to deemed planning permission. I commend the clause to the Committee.
Question put and agreed to.
Clause 16 accordingly ordered to stand part of the Bill.
Clause 17
Applications for necessary wayleaves: fees
Question proposed, That the clause stand part of the Bill.
The objective of the change is to better resource the processing of necessary wayleave applications by the Scottish Government. It is important to act now.
I completely agree with what the Minister is saying about creating the necessary power, but will he commit to further discussions with his colleagues in the Ministry of Housing, Communities and Local Government so that we can ensure—not just in this Bill, but in future legislation—that where we expect a community benefit to derive from something that we decide on, it will be a consistent benefit across the UK?
I am not sure that I would say that consistency at all costs is the right approach. We created the Scottish Parliament and the Welsh Assembly so that they could make decisions locally that affected them in a different way. We have worked with the Scottish Government on these changes to make sure that there is a package of reforms to the consent arrangements under the Energy Act that relates to the planning system in Scotland as it currently is. It is not the same starting point as the system in England and Wales, so it is important to look at them separately. Nevertheless, I understand the hon. Gentleman’s point.
I return to clause 17. Fees are already charged in England and Wales for processing wayleave applications. I reiterate—this comes back to the point made by the hon. Member for Broxbourne—that the Scottish Government do not have the power in legislation to raise those fees. That power is reserved. The clause will give them that power.
We are very enthusiastic about clause 17—who would have thought it? To be clear about this point—I feel as if I am the only Scottish MP on this Committee, but I am not—when this Government increase spending in a particular area, that results in a budget transfer to the Scottish Government, the Welsh Government and the Northern Irish Executive, which they can spend on whatever they see as their local priorities. An increase in NHS spending in England does not lead to the exact same in Scotland. We will not bind the hands of every single decision that is made in this case. This is about conferring a power on Scottish Government Ministers to set and charge fees to electricity network operators for necessary wayleave applications in Scotland.
“The objective of this change is to better resource the processing of necessary wayleaves applications by the Scottish government.”
The Minister is therefore directing the Scottish Government to spend the money that they get in through this process on that planning process. How is that different from amendment 80 which we discussed earlier and the Government said they will not accept?
“consumer benefits packages, or…local planning authorities”.
Neither of those things is in the gift of the UK Government to direct the Scottish Government to do. Consumer benefits packages are ill-defined, if nothing else, but local planning authorities are democratically elected in their own right, and the Scottish Government make budget decisions to local government, separate from any budget decisions that the UK Government make to the Scottish Government. The two are not comparable in any way. In any event, the Committee has already voted down that amendment.
“The objective of this change is to better resource the processing of necessary wayleaves applications by the Scottish government.”
When I asked the Minister whether he had sought an assurance from Scottish Government Ministers, I was not asking him to instruct them. I asked him whether he had any information on the total amount of money that would be brought in, which I accept could vary. I perfectly understood and respected that answer, but in his second answer he said that he could not seek such an assurance because he does not want to direct Scottish Government Ministers or take power away from them. Given the objective set out in the explanatory notes, how can we have confidence—
I have said clearly, I think six or seven times now, that at the moment Scottish Government Ministers have no power to charge for the processing of wayleave applications. The clause will give them the power to do so. Of course, I would hope that those funds will be spent on the planning system, or whatever it might be, but I am not going to bind their hands and evaluate the success or otherwise of that in this Committee. The two issues are quite separate.
“is to better resource the processing of necessary wayleaves applications by the Scottish government”
while claiming that he does not have the power to ensure that it happens?
I am not trying to be difficult. The Minister is doing a very good job of outlining the clauses, but he has said several times in response to my hon. Friend the Member for Broxbourne—not just in relation to amendment 81, which was not accepted, but in relation to the clause—that he does not have the power to direct Scottish Government Ministers. All I am asking is why he set out the objective of the change in his approved explanatory notes if he cannot make it happen.
I am not asking the Minister to strengthen the legislation; I asked whether he has sought reassurances from Scottish Government Ministers that that is what they will do with the extra income from the measures. He answered that he did not want to force them. That was not the question. All I am asking—he is welcome to intervene on me—is whether he has had a conversation with Scottish Government Ministers about whether they will use this income for the purposes that his legislation has set out.
I do not know how familiar the shadow Minister is with the devolution legislation in the United Kingdom, but I gently say that this Parliament gives the devolved Administrations power to raise a whole series of taxes, charges, levies, fines and various other things. We give that power to those devolved assemblies; we do not then tell them exactly how to spend every single penny of that money. This is another example of that. It is a perfectly common thing in the devolution settlement.
I hope that when it comes to other clauses, UK Government documents will be very clear about the aims, ambitions and outcomes of what they will do because what we have seen this afternoon has been questionable. The UK Government are setting an objective, with no way to actually achieve it.
I urge the Minister, on behalf of my hon. Friend, to please come back to the Committee with that assurance. For those listening to this debate who expect that the funds raised will be spent on the purpose that the Minister has told the Committee they are intended for, that assurance needs to be there.
We will not push this to a vote because, as I have outlined in a very long-winded and convoluted way, we support the clause, but I hope the Minister will take a firmer line in speaking to Scottish Ministers. Before he says this again, I am not asking him to direct those Ministers; he seems to have a preoccupation with me claiming that I want him to instruct Scottish Ministers to do certain things. I am asking him, within his role and remit as a UK Government Minister legislating to give those Ministers extra powers, to use the art of politics and diplomacy to make sure that the outcomes he wants, as per the explanatory notes of his Bill, are delivered for the people affected by his changes.
Question put and agreed to.
Clause 17 accordingly ordered to stand part of the Bill.
Clause 18
Regulations
Question proposed, That the clause stand part of the Bill.
Clause 19 stand part.
Schedule 1.
Clause 19 introduces schedule 1, which makes amendments to the Electricity Act 1989 consequential to the amendments made by clauses 14 to 18. It also makes some minor amendments relating to consents for electricity infrastructure in Scotland. These amendments are made to sections 36, 36B, 36C and 37 of and schedule 8 to the 1989 Act. Schedule 1 is needed to ensure the Bill’s consistency and clarity in relation to the 1989 Act. Some changes are needed to ensure that the new Scottish consenting reforms can function as intended. Some of the clarifications are needed because the 1989 Act was originally drafted prior to the Scotland Act 1998, which created the Scottish Parliament. Given the number of changes made to the 1989 Act in relation to Scotland, it is necessary to update outdated references in legislation to ensure that such references are clear and consistent.
The consequential amendments cover three main aspects. First, as clause 14 amends schedule 8 to the 1989 Act to allow the Secretary of State or Scottish Ministers to make regulations about time limits for various parts of the consenting process, the amendments clarify how this relates to Scottish Ministers obtaining advice from the Scottish Environment Protection Agency. Secondly, as clause 14 amends schedule 8 to the 1989 Act to allow the Secretary of State or Scottish Ministers to make regulations about applications made to Scottish Ministers, amendments have been made so that proposed new paragraph 1A will apply only to applications made to the Secretary of State, not to those made to Scottish Ministers.[Official Report, 12 May 2025; Vol. 767, c. 2WC.] (Correction)
Thirdly, there are clarifications to reflect the new processes for variations of consents and the new procedure following objection by the relevant planning authorities for consents under sections 36 and 37 of the 1989 Act. In addition, the minor amendments include those to reflect previous transfers of functions to Scottish Ministers, and some references to the water environment regulations are updated to refer to the most recent version.
As I have said, this is a very technical clause. I look forward to having slightly less debate on it, unless there are any questions.
Question put and agreed to.
Clause 18 accordingly ordered to stand part of the Bill.
Clause 19 ordered to stand part of the Bill.
Schedule 1 agreed to.
Clause 20
Environmental impact assessments for electricity works
Question proposed, That the clause stand part of the Bill.
As part of the consenting process for electricity infrastructure in Scotland, Scottish Ministers are required to assess the likely significant environmental effects arising from a proposed EIA development. Before the UK left the European Union, Scottish Ministers and UK Government Ministers had concurrent powers, under the European Communities Act 1972, to make regulations for electricity works EIAs. However, although the EIA regulations remained in force as assimilated law after the European Communities Act was repealed, the result is that neither Government have the power to amend them.
Earlier on, we said that we would amend legislation through the Bill to remove that process in England. Given the intention to effectively introduce a top-quality process for applications to be considered in Scotland, does the Minister agree that there is an element of contradiction in that, in the same piece of legislation, we are seeking to remove many of the equivalent processes in England?
This particular clause is even more narrow than the hon. Member recognised. It is simply about the assimilated regulations. I have been in a number of Delegated Legislation Committees where we have discussed some of the unintended consequences, as we obviously assimilated thousands of different pieces of legislation into UK law. As I say, the result was that neither the UK nor the Scottish Government currently have the power to amend these regulations, which is a ludicrous position for us to be in. This clause is narrow in scope, and I do not think it has quite the reach that the hon. Member is suggesting.
Question put and agreed to.
Clause 20 accordingly ordered to stand part of the Bill.
Ordered, That further consideration be now adjourned. —(Gen Kitchen.)
PIB71 Joint submission from EVA England, New Automotive, The REA, and Kerbo Charge
PIB72 London Councils
PIB73 Wildlife and Countryside Link
PIB74 The Housing Forum
PIB75 Solar Energy UK
PIB76 NatureSpace
PIB76a Statement from NatureSpace regarding KC opinion on Part 3 of the Planning and
Infrastructure Bill
PIB76b NatureSpace: Two amendments to strengthen Part 3 of the Planning and
Infrastructure Bill
PIB77 Environmental Services Association
PIB78 Institution of Civil Engineers
PIB79a Friends of the Lake District (on Part 3 of the Bill)
PIB79b Friends of the Lake District (on Parts 2 and 5 of the Bill)
PIB80 Manchester Social Housing Commission
PIB81 Renewable Energy Association (REA)
PIB82 Environment Bank
PIB83 Adfree Cities
PIB84 Sequence (Iver) UK Ltd
PIB85 Freshwater Habitats Trust
PIB86 Renewable Power Capital
PIB87 Surrey Dormouse Group committee
PIB88 British Chambers of Commerce
PIB89 Retirement Housing Group
PIB90 Fastned
PIB91 Zurich UK
PIB92 RenewableUK and Scottish Renewables
PIB93 Local Government Association