PARLIAMENTARY DEBATE
Energy Bill [ Lords ] (Sixth sitting) - 8 June 2023 (Commons/Public Bill Committees)
Debate Detail
Chair(s) Dr Rupa Huq, James Gray, Mr Virendra Sharma, †Caroline Nokes
Members† Afolami, Bim (Hitchin and Harpenden) (Con)
† Blake, Olivia (Sheffield, Hallam) (Lab)
† Bowie, Andrew (Parliamentary Under-Secretary of State for Energy Security and Net Zero)
† Britcliffe, Sara (Hyndburn) (Con)
† Brown, Alan (Kilmarnock and Loudoun) (SNP)
Clarkson, Chris (Heywood and Middleton) (Con)
† Fletcher, Katherine (South Ribble) (Con)
† Gideon, Jo (Stoke-on-Trent Central) (Con)
Jenkinson, Mark (Workington) (Con)
Levy, Ian (Blyth Valley) (Con)
McCarthy, Kerry (Bristol East) (Lab)
† Morrissey, Joy (Beaconsfield) (Con)
† Nichols, Charlotte (Warrington North) (Lab)
† Owatemi, Taiwo (Coventry North West) (Lab)
Shelbrooke, Alec (Elmet and Rothwell) (Con)
† Western, Andrew (Stretford and Urmston) (Lab)
† Whitehead, Dr Alan (Southampton, Test) (Lab)
ClerksSarah Thatcher, Chris Watson, Committee Clerks
† attended the Committee
Public Bill CommitteeThursday 8 June 2023
(Morning)
[Caroline Nokes in the Chair]
Energy Bill [Lords]
I understand that the Government wish to move a motion to amend the programme order agreed by the Committee on 23 May and amended on 25 May, to change the order of consideration of the provisions of the Bill.
Motion made, and Question proposed,
That paragraph 2 of the Order of the Committee of Tuesday 23 May (as amended on 25 May) be amended—
(a) by leaving out “132; Schedule 7; Clause 133; Schedule 8; Clauses 134 to 137; Schedule 9; Clauses 138” and inserting “131; Clauses 140”;
(b) by inserting, after “273;”, “Clause 132; Schedule 7; Clause 133; Schedule 8; Clauses 134 to 137; Schedule 9; Clauses 138 and 139;”. —(Andrew Bowie.)
While we are on matters of procedures, I also ask the Minister about his intentions for the new clauses tabled yesterday. They are clauses on the support of—
Question put and agreed to.
As has been discussed, the Government have kindly tabled a number of new clauses relating to Great British Nuclear and energy-intensive industry assistance. That brings to four the number of areas on which the Government have introduced new clauses while the Bill has been proceeding. This is beginning to resemble those episodes where people book a holiday in Spain, thinking they have a nice hotel, only to get there and find that it is a building site, with no rooms booked in sight.
That aside, given that the clauses have been tabled, it would be helpful to have an indication of when the Government intend to consider them. I say that because the Opposition need to properly scrutinise them, and may want to introduce amendments. The Minister will know that the deadline for tabling such amendments is today, so if the Minister was considering dropping those clauses into the Bill next week, that would obviously prevent us from tabling amendments in the usual manner. I would be grateful if the Minister clarified his intentions.
Clause 106
Setting of targets etc
Question proposed, That the clause stand part of the Bill.
Will the Minister say how many heat pumps were installed in 2022? What is the plan to get up to the Government’s target of 600,000 heat pump installations a year? This is an important Bill but it also shows the need for the Government to think in the round in terms of legislation. The clause and the amendment are all about heat pump installations. We are still awaiting the future homes standard. Will the Minister outline what will happen with that? Last year more than 200,000 houses were built in the UK—the largest number completed since the 2008 housing crash—and the majority of them are going to be connected to the gas grid and will not have heat pumps installed. Year in, year out, the number of houses that will need to be retrofitted with heat pumps will increase until the Government bring forward the future homes standard. I would like more clarity from the Minister on that, and about targets the Government are looking to set to drive it forward.
There is a considerable difference between Government targets, how many heat pumps have already been installed and how many heat pumps are likely to be installed over the next few years. One of the purposes of the amendment, which was not moved, was to stiffen the Government’s resolve in that respect by placing those targets on the face of the Bill, so that the question of how the gap is made up is rather more focused in the minds of the Government now and, indeed, any future Government.
It is important that we start the process of filling in the gap between target and actuality. I would be grateful if the Minister could give us a few brief views on how that might be done, and what he intends to do, possibly on the basis of this legislation, to make that gap clearly reachable and incorporate it into the progress that has already been made with heat pump installations.
I will answer the hon. Gentleman’s original questions. He asked why the Bill does not introduce the 900,000 heat pump installations recommended by the Climate Change Committee’s balanced pathway to net zero. Indeed, he asked why our aim is to introduce two thirds of that number, 600,000. The Government’s ambition for developing the heat pump market this decade is strategically compatible with all future heating scenarios, including those where hydrogen plays a major role. I know that the hon. Gentleman is fully aware of that, given his interest in hydrogen.
The CCC pathway, which suggests a market of 900,000 installations by 2028, assumes a minimal role for hydrogen in 2050. By contrast, it is interesting that the CCC’s hydrogen-led pathway suggests a much more modest deployment rate of heat pumps in earlier years. The Government believe that the step-change ambition for building a heat pump market as set out, which does not pre-empt wider strategic decisions in the middle of this decade, is the most prudent approach to this investment.
In answer to the hon. Gentleman’s second question, the building regulations will continue to set a performance-based standard, rather than mandating or banning the use of any technology if we do not want to head down that route. However, homes built under the future homes standard will be zero-carbon ready, with low-carbon heating and high levels of energy efficiency. I can confirm that 70,000 heat pumps a year are now being installed in the United Kingdom.
Question put and agreed to.
Clause 106 accordingly ordered to stand part of the Bill.
Clause 107
Further provision about scheme regulations
Question proposed, That the clause stand part of the Bill.
Clause 108 enables the appointment in regulations of an administrator for a low-carbon heat scheme and the conferral of functions on that scheme administrator. The clause sets out that one or more public authorities may be appointed as scheme administrator. That would include the Secretary of State, as well as public bodies and regulators such as the Environment Agency and Ofgem. The clause also provides for regulations to authorise an appointed administrator to arrange for functions to be carried out by a third party.
Clause 109 provides for the assessment, enforcement and sanctioning of non-compliance with a low-carbon heat scheme. It enables the administrator to conduct a range of enforcement activities and provides for the regulations to establish sanctions for non-compliance, such as the failure to produce the required documentation or to make a necessary payment. That could be in the shape of both civil penalties, and potentially criminal offences where warranted. Clause 110 sets out that regulations may determine how any payments made by virtue of the penalties set out in clause 109, or by virtue of the payment framework provided for by clause 107, are to be used.
Clause 111 provides for the regulation to establish an appeals process against decisions by the administrator of a low-carbon heat scheme, or against penalties or other enforcement action taken for non-compliance by a scheme participant. Such an appeals process is relatively commonplace for obligations and trading schemes of that kind, so that disputes can be settled, enhancing confidence in decision-making processes related to scheme administration.
Clause 112 establishes procedural requirements for the making of low-carbon heat scheme regulations. The affirmative parliamentary procedure will be used for statutory instruments that first establish a low-carbon heat scheme. The affirmative procedure will also apply for regulations that make substantive changes to the fundamental parameters of a scheme—that is to say, the parties in scope of the targets or the heating appliances that the scheme is designed to encourage. Where the regulations are more administrative in nature, and the fundamental elements of a scheme are not being altered, the negative resolution procedure will apply. That will include, for instance, adjustments to the requirements for the keeping or provision of information, year-to-year adjustment of targets, or adjustments to the rules around the certificate trading between parties.
The clause also stipulates a requirement that before making scheme regulations the Secretary of State must consult the relevant Ministers in the devolved Administrations, so far as the regulations apply in relation to those respective nations. The Government have constructive engagement with our counterparts in the devolved Administrations at both official and ministerial level on the development of the clean heat market mechanism. We look forward to continuing to work closely and consultatively as we move forward with the scheme’s development. Finally, clause 113 provides definitions of key terms within the chapter.
Question put and agreed to.
Clause 107 accordingly ordered to stand part of the Bill.
Clauses 108 to 113 ordered to stand part of the Bill.
Clause 114
Modifications of the gas code
Question proposed, That the clause stand part of the Bill.
Amendment 118, in clause 115, page 106, line 23, at end insert—
“(4A) Provision under subsection (4), where a gas transporter is conducting a trial involving a fully alternative grid for the purpose of hydrogen delivery, must include guaranteed installation of other forms of low carbon heating by the gas transporter where a household does not wish to take part in the hydrogen grid conversion trial.”
This amendment seeks to ensure that no household will be forced to take part in the trial and will be given an alternative heating solution by the gas transporter (the DNO).
Clause 115 stand part.
Taking timely strategic decisions on heating is critical to meeting future carbon budgets and the UK’s net zero target. Subsection (1) allows the Secretary of State to designate a hydrogen grid conversion trial and ensures that both clause 114 and clause 115 are narrow in scope and would apply only for the purposes of such a trial. Clause 114 also makes certain modifications to the Gas Act 1986 to build on existing provisions concerning powers of entry. That will ensure that the organisation running the trial has clear grounds to enter private properties to carry out any essential works, including replacing appliances and installing and testing safety valves; undertake inspections and tests for the trial, such as safety checks; and safely disconnect the gas supply in a property.
Gas transporters already have powers of entry into properties through the Gas Act. We are extending those powers in a very limited way to conduct the necessary work to set up and deliver the trial. Gas transporters will use the extended powers only ever as a last resort, once all other attempts to contact property owners and reach an agreement are exhausted. The existing rules on powers of entry requiring the gas transporter to obtain a warrant from a magistrates court will continue to apply. No one in the trial location will be forced to use hydrogen.
The gas transporter delivering the trial will develop an attractive consumer offer for participants, as well as viable alternative options such as electric cookers and heating systems, for consumers who do not wish to or cannot participate in the trial. Finally, I draw the Committee’s attention to the fact that most responses to the Department’s 2021 public consultation on facilitating a hydrogen village trial were broadly supportive of our proposals to change the legislation in this way.
Clause 115 focuses on establishing consumer protections for people taking part in this first-of-its-kind hydrogen village trial. It will do so by giving the Secretary of State two delegated powers to make regulations that require the gas transporter running the trial to follow specific processes to engage and inform consumers about the trial and ensure that consumers are protected before, during and after it.
Consumer engagement and support are vital for the successful delivery of the trial. The Department is working closely with the gas transporters as they develop their plans for consumer engagement and protection. Regulations will ensure that the gas transporter running the trial takes the necessary steps to inform consumers about how they will be impacted. That means that people will have the information they need to make an informed choice about whether to connect to hydrogen or accept the alternative offer during the trial. The gas transporter will also need to give adequate notice about the requirement to disconnect properties from natural gas.
The power to introduce regulations for consumer protections will work alongside existing protections such as the Consumer Rights Act 2015 and the Gas (Standards of Performance) Regulations 2005. I am sure that Members of the Committee will agree that the provisions in clause 115, which were well received by stakeholders when we consulted on them in 2021, are crucial to ensure the fair treatment and protection of people in the trial area. The powers will also allow the Department to set out the enforcement requirements for the regulations, which may include civil penalties but will not create any new criminal offences.
There are two village trials under way at the moment: one in Ellesmere Port and one in Redcar. Interestingly, public appreciation of those trials is markedly different. One is trying to get everybody on board straight away. In the other, the company running the trial has taken a different approach to universal involvement. We might think that all the properties in a particular area need to be in the trial for it to be entirely valid, but that is not necessarily the case. One company is intending, at rather a late stage of the trial, to introduce a separate hydrogen main into the area. The other trial company is trying to get people on board without modifying the main and will use what was the gas main for carrying the hydrogen. That creates a considerable issue for participation in the trial.
The Minister said that no one would be forced to take part in trials, but at the same time spoke about enhanced powers of entry and various other things, which suggests that the powers could be used to force everyone to take part. That is what amendment 118 is concerned with. It states:
“where a gas transporter is conducting a trial involving a fully alternative grid for the purpose of hydrogen delivery”.
If we wish to adhere to the principle that not everybody has to take part in a trial—there might be many good reasons why people do not want to do so—there must be guaranteed arrangements for the installation of other forms of low carbon heating or indeed for no low carbon heating at all if an alternative main is put in place for people who do not wish to take part in grid conversion trials. Under subsection (4), the amendment would require companies undertaking trials to guarantee the installation of other forms of low-carbon heating, such as heat pumps or low-carbon gas heating. That would enable the trials to bring valid results, and give people in those areas the ability not to take part if they do not wish to do so.
It is important that we take people with us. They must have the option to say no to such trials and get low-carbon heating by another means. That is all I wanted to say on the amendment.
That trial in Fife highlights the issues that we are debating today. Will the Minister update the Committee on the number of properties signed up to H100? Investigative journalists have reported that the £1,000 sign-up offer was not enough of an inducement to make households sign up. That is the conundrum: it is fine to say that there will be a financial incentive or a consumer offer—the Minister says that we will never need to resort to using the powers in these clauses—but it is clear that some people are reluctant to sign up. If the financial inducement is not enough, how will the Government and the gas operators take those people with them and get this over the finishing line?
It is absolute critical that we take people with us. It is critical that consumers understand the offer they are getting, the risk and the way that the hydrogen trials are being undertaken. It is important that there is transparency in the reporting of the trials. In particular, we need to understand how risks and leakages will be reported. The worst thing that can happen is for rumours or wrong perceptions to circulate.
Amendment 118 is intended to give people an alternative to being part of a hydrogen trial. I support that principle, but that still leaves us with the dilemma of what happens if a household says, “I don’t want to be part of a hydrogen trial and, by the way, you can forget these heat pump things. I am quite happy with my methane gas, thank you very much.” What would happen in that circumstance?
That brings me to the Minister’s argument on Second Reading that the powers will not be used to either force people into the hydrogen trial or leave them disconnected from the gas network. What happens if not enough people are signing up? Frankly, the Government will then have a dilemma. If they want to facilitate these hydrogen trials, they need enough people on the hydrogen network, otherwise the trials will not be sufficient to get an understanding of, or see, the proper operation and benefits of hydrogen.
What will the Government do if not enough people are signing up? How will they facilitate people signing up without forcing them, and how will they get these powers to be successful in terms of mass criticality? There is the old phrase, “You can’t make an omelette without breaking some eggs.” It might well be that the Government are going to upset some people, but they will have to be honest about it. Just saying, “There is no way we will use the powers in the Bill” might be unintentionally disingenuous. I am curious what the Minister’s thoughts are. It is fine to say that the Government will not use them, but that remains to be seen.
On the other two trials, final decisions have yet to be made on the locations, and details of the exact processes are a matter for the companies and operators engaging in the trial. I thank the hon. Member for Southampton, Test for his amendment. It is very important that we discuss the issues he raised. We have always been very clear that nobody will be forced to use hydrogen, and alternative heating solutions and appliances such as electric heating systems and cookers will be offered for those who do not take part in the trial. As my noble Friend Lord Callanan confirmed in the other place, all consumers in the trial location will have the right to decide whether they use hydrogen or an alternative heating solution for the duration of the trial.
The requirement was clearly established in a joint letter from the then Department for Business, Energy and Industrial Strategy and Ofgem to the gas transporters, which set out the requirements that will have to be met before any funding is provided to the next stages of the trial. It is on the shoulders of the operator to prove that they have community consent to proceed with the trial in a given location. This is a fundamental requirement for the trial. The gas transporters need to demonstrate that they have a viable plan for providing alternatives, otherwise His Majesty’s Government will not proceed with the trial proposal. This obligation will also form part of any future funding agreement.
I would like to say again that there is already an effective way to ensure that the networks provide an alternative to hydrogen. As such, we do not believe that adding to the Bill is necessary for the success of any of the trials. I fully appreciate the intention of the hon. Member for Southampton, Test to ensure that the trials are conducted properly, with alternative systems offered to those who take part.
I realise that I have not answered the hon. Member for Sheffield, Hallam’s question; the same offer will be made to businesses as households. Businesses will be protected in the same way as individual households are as a result of how we have drafted the Bill. I hope hon. Members are reassured that there are already steps in place to ensure that everybody is protected and that there is a choice. I hope the hon. Member for Southampton, Test will find it within himself not to press his amendment to a vote.
Question put and agreed to.
Clause 114 accordingly ordered to stand part of the Bill.
Clause 115
Regulations for protection of consumers
Amendment proposed: 118, in clause 115, page 106, line 23, at end insert—
“(4A) Provision under subsection (4), where a gas transporter is conducting a trial involving a fully alternative grid for the purpose of hydrogen delivery, must include guaranteed installation of other forms of low carbon heating by the gas transporter where a household does not wish to take part in the hydrogen grid conversion trial.”—(Dr Whitehead.)
This amendment seeks to ensure that no household will be forced to take part in the trial and will be given an alternative heating solution by the gas transporter (the DNO).
Question accordingly negatived.
Clause 115 ordered to stand part of the Bill.
Clause 116
Fusion energy facilities: nuclear site licence not required
Question proposed, That the clause stand part of the Bill.
“The Secretary of State must consult on and establish a revised nuclear site licence regime for fusion energy which will not be subject to the full range of safeguards associated with the use of fissionable materials but must have regard to the residual radioactivity of the proceeds of fusion activity.”
The UK is widely recognised as a world leader in the most promising fusion technologies. For example, the UK’s ambitious spherical tokamak for energy production programme—STEP— aims to develop and build a fusion prototype powerplant in the UK by 2040. That is only 17 years away. We announced in October 2022 that the site for STEP would be at West Burton in Nottinghamshire, which will help to bring high-skilled jobs and investment to that region.
Experimental fusion facilities currently operating in the UK are regulated under a framework that is separate from the nuclear site licensing regime. Under that framework, the Environment Agency and the Health and Safety Executive have, since 1983, successfully regulated the Joint European Torus, which is currently the most powerful operational fusion device in the world. It is run by the UK Atomic Energy Authority in Oxfordshire, which I have had the pleasure of visiting.
Following consideration of the responses from last year’s consultation on fusion regulation, the Government have decided that this framework would provide proportionate and appropriate regulation of future fusion energy facilities. It is a position supported by the current regulators. Clause 116 makes the UK the first country in the world to legislate for fusion energy. It will enable the sector to plan with confidence, based on a regulatory framework that will continue to maintain public and environmental safety, helping to encourage investment and accelerating the commercialisation of fusion energy.
“To produce usable heat, the neutron streams carrying 80 percent of the energy from deuterium-tritium fusion must be decelerated and cooled by the reactor structure, its surrounding lithium-containing blanket, and the coolant. The neutron radiation damage in the solid vessel wall is expected to be worse than in fission reactors because of the higher neutron energies. Fusion neutrons knock atoms out of their usual lattice positions, causing swelling and fracturing of the structure. Also, neutron-induced reactions generate large amounts of interstitial helium and hydrogen, forming gas pockets that lead to additional swelling, embrittlement, and fatigue. These phenomena put the integrity of the reaction vessel in peril.”
I think the hon. Member will be clear from that that it is not the neutrons that are the issue; it is the radiation.
As I have described, the side effects are not just about the problem of the potential embrittlement of the casing and the need to treat that casing in due course, the need to stop tritium release through lithium blankets around the sphere core and the difficulty of making those blankets completely sealable. All those things suggest that the sorts of actions in the nuclear installation regulations and the Nuclear Installations Act 1965 are rather more pertinent than we might have thought, than the Minister suggested or than the clause seems to provide. I suggest a modest revision of the clause so that, instead of dismissing the safety concerns about and operational arrangements for fusion, it brings forward a revised, and perhaps acceptably less rigorous, process that nevertheless falls within overall nuclear guidelines for fusion activities.
In any debate on fusion, it has always been said that fusion is a very bright future for us but that it is 40 years away. Well, it is not 40 years away now; it is much closer to being realised. As the Minister said, in the UK, spherical tokamak for energy production is potentially producing good results, so we could be a few years away from having to get this regime right, and it is right that we do so now. Our new clause 51, which—for the guidance of those who have given up going through all the amendments and new clauses in the amendment paper—is to be found right at the back on page 58, states:
“The Secretary of State must consult on and establish a revised nuclear site licence regime for fusion energy which will not be subject to the full range of safeguards associated with the use of fissionable materials but must have regard to the residual radioactivity of the proceeds of fusion activity.”
That is a sensible alternative that will not, or should not, in any way impede the development of fusion, but will provide a clear understanding as to what we are dealing with as far as fusion is concerned. It would be a programme of appropriate and proportionate safeguards—yes, associated with nuclear safeguards in the background—that makes clear the very different circumstances under which fusion works. That would be helpful.
This morning, I heard the Minister say that the Government are perhaps thinking about some form of regulation that would go beyond what appears to be the negative nature of this particular proposal, but at the moment I cannot see any moves in that direction. The new clause would, I think, give us the best of both worlds. It would allow us to proceed with fusion activity with safety clearly uppermost in our minds, but we would not be impeding the process by the way we regulated. We would all want this to happen. It is a proper arrangement as far as safety is concerned, and would enable proper progress as far as fusion is concerned.
Once again, if the Minister is not more forthcoming in moving away from the position of this particular new clause, we may want to divide on it: it is an important principle that we should get regulation right, from the start of the fusion process. I agree with the Minister that it could mean an exciting future, but it needs to have the proper safeguards in place for it to work in all our interests in the years to come.
What the hon. Gentleman was describing was neutrons degrading a physical structure, as a by-product of the plasma. There is an analogy here: it is almost like it getting shot at or water going through a concrete structure and then causing rust and degrading the steel within it. That is not necessarily the creation of a nuclear radioactive source; that is something being peppered with neutrons. And that is why it is not a commercially viable facility at the moment—because there are still things to be worked out, not least how we ensure that we do not build a very expensive thing that, by its own nature, then degrades over time and use. But that is not the same as creating a radioactive source.
The hon. Gentleman mentioned deuterium and tritium, which are different types of naturally occurring hydrogen elements. Tritium sounds, to my ear, almost like something that the Terminator would be using to do something particularly exciting. In fact, it is only a hydrogen that occurs in nature and that has a single proton and two neutrons within the nucleus, so it is a bit bigger and heavier than is typical. What that means is that it is a little more unstable. The natural half-life of tritium is 12 years, whereas the nuclear regulations that the hon. Gentleman seeks to apply or partially apply in this instance are designed to deal with things that have half-lives of thousands of years. Someone will tell me that I have this wrong, but with uranium-238 we are talking about very different orders of magnitude—
I wondered about the criteria, given that the hon. Member for Sheffield, Hallam mentioned radioactivity occurring in the fusion environment. What percentage of Cornwall, with its radon gas, might be caught up in the thresholds? I will be interested to pursue on Report what we are actually talking about. As a scientist, the hon. Lady knows that 100 is very different from 1, even though 1 poses some risk.
I am grateful to the hon. Member for Southampton, Test for tabling the new clause, but given the opportunity for clean, net zero energy—which really could be the panacea for the world, as tree-huggers like me would say—in the UK we should look to tread lightly, but carefully, with any regulation of an industry that has such a level of potential and to which the UK has contributed so much already. He mentioned torus structures, but those are only one of a series of different potential generational tools—torus might be the research tool, not the commercial tool, so his concerns could disappear with a completely different production facility, perhaps based on electromagnetic rather than physical containment.
With regret, because I understand the genuine and heartfelt nature of the hon. Gentleman’s new clause, I think it is important that we do not stifle a nascent industry with regulation. I will therefore support the Government’s position.
The Government’s plans are about working up from the frameworks that apply to existing fusion sites, rather than working down from them. We believe that the new clause could stifle the development of the technology that we have been exploring in depth this morning. It is vital to stress that we are not—definitely not—trying to make fusion energy facilities avoid licensing requirements. Nor are we seeking to water down any regulations. For a fusion energy facility to be developed and operated in a lawful way, it must go through permitting and consenting processes governed by the relevant regulators. In England, those are the Environment Agency and the Health and Safety Executive. This is consistent with how other facilities with radioactive materials such as cyclotrons and large-scale industrial irradiators are regulated for at the moment.
The regulatory process that we have right now requires fusion energy facilities to go through various approval stages as well as ongoing compliance and engagement. The requirements associated with those regulatory obligations are proportionate to the hazard associated with the fusion energy facility. I should also say the legislative consent motion procedure has been invoked. We have already consulted the Scottish Government on the procedure and they raised no concerns; obviously, there are separate regulations and bodies responsible for the issue in Scotland.
We do not believe that fusion energy facilities should require nuclear site licences. That is what we are discussing this morning. They should not go through the process requiring nuclear site licences because, following consultation, we believe that that would be disproportionate to the hazards associated with fusion. Such hazards, as various hon. Members have explained in greater detail than I would ever be able to, are significantly lower than with nuclear fission, and the regulatory frameworks required for fission would therefore be too burdensome for the technology.
The Government agreed with the majority of the consultation respondents that the existing regulatory processes of consenting and permitting would be proportionate and appropriate for fusion energy facilities. That was all set out in a full consultation that preceded the introduction of the Bill. We see no need to consult again on the same issue at this time. I hope I have been able to set the minds of the hon. Member for Southampton Test and others at rest following their justifiable, reasonable and well thought through questions on this matter. I hope that he will feel able to withdraw his amendment.
Question put and agreed to.
Clause 116 accordingly ordered to stand part of the Bill.
Clause 117
Treatment of recycled carbon fuel and nuclear-derived fuel as renewable transport fuel
Question proposed, That the clause stand part of the Bill.
Clause 117 will enable two types of low carbon to be treated as though they were renewable for the sole purpose of those schemes, helping the UK to further decarbonise transport. The two low carbon fuels are recycled carbon fuels, produced from otherwise unrecyclable waste plastics or industrial waste gases that cannot be avoided, reused, or recycled, and fuels derived from nuclear energy.
Currently, powers under the Energy Act 2004 only permit renewable fuels to be supported. The clause has been carefully drafted so that it does not classify recycled carbon fuels and nuclear-derived fuels as renewable fuels, ensuring these fuels are treated as though they were renewable for the sole purpose of part 2, chapter 5 of the Energy Act 2004. That allows schemes such as the renewable transport fuel obligation and forthcoming sustainable aviation fuel mandate to support the use of those types of fuels. It does not grant them wider consideration as renewable fuels.
Both fuel types have the potential to deliver significant carbon savings over traditional fossil fuels and are a vital replacement for difficult-to-decarbonise sectors such as commercial aviation and heavy goods vehicles.
The UK Government have targets to phase out wastes generally, especially unrecyclable plastics. There is a huge public push for that, with the reduction of single-use plastics. By creating a new market for that waste, there is a real risk of creating disincentives to achieve carbon reduction in products and plastics, to achieve waste avoidance. This could be used as a mechanism to prevent further progress in that space.
More broadly, as we all know, there is an urgent need to reduce the current level of carbon dioxide in our atmosphere. This proposal would instead convert waste fossil fuels into a liquid form that allows carbon to be rereleased as CO2 into the atmosphere, together with non-CO2 impacts generated from aviation. We cannot simply go about changing definitions and hoping that that will lead to more decarbonisation. Allowing the aviation sector to make misleading or simply wrong claims about sustainability would be deeply unhelpful in meeting the target for net zero for aviation by 2050.
There are many ways in which we can make synthetic aviation fuel that are truly about carbon capture, and there is a lot of work on that, but simply changing the label on what unrecyclable plastics are is deeply unhelpful. The Minister should think deeply about the unforeseen consequences of allowing that business to thrive. We really want to reduce our reliance on fossil fuels. Net zero is what it says on the tin—it is about net zero—but we also have to make efforts to reduce our usage of carbon products from fossil fuels. This is a difficult point for me to get my head around, and I would like to understand the Minister’s reason for embracing a measure that seems quite anti-progress in terms of reducing our use of plastics, and how it is compatible with the future of net zero.
The hon. Lady also asked about the potential that this may, by accident, incentivise or perpetuate the creation of plastic waste or industrial processes that generate waste gases. Recycled carbon fuels are fuels produced from fossil waste that cannot be avoided, reused or recycled, and have the potential to reduce greenhouse gas emissions relative to petrol or diesel. I know that she understands that.
In line with the principles of the waste hierarchy, our recent consultation on introducing recycled carbon fuels into the renewable transport fuel obligation set out eligibility criteria to ensure that recycled carbon fuels would not be produced from recyclable material. Other schemes, such as the sustainable aviation fuel mandate, will have similar criteria to ensure that the production of waste is not incentivised by this. For solid recycled carbon fuels to be eligible for support, suppliers must be able to demonstrate that the waste is derived from facilities that have adequate separation processes to remove recyclable plastics. We believe that converting non-recyclable waste plastic into recycled carbon fuels can achieve a greater energy recovery than disposing of the waste via conventional means. I hope that answers the hon. Lady’s concerns.
Question put and agreed to.
Clause 117 accordingly ordered to stand part of the Bill.
Clause 118
Climate Change Act 2008: meaning of “UK removals”
Question proposed, That the clause stand part of the Bill.
Question put and agreed to.
Clause 118 accordingly ordered to stand part of the Bill.
Clause 119
The Independent System Operator and Planner (“the ISOP”)
“including the oversight of efficiency and loss reduction in cabling”.
This amendment would give the Independent System Operator oversight of cabling efficiency and loss reduction in cabling.
Amendment 96, in clause 119, page 109, line 3, at end insert
“and of distribution systems in conjunction with licenced distribution system operators”.
This amendment would include certain distribution systems in the functions of the ISOP.
Amendment 97, in clause 119, page 109, line 5, at end insert
“and of distribution systems in conjunction with licensed distribution system operators”.
This amendment would include certain distribution systems in the functions of the ISOP.
Clause stand part.
Clause 120 stand part.
New clause 37—Assurance of independence of system and distribution operators—
“(1) The Secretary of State must appoint a supervisory and advisory board of at least eight suitably qualified independent energy figures to assist the person designated as the ISOP under section 120.
(2) The purpose of the board appointed under subsection (1) is to assure the independence of transmission and distribution system operators through independent oversight of and advice to the ISOP.
(3) Energy UK and the Energy Networks Association must be consulted on the appointment of the board under subsection (1).
(4) The Secretary of State may make provision of financial assistance to enable the board to carry out its functions.”
This new clause aims to ensure the independence of system and distribution operators.
As the Minister will know, the independent system operator has been in gestation for a while, in terms of the separating of National Grid ESO from the National Grid itself. National Grid ESO now performs something of the function I have started to describe, but without the remit to do so. What we need over the next period is not just National Grid ESO, nor something with a different name from National Grid ESO, but something that is much closer to a system architect in upgrading our systems for renewable purposes. That is how I see the development of the ISOP. It is important that in our first go at what the ISOP does, as it were, we get the best combination of things it is responsible for and that we get right its ISOP set-up.
In the development of the grid so far, certainly as far as renewable energy connections are concerned, there is no real distinction between the high-level grid, which was the historic purview of National Grid and ISOP, and the lower-level grid, which is still pretty powerful but is in the hands of the distributed network organisations. Sometimes a false distinction is made between what is happening at National Grid level and what is happening at a more regional or local level. There is no real distinction now, because renewable sources, in particular, are seeking to substantially connect to 123 kV cables to a far greater extent than they are seeking to connect to high-level grid 440 kV cables. Consequently, some of the biggest backlogs in connection dates are not just in the high-level grid.
The Minister will be aware—we have discussed this previously in the House—that a number of large wind farms are getting connection dates to bring ashore and distribute the electricity they are producing not just a few years away, but in 2036. As I have mentioned previously in the House, that is one year away from when the Government have indicated they wish to see a predominantly renewable energy system in place. We may well have the tools to have the low-carbon energy system in place, but if we cannot deliver the electricity from those tools to anybody, we do not have a low-carbon energy system in place in the end. It is important that we get the system properly in place, so that it can deliver the connections and the offshore re-cabling. That way we will have a decent grid highway with anticipatory investment.
The hon. Member for Kilmarnock and Loudoun rightly draws attention to the fact that some Scottish-based offshore schemes are now being asked, on a point-to-point basis, to connect south of the border, because the facilities for delivering from those connections, were they to be north of the border, are not as good as they should be. Interestingly, the Government are presently considering a bizarre series of arrangements called marginal cost pricing, which will deter certain people from taking particular views about where they should connect because there will be a price differential in connecting. As I am sure the hon. Member will agree, the solution is not to start messing about with theoretical market considerations about who might connect where, but to build the stuff so that people can connect to it properly, where they are and where they want to be, with a certainty that there will be a connection in a short period of time and that what they have connected to gets to where we want it to be. Those are all reasons why the ISOP will be so important.
Through these amendments we want in no way to undermine, but rather to enhance, the substance of the ISOP. Our amendments, which are on page 5 of the amendment paper, seek to do several things regarding the structure and operation of the ISOP. First, we think that the ISOP should have oversight not just of the cabling itself, but of the cabling efficiency and loss reduction in cabling as it goes around the country. That is a potentially important issue for the future. I am sure that hon. Members know how much electricity is lost just by the transmission function.
I visited—this shows the exciting things that I do as shadow Energy Minister—a test site of a highly efficient cable system. I will not mention the company’s name, but as far as I know it is pursuing a much more efficient cable system with a number of DNOs. When I got to the site, there was not very much to see because the cable had been buried underground; I was pointed to a field. There was, however, in the corner of the field, a hut in which calculations on how the cable was performing, and how it would perform in conjunction with other forms of cable, were being undertaken. I was able to see for myself an increase in the efficiency of the cable of about 15%, just by having that cable design as opposed to others.
It seems to me quite important that the cabling introduced to our new system be as efficient as possible. It needs to be clear to the companies that will put the closed cables in that that is what will be expected of them. That is why we would like an additional function to be added to the ISOP’s concerns: oversight of efficiency and loss reduction in cabling.
We have tabled other amendments, which concern the relationship with the DNOs. It is important that we do not make an artificial distinction in terms of what we are doing with the ISOP in the high-level system and others. I am afraid that the Bill, whether intentionally or not, appears to create that divide. The DNOs can get on with their activities, and the high-level grid will have a different system of governance and management. That is why amendment 96 would add
“and of distribution systems in conjunction with licenced distribution system operators”
to the end of line 3, in clause 119. Amendment 97 would add the same words. That would create a much better system of co-operation and collaboration between the DNOs and the new system operator.
I appreciate that we will not vote on new clause 37 today. It is important for the independent system operator really to be independent, and not a creature of either the energy companies or the Government, so that it has its own ability to look at the system, to produce recommendations and arrangements, and to oversee the development of the system as its own master within that.
We therefore suggest in new clause 37 that an independent advisory board be set up to ensure the independence of the ISOP. There are other ways of doing this, but we are suggesting one particular way of ensuring that the ISOP operates in the genuinely independent way that we all want it to in pursuit of the future of grids and connections.
I hope that the Minister and the Committee understand that our amendments and new clauses all seek to help with the ISOP. I hope that the Minister will respond positively by saying that there are different ways of achieving what we want to achieve with the ISOP’s powers, or that, although he might not be able to accept the amendments today, he is actively minded to have a good think about them. By the way, I am grateful for the note that the Minister wrote to me last night about the fact that the Government have done just that with one particular amendment to the Bill. That sort of process could easily be followed in such circumstances in future.
I will now turn to the question asked by the hon. Member for Southampton, Test about why an advisory board would make ISOP risk-averse and not fully independent. We are concerned that, rather than enhancing independence, the members of such a board would likely hold various energy sector conflicts. That could crystallise in many ways, including resistance to systematic reform, advice to pay compensation to energy sector participants or an incumbent bias that would seek to frustrate new market entrants. Establishing an industry-led advisory board for the ISOP would be similar to establishing one for the Climate Change Committee—it is not required for an organisation that needs to remain independent, such as the Climate Change Committee, which we are using as the basis for how we proceed.
A prime consideration of the ISOP consultation was that the body should be independent from day-to-day Government control and from other energy sector interests. That is why we need to ensure that the ISOP is a trusted and independent voice within the energy sector.
I turn to amendments 95, 96 and 97, tabled by the hon. Member for Southampton, Test. The Government agree that those are all things that the ISOP needs to bear in mind, but we think that the balance in part 4 would be distorted by calling them out in the high-level illustrative list of the ISOP’s initial functions in the clause.
On amendment 95, matters already of concern to the existing system operator will continue to be a concern to the ISOP, in particular as it seeks to promote system efficiency under clause 121. On amendments 96 and 97, we understand that a closer relationship between the system operator and the distribution system operators—indeed, closer relationship across all energy networks—will allow for better co-ordination and ensure optimal system-wide planning. However, we do not think that such things should be included in the high-level illustrative list of the ISOP’s initial functions. A new collaboration duty is not necessary as that lies at the very heart of our vision for the ISOP. The importance of co-ordination across networks is made clear by clause 121(4)(a) and the whole systems duty in 122(1)(c).
Clause 120 empowers the Secretary of State to designate the ISOP, doing so by granting a power to the Secretary of State to make the first designation of a person as the ISOP and, if needed, to revoke that designation and issue a new one. I commend clauses 119 and 120 to the Committee.
Adjourned till this day at Two o’clock.
Contains Parliamentary information licensed under the Open Parliament Licence v3.0.