Rail Timetabling - 4 June 2018 (Commons/Commons Chamber)
Debate Detail
I want to be absolutely clear: passengers on these franchises are facing totally unsatisfactory levels of service. It is my and my Department’s No. 1 priority to make sure that the industry restores reliability for passengers to an acceptable level as soon as possible. I assure the passengers affected that I share their frustration about what has happened, and that I am sorry that this has taken place.
The timetable change was intended to deliver the benefits to passengers of major investments in the rail network, meaning new trains, including all trains on the Northern and TransPennine Express networks, being either new or refurbished; the great north rail project infrastructure upgrades worth well over £1 billion, such as those at the Ordsall Chord and Liverpool Lime Street; and in the south-east, through the Thameslink programme, new trains and improved stations, including London Bridge and Blackfriars.
The huge growth in passenger numbers in recent years demanded expanded routes, services and extra seats, but this timetable change has resulted instead in unacceptable disruption for the passengers who rely on these services. The most important thing right now is to get things back to a position of stability for those passengers, but it is also vital to understand what has happened and why we are in the situation we are in today. The circumstances of the failures are different on the Northern and GTR networks.
The investigations that are being carried out right now are providing more information about what has gone wrong, but it is worth being clear that the industry remained of the view until the last moment that it would be able to deliver the changes. That is the bit that everyone will find hard to understand and it is why there has to be a proper investigation into what has taken place.
On Northern, which is co-managed through the Rail North Partnership by Transport for the North and my Department, early analysis shows that the key issue was that Network Rail did not deliver infrastructure upgrades in time, in particular the Bolton electrification scheme, with damaging consequences. This forced plans to be changed at a very late stage, requiring a complete overhaul of logistics and crew planning. The early analysis also shows that on GTR’s Thameslink and Great Northern routes, the industry timetable developed by Network Rail was very late to be finalised. That meant that train operators did not have enough time to plan crew schedules or complete crew training, affecting a range of other complex issues that impact on the service on what is already a highly congested network.
It is also clear to me that both Northern and GTR were not sufficiently prepared to manage a timetable change of this scale. GTR did not have enough drivers with the route knowledge required to operate the new timetable. Neither Northern nor GTR had a clear fall-back plan.
In GTR’s case, the process of introducing the new timetable has been overseen for the past two years by an industry readiness board, comprising some of the most senior people in the industry, which told me it had been given no information to suggest the new timetable should not be implemented as planned, albeit with some likely early issues as it bedded down. This body was set up specifically to ensure that all parts of the rail network—Network Rail, GTR, other train operators—were ready to implement these major timetable changes. It should have been clear to it that some key parties were not ready. It did not raise this risk.
The Department received advice from the Thameslink readiness board that, while there were challenges delivering the May 2018 timetable—namely, the logistics of moving fleet and staff—a three-week transition period would allow for minimal disruption. My officials were assured that the other mitigations in place were sufficient and reasonable. Indeed, as few as three weeks before the timetable was to be implemented, GTR itself assured me personally that it was ready to implement the changes. Clearly this was wrong, and that is totally unacceptable.
The rail industry has collectively failed to deliver for the passengers it serves. It is right that the industry has apologised for the situation we are currently in and that we learn the lessons for the future, but right now the focus should be on restoring the reliability of its service to passengers. This morning, I met again with chief executives of Network Rail, GTR and Northern—the latest in a series of meetings that I and my Department have been holding with these organisations—and the rail Minister has today been to Network Rail’s control centre at its Milton Keynes headquarters. We have made it clear to them all that the current services are still not good enough. I have also demanded that Network Rail and the train operator work more collaboratively across the industry to resolve the situation, where necessary by using resources from other train operators to support the recovery effort. Officials in my Department are working around the clock to oversee this process. We have strengthened resources in both the Department and Rail North Partnership, which oversees the Northern franchise, to hold the industry to account for improving services.
I would like to be able to tell the House that there is an easy solution or that the Department could simply step in and make the problems passengers are facing go away—if there were a way of doing so, I would do it without a moment’s hesitation—but ultimately the solution can only be delivered by the rail industry. These problems can only be fixed by Network Rail and the train operators methodically working through the timetable and re-planning train paths and driver resourcing to deliver a more reliable service. It is for such reasons that I am committed to unifying the operations of track and trains, where appropriate, to ensure that we do not encounter such problems in the future.
Northern Rail has agreed an action plan with Rail North Partnership that is focused on improving driver rostering so as to get more trains running as quickly as possible; rapidly increasing driver training on new routes; providing for additional contingency drivers and management presence at key locations in Manchester; and putting extra peak services into the timetable along the Bolton corridor. Work on this action plan has been under way for some time. They have also published temporary timetables that will be more deliverable and will give passengers much more confidence in the reliability of their service. This will mean removing certain services from the new expanded timetable while still ensuring an improvement in the total number of services run by Northern compared with before the timetable change. Alternative arrangements will be made for passengers negatively impacted by the changes. I believe that this temporary measure is necessary to stabilise the service and enable improvements to be introduced gradually.
On GTR, there are more services running on a day-to-day basis today than before the timetable change, while Southern and Gatwick Express services are performing well on some routes but not all. GTR is not currently able, however, to deliver all planned services on Thameslink and Great Northern routes. In order to give passengers more confidence, it is removing services in advance from its timetable rather than on the day and reducing weekend services to pre-May levels. These measures will be in place until a full re-planning of driver resourcing has been completed.
I would like to make it clear that, while I expect to see stable timetables restored on both networks in the coming days, I expect the full May timetable and all the extra trains to be introduced in stages over the coming months to ensure it can be delivered properly this time. Once the full service is operating on GTR, 24 Thameslink trains will run through central London every hour, and by next year, 80 more stations will have direct services to central London stations such as Farringdon, City Thameslink and Blackfriars. There will also be 115 new trains and more than 1,000 new carriages providing faster, more frequent and more reliable journeys for passengers.
On Northern, the great north rail project, an investment of well over £1 billion in the region’s rail network, will enable by 2020 faster and more comfortable journeys as well as new direct services across the north and beyond. By 2020, the train operators, Northern and TransPennine Express, will deliver room for 40,000 extra passengers, and more than 2,000 extra services a week.
That, however, is the future. What matters now is restoring a stable service for passengers today. I completely understand their anger about the level of disruption that the timetable change has caused in recent weeks. There must, of course, be a special compensation scheme for passengers on affected routes on both GTR and Northern. In the case of Northern, the scheme will be subject to agreement with the board of Transport for the North, although I doubt that the board will have a problem with it. The purpose of the scheme, which will be introduced and funded by the industry, will be to ensure that regular rail customers receive appropriate redress for the disruption that they have experienced. The industry will set out more details of the eligibility requirements, and of how season ticket holders can claim, but I think it is very important for passengers—particularly in the north, where disruption has been protracted—to be given entitlements similar to those conferred by last year’s Southern passenger compensation scheme. Commuters in the north are as important as commuters in the south, and they should receive comparable support.
It is clear to me that, aside from Network Rail’s late finalisation of the timetable, GTR and Northern were not sufficiently prepared to manage a timetable change of this scale, so today I am also announcing that work has begun to set up an inquiry into the May timetable implementation. It will be carried out by the independent Office of Rail and Road, and chaired by Professor Stephen Glaister. It is necessary to have a full inquiry, and Professor Glaister will lead one. The inquiry will consider why the system as a whole failed to produce and implement an effective timetable. Its findings will be shared as early as possible with me and with the rail industry, so that lessons can be learnt in advance of future major timetable changes. The final report will be published by the Office of Rail Regulation by the end of the year, but I want to see initial responses much sooner than that.
In parallel with the inquiry, my Department will assess whether GTR and Northern met their contractual obligations in the planning and delivery of the timetable change. It will consider whether the issues could have been reasonably foreseen and different action taken to prevent the high levels of disruption that passengers are experiencing.
In GTR’s case, the assessment will cover whether the operator had sufficient resources and skills to deliver the new timetable and whether drivers could have been trained in a faster and more effective way, and will examine the contingency and risk management arrangements currently in place. If it is found that GTR is materially in breach of its contractual obligations, I will take appropriate enforcement action against it. That will include using the full force of the franchise agreement and my powers under the Railways Act 2005, and consideration of how such a failure affects GTR’s eligibility to hold a franchise bidding passport. In the case of Northern, my Department will assess the operator’s planning, risk assessment and resilience in preparing for the May timetable change. Bearing in mind Network Rail’s failure to deliver infrastructure on time, we will hold the operator to the terms of its contractual obligations.
I will not be afraid to take enforcement action when it is necessary, but it is right to go through the process of the inquiry and to understand where fault truly lies. I will not hold back from taking appropriate action if the review finds that there has been negligent behaviour.
Given the importance that Members throughout the House ascribe to these issues, I have arranged for both Northern and GTR to come to the House this week to discuss with colleagues any specific issues that they wish to raise with the operators. I am also meeting Members on both sides of the House today to discuss the issues with them. I am incredibly frustrated that what should have been an improvement in services for passengers has turned into significant disruption, and I am sorry about the levels of disruption that passengers are experiencing. I am also sorry for the staff members who have been caught at the sharp end of these changes.
There clearly have been major failures that have led to the situation that we are in today. I am clear about the fact that the industry must and will be held to account for this, but my immediate priority is to ensure that we improve train services to an acceptable level as quickly as possible, and that will remain my priority.
It is said that Henry Kissinger once asked who he should call if he wanted to speak to Europe. The answer was not clear. Similarly, I would ask who I should call if I want to speak to the UK rail industry. Therein lies the heart of today’s problem and the whole rail debate more generally: no one will take responsibility for Great Britain’s rail industry. But, amid all the clamour, recriminations and buck-passing that characterise discussions about rail there is one person who is ultimately responsible: the Secretary of State for Transport, the right hon. Member for Epsom and Ewell (Chris Grayling). But he blames Network Rail for the timetabling failures. Yes, Network Rail has not delivered, but he seems to forget that, as a company limited by guarantee, Network Rail has one member: the Secretary of State for Transport—him. He is the man in charge—allegedly. The right hon. Gentleman might want to blame Network Rail, but it is he who has failed in his responsibility to oversee it; the buck stops with him. What is more, the right hon. Gentleman has burnt his bridges with the leadership of Network Rail, which can only have damaged his oversight of this process. Is not this a terrible failure of him and his role atop the system?
The Northern Rail and Thameslink contracts were awarded by the right hon. Gentleman’s Department to private operators. It is the job of his Department to ensure that the companies fulfil their contracts. Arriva and GTR have had years to prepare for these timetable changes; neither have trained enough drivers to deliver the timetable changes, yet the Department has failed to hold the companies to account. Can the right hon. Gentleman confirm that it is within the franchise agreement for Arriva to report directly to him on progress in recruiting and training drivers? Does not the buck, once again, stop with him?
GTR even had its own readiness board to implement the timetable changes, except that it was not ready; we could not make this up. Chris Gibb’s report on Southern exactly a year ago highlighted the issue of driver numbers as a major operational issue within rail. Why did the Secretary of State not take the report as an alert to review the availability of the train drivers who were needed across the country and do something about it? He says the Office of Rail Regulation will report on the failings by the end of the year, but, with the new timetable due in December, this will be too late. What confidence can we have that it will not be another shambles? Is not the reality that this Secretary of State has been asleep at the wheel and this is just the latest episode in a series of rail management failures on his watch?
The right hon. Gentleman is determined to cling on to the micromanagement of the railway when it suits him, but he will quickly point the finger of blame when things go wrong. He cannot have it both ways. The Secretary of State says he is sorry for the disruption passengers are facing. That is not good enough; he should apologise to passengers for his failures that have put their jobs at risks and played havoc with their family life.
The travelling public and the rail industry have no faith in this Transport Secretary to fix this situation. Were the Prime Minister not so enfeebled, she would sack him. If he had any concept of responsibility, he would resign. The Transport Secretary should do the right thing and step aside.
There are two specific points. On what we are going to do about the timetable in December, I have been very clear in the letter I sent to all colleagues last week that we are not going to do a major change of this kind again in the way that has happened in the last couple of months; it must be done in a more measured and careful way. We are already doing work now on how that timetable change should happen—how it should be modified—and the incoming chief executive of Network Rail, Andrew Haines, who I think will bring enormous experience to this, is the person who was responsible 10 years ago for the very successful timetable change on South Western. I have great confidence that as he comes into the organisation in the coming months, he will be able to put in place a plan for timetable change both at the end of this year and in the future that works better for passengers, who are the most important people in all of this.
The hon. Gentleman also asked me why we did not pay more attention to Chris Gibb’s report last year. Actually, we did. We appointed Chris Gibb chairman of the industry readiness board. Chris is one of the most experienced and respected figures in the rail industry, but that board still did not gather the scale of the problem that lay ahead when it last reported to me in May. Lessons have to be learned by the people on that board. We have to make sure that this cannot happen again, and everyone in the rail industry—and everyone in my Department, including me—is working to ensure that that happens.
Anticipating an article by Nigel Harris in Rail magazine, I would suggest that those who have power need to be accountable and those who are accountable need to have power.
Anyone who has no expertise should take advice from those who can make things better. That requires getting everyone—unions, managers and knowledgeable passengers —together to see how best we can get out of the hole we are in at the moment.
It is too bad, and it has been too bad for too long.
We know that late-running Network Rail projects reduced the time available for train operators to plan the new schedules, but what assessment has the Secretary of State made of his Department’s culpability in this, with regard to Network Rail? Despite assurances that all was well, it is now clear that there was no possibility of the timetables being capable of being operated in full from day one. Why did no one in the train operating companies, Network Rail or the Department for Transport ask for a postponement of the new timetable roll-out?
The Secretary of State has said that he will take the strongest enforcement action against GTR if it has broken its franchise agreement. Will that action be stronger than that taken against Virgin Trains East Coast, which has been allowed to walk away owing the Department for Transport billions of pounds?
What is the Secretary of State’s exact timeframe for resolving these timetable issues? He has mentioned putting in additional resources. What additional resources will be put in from his Department? What is he doing to ensure that the driver shortage is not met by poaching drivers from other franchises, which could have an impact on services elsewhere? On the question of compensation, what will he do to ensure that the rail industry does not recover the costs of compensation from other fare-paying passengers?
The Secretary of State continually highlights Network Rail failings, but when will he accept that he has responsibility and culpability for Network Rail and fall on his own sword? An apology is not good enough.
“We promised passengers a world class rail service that would make the Northern Powerhouse a reality—and I’m delighted”.
He also said that the new operator would
“bring the Northern Powerhouse to life.”
Such promises would be laughable, except that they are tragic, because my constituents cannot get into Manchester for their jobs, cannot get to hospital appointments and cannot return home to pick up their children from childcare places. Why will the Minister not take responsibility, stop passing the buck and fix this now?
“we are looking at understanding the root cause”,
it sounds as if it is running a seminar rather than a railway. Will my right hon. Friend get rid of these incompetents, now?
I ask the Secretary of State for two actions. First, he says that the emergency timetable that has been implemented today would take us back to pre-May levels. It is not doing so at all; it is actually worse. By the end of this week, can we please aim to have the pre-May timetable back in place? Secondly, we have heard about compensation for Northern passengers being akin to that of Southern last year. I have to tell the Secretary of State that the GTR performance up and down the line in my constituency is as bad, and we should be considered for the same levels of compensation.
If someone conspired to break into my garage and steal or immobilise my car, they would face the full force of the law. The Secretary of State’s Department has conspired with the railway companies in an incompetent manner to change the timetables, and despite repeated warnings from the Opposition, the companies went ahead with it. When will they face the full force of having their franchises stripped from them, or when will he be brave enough to face up to this and resign?
In the two years that the Secretary of State for Transport has been in post and I have sat on the Transport Committee, he has always been very honest, open and direct about the need for change. For any project management exercise to fail to get the sign-off from Network Rail and for it to find out only three weeks before, by which time it is too late to turn the oil tanker around, has got to be a spectacular failure. Who was the project manager and penholder for this exercise?