PARLIAMENTARY DEBATE
HS2 Update - 17 July 2017 (Commons/Commons Chamber)
Debate Detail
Today marks a major milestone in the Government’s plans to deliver High Speed 2. High Speed 2 will deliver economic growth across the United Kingdom. It will provide the rail network with the capacity we need for the next century, faster journeys and better connections between cities across the UK.
As announced to the House this morning, we will be awarding stage 1 of the main works civil engineering contracts for the phase 1 route from London to Birmingham. This stage primarily covers design and pre-construction activities, although it is worth saying that the initial works have already begun. We expect these contracts to be signed by the end of this month after the completion of the mandatory standstill period. The expected total value of these contracts covering stages 1 and stage 2, which is the full construction phase, is £6.6 billion. They will support around 16,000 jobs across the country and are expected to generate around 7,000 contract opportunities in the supply chain, of which I expect around 60% to go to small and medium-sized enterprises. I have also confirmed the shortlists for the station design contracts and Euston master development partner procurements.
As well as that announcement, today I am introducing the phase 2a High Speed Rail (West Midlands - Crewe) Bill to the House. This seeks the powers to construct HS2 from the west midlands to Crewe so that this important section, which links up to the west coast main line just south of Crewe, can open in 2027.
The design of the route set out in the Bill is largely as announced in 2015. However, there are three refinements I have decided to make, following consultation last year. I have decided to move the connection to the west coast main line and the start of a tunnel in Crewe further south. I have also decided to move the construction railhead, and subsequently the infrastructure maintenance facility for this part of HS2, from the Basford area near Crewe to a location near Stone. I am very sensitive to the impact that that could have on the local community, which my hon. Friend the Member for Stone (Sir William Cash) has diligently drawn to my attention, but I believe this site is a better location from which to construct and maintain phase 2a. The new location near Stone is strategically located midway along the phase 2a route, which means that it can support construction activities heading north and south simultaneously, offering significant programme and construction benefits. Of course, the site at Stone benefits from good transport links, with access to the M6 and the existing rail network right at that location.
In Crewe, moving the railhead from the Basford area avoids planned housing regeneration in that part of Cheshire. It also negates the need for maintenance loops at Pipe Ridware, thereby reducing impacts along the phase 2a route. It is worth saying that that area of Basford is one of Cheshire’s most significant economic development and housing development sites, and I have been very sensitive to that. The construction railhead and infrastructure maintenance facility have been carefully designed so as to minimise impacts locally, particularly on the community of Yarnfield. Having heard local concerns, I have made sure that Yarnfield Lane will remain open.
In preparing the Bill, HS2 Ltd has sought to minimise impacts on the environment and on communities. Following the deposit of the Bill, there will be a consultation on the scheme’s environmental statement. That will provide the opportunity to comment on the environmental effects of the proposed phase 2a scheme and the reasonable alternatives considered and reported by HS2 Ltd. The process will result in a report from an independent assessor, which will be provided to all Members of the House before Second Reading.
Turning to Crewe, the HS2 business case has always included two trains per hour stopping at Crewe. The phase 2a Bill includes the interventions needed to support that, but I know that there is a strong ambition to achieve even more. Today, I am therefore launching a consultation on options to develop a Crewe hub. This work shows how such a service pattern could support an HS2 service to Stoke-on-Trent and bring benefits to places like Chester, north and south Wales, Shrewsbury and Derby. Future decisions will be subject to affordability and value for money. Funding the broader vision for a Crewe hub will require national and local government to work together, but I believe that there is the potential to deliver even more benefits.
Finally today, I am announcing my decision on the outstanding sections of the phase 2b route to Manchester and Leeds, which we consulted on last year. After carefully considering the responses to the consultation, I have decided to confirm the following changes to the route. The western leg rolling stock depot will move from a site near Golborne to a site north of Crewe. That site will be included in the full environmental assessment being undertaken for the whole route and I will look carefully at that assessment.
A 26 km section of the route in the Middlewich and Pickmere area of Cheshire will change and be raised as it passes through the Cheshire salt plains, to avoid brining and gas storage infrastructure. The approach to Manchester Piccadilly station will be adjusted to improve operational efficiency and reduce impacts on residential areas and a primary school. The route near East Midlands airport will now closely follow the eastern side of the A42. This avoids tunnelling under the airport and reduces the impacts on some communities. At Long Eaton, after much consultation with the local community, the route will pass through the town on a high viaduct.
The route in South Yorkshire will be the route we consulted on in 2016, which in part follows the M1 and M18, and serves Sheffield city centre via a spur from the HS2 line. I am also asking HS2 Ltd to take forward the provision of a northern junction back on to HS2, giving a city centre to city centre connection between Leeds and Sheffield in less than 30 minutes. That is very important for the development of Northern Powerhouse Rail. We will also continue to work on a possible parkway station.
Finally, I have decided not to proceed with the proposed change of route to the east of Measham. Instead, I am confirming a modified version of the 2013 preferred route to the west of Measham. In Measham itself, the route is moved approximately 80 metres and the viaduct extended to mitigate commercial property impacts. I have heard the concerns raised by local communities about the proposed eastern leg rolling stock depot at Crofton. HS2 Ltd believes it has found a better option, on which I am now consulting, which is east of Leeds in the Aire valley, adjacent to the M1 on a brownfield site.
I intend to bring forward a third hybrid Bill for phase 2b in 2019. In preparation for that Bill, HS2 Ltd is today launching a consultation on the technical scope and methodology to be used in the environmental and equality impact assessments.
Today’s decisions bring certainty for communities who have been unsure of the route for some years. I am updating the safeguarding directions for the phase 2b route to protect the land required for the construction and operation of the line. I can also confirm that the same range of property schemes currently operating for phases 1 and 2a will be available for phase 2b. This goes over and above what is required by law and gives assistance to those along the line of the route. I have also made amendments to some of the detailed urban/rural boundaries for phase 2b and to the treatment of properties around tunnel portals.
A report published today by property specialists Carter Jonas tells us that the particular circumstance of the Shimmer estate development in Mexborough, South Yorkshire means that this package may not allow some homeowners to acquire a similar property in their local area. In the light of the report’s findings, I therefore also confirm that the Government will ensure that Shimmer homeowners can secure a comparable home, as referred to in my summary document “High Speed Two: From Concept to Reality”, which is also being published today. That is really important.
We need HS2. Since privatisation, the number of passenger journeys on our railways has doubled. It has nearly tripled on the key west coast inter-city corridor. We cannot continue to rely on the legacy of our Victorian forebears, far-sighted though they were. By providing new routes for inter-city services, HS2 will free up space on our existing railways. It will reduce overcrowding and allow options for more varied and frequent services, including for places that currently do not have a good connection to London. This released capacity could allow more freight trains. It could also more than double the current number of peak-time seats on busy services from Manchester Piccadilly towards Stoke and Crewe, and from Leeds towards Wakefield. It has the potential to almost double peak seats from London to Peterborough and east coast destinations further north.
Any significant investment needs to offer good value for money, as HS2 does. Today I am publishing the updated business case for phase 2, which shows that, including the wider economic benefits, the full HS2 network will create £2.30 of benefit for every £1 spent. We want to make the most of our investment in HS2. When phase 1 becomes operational, HS2 trains will run to Manchester, Liverpool, Preston, Warrington, Wigan and Glasgow. Phase 2 will further reduce journey times between London and Glasgow and Edinburgh to around three hours and 40 minutes. To my Scottish colleagues, let me say that we will continue to work with Transport Scotland and Network Rail to look at the best ways of further reducing times, towards an ultimate ambition of a three-hour journey time between London and Scotland. We are also looking at opportunities to use HS2 to support Northern Powerhouse Rail and Midlands Connect.
Finally, I know that today’s announcement will not be welcome news for those living along the line of the route. There will be concern about how HS2 will affect their homes, communities and businesses. That, sadly, is inevitable if we are going to do big projects of this kind for our nation, but I am determined that we will engage extensively with everyone affected and that we will show fairness, compassion and respect. All the products mentioned today are in the Libraries of both Houses.
Our plan for Britain is a plan to build a stronger, fairer country, with an economy that works for everyone—one in which wealth and opportunity are spread across the country and we are set up to succeed in the long term. Investment in economic infrastructure is a key part of this. HS2 will be the new backbone of the UK rail network. It will transform a rail network built for the 19th century into one designed for the 21st century. It will increase capacity and connectivity across our rail network, bring our country closer together and support economic growth. The benefits of HS2 will be felt across the whole of the United Kingdom. I commend the statement to the House.
Perhaps the Secretary of State will be kind enough to explain what happened earlier today, given the widespread trailing of an oral statement on the anticipated announcement and the House’s subsequent disappointment at initially being asked to settle for a written statement, until such time as the outcry seemingly reached the Transport Secretary’s ears and his somewhat belated appearance in the Chamber tonight.
Labour has consistently supported HS2 and the attendant benefits it will bring—indeed, we were its initial proposer in 2009—but that support brings with it many questions. On the construction, there are concerns that companies selected to do the work were previously involved in the practice of blacklisting workers.What assurances can the Secretary of State give that no such practices will be tolerated in the delivery of HS2? Far too often in the case of significant projects in recent times, overseas contractors—and several have been awarded contracts here—have brought in their own labour, and have recruited exclusively from jurisdictions outside the United Kingdom. HS2 clearly represents huge employment and career opportunities for apprentices and established workers alike. Can the Secretary of State guarantee that the practices we have seen in the construction industry that have excluded British workers from UK projects will not be allowed to obtain in the construction of HS2?
There are also concerns about the financial health of Carillion. What measures has the Secretary of State put in place to ensure that any financial instability of any of the contractors will not delay or add to the cost of the project? He said in evidence to the Treasury Committee that it was not his job to monitor conflicts of interest in the delivery of HS2, but given the revelations of the revolving door between HS2 and the engineering firm CH2M, does he accept that he does, in fact, have such an obligation if the public are to have confidence in the arrangements between HS2 and the contractors?
What assurances and guarantees can the Secretary of State give that the total overall cost will not exceed the stated £55.7 billion, and will not spiral, as has been alleged in certain quarters? In one of the many documents published today, we are told that in adopting the M18 route in south Yorkshire, although HS2 Ltd has included in the costs estimate the delivery of a junction north of Sheffield and back to the HS2 main line, it has not costed electrification of the midland main line between Clay Cross and Sheffield Midland, or from Sheffield to the north. Does the Secretary of State intend the line to be electrified in readiness for HS2—and if so, when—or is he working on the basis that trains to Sheffield will be bimodal, and the line will remain unelectrified?
Will the Secretary of State provide further and better particulars of his proposals and preferences in respect of potential parkway stations? Will he also provide an update on the progress of the northern east-west rail and the extension to the north-east—“Crossrail for the north”—and its connection with HS2, and on what discussions he has had with Transport for the North in that regard? Finally, will he reassure the House that his announcement about progress on HS2 will not be followed by an announcement of yet further delays to electrification of the trans-Pennine route?
As I said a moment ago, I am very pleased to be here now. I should have preferred to be here earlier, but, as I said, it is sometimes a case of cock-up rather than conspiracy.
Let me begin by saying something about the construction contracts. We have contracted a range of significant British companies as part of the awarding of contracts today. A range of consortiums is participating, and many of them are already an integral part of Crossrail, which is our biggest engineering project—and the biggest in Europe. We have a good team of UK and international organisations that are used to working as a team to deliver big infrastructure projects. However, the assurance that I give the hon. Gentleman and the House is that, as I have made clear all along, the companies that win contracts for HS2—whether construction, design or, ultimately, rolling stock contracts—will be obliged to make a commitment to leave a lasting skills footprint. That means apprenticeship programmes and skills development, and I think the two high-speed college campuses that we have established in Birmingham and Doncaster will help to develop real expertise for the future.
The hon. Gentleman talked about Carillion. Carillion is a big UK construction business which is clearly going through a troubled time, and we all hope that it will pull through, because we want to see British business succeed. However, I can tell him that Carillion is part of a consortium in which all the organisations involved have committed to delivering their part of the contract, and I am confident that whatever the position in respect of Carillion, that consortium will deliver the results that we expect.
The hon. Gentleman talked about conflicts of interest and CH2M. As he is aware, it pulled out of that particular contract. I have every intention of ensuring that we have proper behaviour by companies in future; they will be unable to continue to work for us if they do not do the right thing.
The hon. Gentleman asked about the total cost of the project. Over the past 24 hours there have been some wild rumours about the cost, based on people who are not involved in the project putting a finger in the air. I simply remind the House that it is incredible, inconceivable and simply nonsense to suggest that HS2 will cost five times the amount of HS1 per mile. This project has a total cost attached of £55.7 billion. It is currently on time and on budget, and I expect it to stay that way. In this country we have experience of major projects, such as Crossrail and the Olympics, and we have been pretty good at delivering on time and on budget. I am sure that we will carry on doing so.
The hon. Gentleman asked about electrification of the M18 route. I can confirm that the route from Sheffield Midland north to Leeds will also be electrified to ensure that through services can run to Leeds. That link is also an important part of northern powerhouse rail. On parkways stations, work is continuing to look at the best options. With regard to the whole northern powerhouse rail project, I am waiting for Transport for the North to bring forward its proposals. With regard to trans-Pennine modernisation, nothing has changed.
I have consistently spoken in favour of High Speed 2, so long as Scotland is not excluded. I therefore welcome the Secretary of State’s restatement of the aspiration to have a three-hour journey time to Scotland. By contrast, my scheduled journey time today from Glasgow to London was four and a half hours—50% longer—which shows the real benefits that high-speed rail could bring. However, my understanding is that when high-speed trains run on the existing network north of Crewe they will actually run slower than my train did today. Can he confirm that, and if so, what will be done to look at the rolling stock to try to improve that speed?
Can the Secretary of State also advise on the estimated journey time of three hours and 45 minutes when high-speed trains start running to Glasgow, and how much that reduced journey time will be due to the reduced number of stops? Can he confirm in which investment periods upgrades to the west coast main line north of Crewe will take place? A previous KPMG report highlighted some possible negative impacts in Scotland, including a predicted £220 million drop in economic output in Aberdeenshire, if high-speed rail continues without including Scotland. Has he updated the review of those figures, and if not, why was the Secretary of State for Scotland able to tweet that today’s announcements on high-speed rail will bring economic benefits to Scotland?
I want to reiterate the concerns about Carillion, which now has the prefix “troubled” when it is mentioned in the newspapers. What engagement has there been with Scottish companies for bids? Will the Secretary of State uphold his predecessor’s commitment that offsite constructions will definitely be in Scotland? With regard to today’s announcement about the Crewe hub, can he confirm that it will not be to the detriment of services to Scotland or the funding of upgrades north of Crewe? Finally, I offer the small reminder that the devolution of Network Rail to Scotland would allow the Scottish Government to progress upgrades north of the border much quicker.
Service patterns for the future will ultimately depend on timetabling much closer to the time, but I expect to see genuine benefits for people across the network served by HS2 in Scotland, the north of England and north Wales. This investment will lead to better services all around the country. It will deliver better services from the east coast ports; I see my hon. Friend the Member for Brigg and Goole (Andrew Percy) in his place, and there is a real opportunity to open new routes to those ports on the existing east coast main line. There is a real opportunity to improve the services to cities off the HS2 network that will be served by HS2 trains—Glasgow, Edinburgh, Newcastle, Preston, Liverpool. This will benefit people on a very widespread basis.
The hon. Gentleman talks about a drop in economic activity. This is a huge project that will feed the supply chain all around the United Kingdom. So this will be good news for Scottish business, good news for English business, good news for Welsh business and good news for Northern Irish business. This is good news for the United Kingdom as a whole.
The hon. Gentleman talked about Carillion. I would hope that everyone in this House would share my ambition that a British company going through a troubled period pulls through and has a stronger future, and I see no reason, when it is part of a consortium that has agreed collectively to deliver for us, why we should hold its current position against it and take away an opportunity that might help that business recover.
Lastly, I do not see how delivering on a Crewe hub that will help connections to north Wales, for example, should in any way disadvantage Scotland.
I also express my thanks to my right hon. Friend for the constructive way in which she has approached the discussions. She is right to say that the regeneration of the Toton site will make a real difference to the east midlands. It is a huge waste at the moment, and I hope to see the project breathe life back into it.
I have heard a lot over the past 24 hours about numbers. The project has a budget of £55.7 billion. This country has a decent track record of late of delivering projects on time and on budget, and I am confident that that is what will happen this time. As far as I can see, those who appear to be telling a different story have no involvement in the project and little direct knowledge of it.
I appreciate that the Secretary of State is seeking to be decisive, but my constituents in Tatton are deeply concerned by what they hear in the media. Will he ensure that my constituents, and I as their representative in Parliament, will be fully involved in the decisions that will hugely affect them, and that he and High Speed 2 will not ride roughshod over their legitimate concerns?
The Shimmer estate at Mexborough was mentioned earlier, and it is estimated that quite a number of houses there will have to come down. On the Broadlands estate at Bramley in my constituency—the estate I live on—at least 81 houses are within 100 metres of HS2, and on the other side is the M18 motorway. The route will be devastating for the constituency, yet HS2 always denies the number of houses that will be affected.
Secretary of State, if HS2 is saying that fewer houses will be affected on the Meadowhall route—I defended that route, which goes through my constituency, too—it is not the truth. I put it in Sir David Higgins’s hands months ago, and he still will not give me a figure for what would happen at Meadowhall.
May I say to my right hon. Friend the Secretary of State that the jobs bonanza that will come with moving the depot to Stourton is hugely welcome to Leeds, the Aire valley and my constituents? On the conversation that I had with the Exchequer Secretary to the Treasury, my hon. Friend the Member for Harrogate and Knaresborough (Andrew Jones), and on the tunnelling that will take place under Woodlesford, has the Secretary of State given consideration to the site on which the depot will sit? Has he considered putting all the tunnelling equipment and the spoil on brownfield land, so as to minimise the disruption to my villages of Woodlesford and Oulton, and the traffic around them, during construction?
Huskisson and his predecessors will have heard many of the concerns about the Victorian railway network as proposed about this village, that village or the other. He and his colleagues wisely proceeded, and the benefits of economic growth and job creation from the Victorian rail network were very clear. Will my right hon. Friend reflect on the important statement made by the shadow Secretary of State? Notwithstanding the parliamentary arithmetic, he provided the support of the official Opposition for this project, understanding and realising the important economic benefits that the proposal brings to the whole United Kingdom. That is to be underscored and welcomed at any time, but particularly in a post-Brexit environment.
I am grateful for the cross-party support. I know that individual Members on both sides of the House have constituency problems or principled concerns about the project, but the fact is that the project was proposed by both parties back at the end of the last decade. It was first put on the table by the last Labour Government and has commanded cross-party support. I hope that will continue because both parties understand the benefits the project can bring to the whole country. I hope we can work together to ensure that we deliver this Bill, the next one and the whole project. I am grateful to the shadow Secretary of State for the support he has given to it.
The Secretary of State has said that there “could be” support for having HS2 in Stoke-on-Trent. That is not a commitment that my constituents can base any real decisions on. Could he confirm that, as was asked by my hon. Friend the Member for Stoke-on-Trent North, the number of fast trains running from Stoke-on-Trent to London—London, and not another part of the region —will not be diminished by this announcement? Could he also confirm that capacity for freight transport on the west coast main line will not be diminished through making space for classic-compatible trains? As the hon. Member for Stafford (Jeremy Lefroy) asked, could the Secretary of State make it clear that the pain that Staffordshire feels will have economic gains, because without that he will struggle to get our support in the vote?