PARLIAMENTARY DEBATE
Smart Meters Bill (First sitting) - 21 November 2017 (Commons/Public Bill Committees)
Debate Detail
Chair(s) †Mike Gapes, Mrs Cheryl Gillan
Members† Carden, Dan (Liverpool, Walton) (Lab)
† Debbonaire, Thangam (Bristol West) (Lab)
† Freer, Mike (Finchley and Golders Green) (Con)
† Gibson, Patricia (North Ayrshire and Arran) (SNP)
† Grant, Bill (Ayr, Carrick and Cumnock) (Con)
† Harrington, Richard (Parliamentary Under-Secretary of State for Business, Energy and Industrial Strategy)
† Kerr, Stephen (Stirling) (Con)
† Lewis, Clive (Norwich South) (Lab)
† McCabe, Steve (Birmingham, Selly Oak) (Lab)
† Morris, Grahame (Easington) (Lab)
† Pawsey, Mark (Rugby) (Con)
Quince, Will (Colchester) (Con)
† Ross, Douglas (Moray) (Con)
† Smith, Laura (Crewe and Nantwich) (Lab)
† Tolhurst, Kelly (Rochester and Strood) (Con)
Warman, Matt (Boston and Skegness) (Con)
† Watling, Giles (Clacton) (Con)
† Western, Matt (Warwick and Leamington) (Lab)
† Whitehead, Dr Alan (Southampton, Test) (Lab)
ClerksJyoti Chandola, Clementine Brown, Committee Clerks
† attended the Committee
Witnesses
Audrey Gallacher, Director of Retail Energy, Energy UK
Bill Bullen, Managing Director, Utilita
Rob Salter-Church, Partner, Consumer and Competition, Ofgem
Angus Flett, Chief Executive Officer, Smart DCC Ltd
Public Bill CommitteeTuesday 21 November 2017
(Morning)
[Mike Gapes in the Chair]
Smart Meters Bill
Today we will consider the programme motion, a motion for the reporting of written evidence for publication and a motion to allow us to deliberate in private about our questions before we take oral evidence. This morning’s sitting is due to conclude by 10.40. In view of the time available, I hope that we can take the procedural matters formally, without debate, if that is agreeable.
Ordered,
That—
(1) the Committee shall (in addition to its first meeting at 9.25 am on Tuesday 21 November) meet—
(a) at 2.00 pm on Tuesday 21 November;
(b) at 11.30 am and 2.00 pm on Thursday 23 November;
(c) at 9.25 am and 2.00 pm on Tuesday 28 November;
(d) at 11.30 am and 2.00 pm on Thursday 30 November;
(2) the Committee shall hear oral evidence in accordance with the following table:
TABLE
Date | Time | Witness |
---|---|---|
Tuesday 21 November | Until no later than 10.10 am | Energy UK; Utilita |
Tuesday 21 November | Until no later than 10.40 am | Ofgem; Data Communications Company |
Tuesday 21 November | Until no later than 2.45 pm | Secure Meters; Trilliant |
Tuesday 21 November | Until no later than 3.15 pm | Smart Energy GB; Citizens Advice Bureau |
Tuesday 21 November | Until no later than 3.45 pm | Dr Richard Fitton, University of Salford; Dr Sarah Darby, Environmental Change Institute, University of Oxford |
(3) proceedings on consideration of the Bill in Committee shall be taken in the following order: Clauses 1 to 11; new Clauses; new Schedules; remaining proceedings on the Bill;
(4) the proceedings shall (so far as not previously concluded) be brought to a conclusion at 5.00 pm on Thursday 30 November.—(Richard Harrington.)
Resolved,
That, subject to the discretion of the Chair, any written evidence received by the Committee shall be reported to the House for publication.—(Richard Harrington.)
Resolved,
That, at this and any subsequent meeting at which oral evidence is to be heard, the Committee shall sit in private until the witnesses are admitted.—(Richard Harrington.)
Examination of Witnesses
Bill Bullen and Audrey Gallacher gave evidence.
Welcome. Please introduce yourselves for the record.
Audrey Gallacher: I am Audrey Gallacher, director of energy supply at Energy UK.
Bill Bullen: I am Bill Bullen, CEO of Utilita.
Audrey Gallacher: It is important that the Business, Energy and Industrial Strategy Committee and the Government maintain sufficient routine oversight over the programme. The extension is to allow that programme to be delivered so that consumers get the benefit. We know that the scheme is due to finish in 2020. There is clearly a question about whether that will happen fully, so it is important that that oversight is retained. We would be concerned about how any future powers are used and that due process is followed, and about all the other attendant requirements around any regulated area.
Bill Bullen: We do not think that the 2020 deadline is realistic, and I reiterate the need for continued administrative powers post 2020. The deadline will not be met, so it is essential that those powers are continued.
Bill Bullen: I just do not think that the programme is anywhere near the level of completion that it needs to be. The DCC was originally intended to be up and running in 2014, at which point 2020 was perhaps a realistic timeframe. We are now nearly at the end of 2017, and the DCC is clearly not up and running at anything like full capacity. It will just not be possible to deliver the remaining 40 million–plus meters in three years. It is logistically impossible.
Bill Bullen: Business is completely focused on the prepay market. We have nearly 600,000 prepay customers now, and more than 85% of those already have smart meters installed. The prepay market in total is something like 20% of the market—5 million households in the UK use prepay, and about 20% of those already have smart meters installed. There is a very simple reason for that: it completely transforms that product and service for those customers. It has huge value benefits for prepay households, which is why they have adopted the technology more quickly. Until the price cap came in, there were also significant price reductions because prepay smart meters allow people to cut their cost to serve ratio, and therefore they deliver a better price as well as a better product. It is a bit of a no-brainer, to be honest.
Audrey Gallacher: I echo that. We know from a lot of early research done on the Government’s smart meter programme that the customer service benefits go beyond improvements and engagement in reducing consumption. The sheer customer service benefits have been massive. Right now, people have to go outside the house to top up their meter, but with a smart meter they can do that in their home. As Bill says, that has proved massively popular.
Audrey Gallacher: We currently have the foundation stage for the smart meter roll-out with first generation meters. That was always the intention, as it is important that a programme of this nature and size is properly trialled and tested, so that when we move on to the mass roll-out that can be done as cost effectively and efficiently as possible, and with the best possible customer experience.
It is probably fair to say that the foundation stage has continued longer than we originally envisaged because there have been some delays around the enduring infrastructure to support the second generation meters. While that was really important, and there are already 8 million of those meters already, a lot of learnings have been taken, which means that we have a delay in the real ramp up. Until we see that ramp up, it might be difficult to understand the consumer appetite and attitude to smart meters, because we have not yet really started in earnest.
Bill Bullen: Obviously I have some difference of opinion about that. Certainly, in the market where we operate there has been great engagement with smart meters. In terms of the roll-out, one of the big issues has been the delays around the central systems for the second generation of meters. Personally, I think it was possibly not the best decision to go down that route in the first place. We would not be where we are, with 8 million meters already installed, if we did not have the first generation going out there.
My key concern, without wanting to rake over the coals of the past, is what is going to happen in the next two or three years. That will clearly be critical to the continued roll-out of smart meters, and particularly to delivering benefits to low-income prepayment households. That will be to do with the rules around the cut-over between SMETS 1 and SMETS 2 and whether continued roll-out of smart meters is going to be financially viable, because of the pre-pay price cap and changes to environmental levies that are going to have an impact on that going forward.
Bill Bullen: You have to realise that there is a completely different benefits case for prepayment customers versus normal credit customers. We are completely focused on prepayment.
As I have said already, the benefits to prepay customers are huge—the convenience alone is worth a considerable amount to somebody who may otherwise suffer an interruption to their power supply at a critical moment. With a smart meter, they can get the supply back on immediately; with a dumb meter, they cannot. Frankly, that is the biggest selling point right now, not least because, with the price cap at the level it is, there is no differential in price anymore. But customers are still buying smart prepay, so our growth rate has slowed down since 1 April, but it has not stopped. Customers do still get the benefits.
Audrey Gallacher: For consumers more generally, there are lots of benefits around an end to estimated balances. There should be improvements in the accuracy of bills and consumers should have more control over their energy because they can see it in pounds and pence in real time, so they can reduce consumption and save money. There is more information available to facilitate easier switching, so you can change to another supplier with more confidence.
Lots of the stats that Smart Energy GB, the communications and marketing company, is providing from its research show that this is starting to bear fruit. People are much more confident that their bill is accurate—83% compared with 61% of the non-smart population. There is a lot of satisfaction with the smart process. About 80% of people like their smart meter and thought it was a good process, 75% would recommend them to friends and family, and 80% have already taken action to reduce their energy consumption. There are lots of real benefits. We have also seen a reduction in complaints and an increase in satisfaction.
But the real prize is much longer term. Smart meters are an enabler for a much smarter and more flexible future. They are going to allow us to have much more control over the networks so that we can not only reduce demand and hopefully reduce the need for ever more energy generation, but use the networks more flexibly. They are an enabler for electric vehicles and storage, and all the other things that we anticipate for the future, so it is really critical that we get this done. To Bill’s point, we want to do it as effectively as possible at the least possible cost to consumers and with minimal interruption, but it is an absolutely essential component of the energy system of the future.
Audrey Gallacher: At the moment, one of the things that we are looking at for the roll-out of smart meters is that they will enable a lot more innovative products. We have seen the obvious customer service benefits for prepayment meter customers, but there are longer-term issues around what kinds of products and innovations can come out there, such as time of use, free weekend use—there are lots and lots of things. We are just starting to see the beginnings of that. It is not yet in place, but that is one of the things that smart will hopefully deliver.
Audrey Gallacher: It has probably been a bigger issue in the newspapers than for customers. That is one thing that we should bear in mind. Last month, 572,000 smart meters were put in and about 200 people contacted Citizens Advice with complaints or questions, so thankfully the customer experience and research looks a lot better than if you are just reading the news clippings.
Bill Bullen: I would make the case even more strongly than that: I do not think there really is an interoperability problem. The companies out there rolling out SMETS 1 generation meters have gone to great lengths to ensure that that is not a problem. We certainly exchange customers with smart meters with other suppliers all the time, and there is not a problem with interoperability. I think the issue has been massively overplayed, frankly.
Bill Bullen: Unfortunately, not all suppliers have engaged with smart meters. Some suppliers do not offer a smart prepayment product, for example. So if your constituent switches to a company that is not offering a smart product, clearly that will be an issue, but that is not to say that they could not switch supplier to someone else who is offering a smart prepay product.
Bill Bullen: First, since the price cap came in, there has been very little difference in price between suppliers. Obviously, consumers do have to check that the new supplier will offer a smart prepaid product.
Bill Bullen: I cannot answer on behalf of all suppliers, obviously, but clearly there are suppliers out there who are engaging in SMETS 1. We have interoperability in SMETS 1 and we exchange customers all the time. I guess there will always be suppliers who do not have or have not invested in the systems for their own strategic reasons or, for whatever reason, have decided not to support a particular product. That will always be the case. I would not want to make too much of one or two examples, but generally speaking there is interoperability between people engaged in the SMETS 1 meter market.
Bill Bullen: It would be a very sensible thing to do right now, yes.
Audrey Gallacher: In the short term, that would certainly be the advice, because, as Bill said, some companies do not have full interoperability. Some companies are not even rolling out any smart meters at all at the moment, and we have got 60 suppliers out there. So, yes in the short term, but there is an enduring solution coming down the line where all the SMETS 1 meters will be enrolled into the new central smart Data and Communications Company systems. Hopefully that will happen next year.
Bill Bullen: No, I am simply saying that I cannot govern all energy suppliers. If you switched to an energy supplier that decided for its own reasons not to support a smart service—
Bill Bullen: As I said, there is interoperability between SMETS 1 meters. In fact, there are only two or three types of meter out there, so actually the same headings are operating all of those meters. The interoperability problems of SMETS 1 is an issue that has been massively overplayed. Frankly, it is also giving some suppliers an easy excuse not to support a SMETS 1 product, saying that interoperability is difficult. It is not difficult. At the end of the day, you are talking about very few electronic messages that you need to exchange with a smart meter system, and it is not difficult. It really is not.
Would you like to comment on concerns, raised by trading standards, that not enough of the energy companies are making it clear to consumers that they can refuse a smart meter if they wish? There are real concerns that some energy companies may be guilty of breaching the Consumer Protection from Unfair Trading Regulations 2008.
What do you think about the idea that consumers are being sold the meters—by “sold” I am talking about the idea—as free, when we all know that in fact they are not free? The other thing is that, as far as I am aware, some of the models rely quite heavily on a wi-fi signal, which may or may not be available to all consumers. I may have got that wrong, because I am not terribly technically minded.
One of my concerns is what we do with the information when we have it. If we imagine a future where everybody has a smart meter, will that be used to charge a higher rate for electricity usage during peak times, when families cannot avoid using it? Will the need to use electricity at specific times be used to increase the price in the market?
I realise I am throwing a list at you, and I apologise for that. The idea that you pay for what you use is attractive to consumers, but the fact is that when a smart meter is installed on your property, as I know from my own experience, your direct debit bill stays exactly the same, because they spread it over the year. Yes, you are paying for what you use, but when you reduce your usage, your monthly or quarterly bill does not necessarily go down. What are your thoughts on that, given that it is sold comprehensively as, “You only pay for what you use”? You do, but not necessarily at the time when you use it. You will also know that there are concerns about the security of the data. I know that I have given you a long list, but I would be very interested to hear your thoughts.
Audrey Gallacher: I will run through it as quickly as possible. The questions you have raised are all legitimate ones, which are discussed on an ongoing basis through the programme. There is a lot of scrutiny and oversight of the programme, and everybody is working hard to get it right, so your questions are the right ones.
Loads of stuff has been done on security. This will not be happening over the internet, and GCHQ has been all over it. There are really strict security protocols; you will probably have experts in later today who will know more about it than I do, but if there is anything that we should be worried about in the programme, it is not security. A lot has been done there, for obvious reasons. It is a critical national infrastructure, not to mention the impact on individual consumers in their own home if something goes wrong. I would take some comfort that we have that.
The question of deemed appointments is a tricky one. This is an opt-in programme. The Government’s manifesto commitment is that customers should be offered a smart meter, but suppliers have an obligation to install them by 2020, so it is already quite a complex policy environment. Companies have to go out there and sell the benefits of smart meters and encourage consumers to take them. We are working hard to do that. We have also had some feedback from Ofgem, the regulator, that companies should be taking a much more assertive approach, because we have heard reports that they are really struggling to get people to take a day off work to stay in the house and get the smart meter installed.
We need to sell the benefits and we also have to try to encourage people. Clearly, there is a line there that should not be crossed, because it is not currently a mandatory programme. At some point in the future, we might want to think about the policy framework to ensure that we get as many meters out there as possible, and not just for the individual consumer benefits they would bring—a whole business case around the programme is predicated on as many people as possible having meters. We need to be really careful on communications: sell the benefits and encourage people to get meters, but do not cross that line. That is really important.
Thirdly, you currently pay for metering equipment. It is free at the point of installation, so there should be no charge. Let us be quite clear that nobody will be charged up front, but, like everything else in the energy system, there is an associated cost, whether it is the pipes and wires getting the gas and electricity to users or the metering equipment, right down to the customer service. The key is to make sure that it is done as efficiently as possible. It is a competitive market and it is really important that costs are kept down.
I have a lot of sympathy with the point about direct debits and budgets, but we know from research that people like to spread the cost of their energy over the year. They do not want to see big spikes on their bills—high bills in the winter when they are using loads and nothing in the summer when the gas central heating is off. Smart meters should allow customers to move to an option where they can pay monthly as they go, but for a lot of people direct debit is a budgeting tool and has been very popular.
As for the future, Bill spoke about what he is doing for prepayment meter customers. Some analysis suggests that when everybody has smart meters, up to 50% will not be paying by direct debit, but on a pay-as-you-go basis, as with mobile phones. You will probably see the market and how people engage with their energy supply and pay for it radically changing as we roll this out. That will be good, if there are innovations and benefits. Obviously, we need to make sure that people are adequately protected and know what they are doing from a trading standards perspective.
Finally, on data, a lot of protocols are in place to make sure that we are quite clear that it is customers’ data coming out of the meters. People can opt out of more granular data collection. If you do not want information to be taken daily, you can opt out of that. Right now, it is taken monthly. If the supplier wants to take data from the smart meter every half hour, the customer has to provide consent. A lot of rules have been put in place to ensure that data use and privacy are at the forefront of the programme.
Bill Bullen: A couple of points are relevant to us. First, on customers accepting meters, until the prepay price cap came in we were typically saving customers something like £100 compared with the big six, if they switched to a prepay meter. Whether that counts as being free or not, I do not know, but they were clearly making significant financial savings from switching to smart prepay. That is one of the reasons customers do it, in addition to the other benefits.
Clearly, we are a competitive company. Customers could always refuse to take our product; if they want to stick with a dumb meter, they are entitled to. Something like 80% of the prepay market still has not switched to smart, but 20% has, so more and more are doing so.
Audrey has already answered the point about direct debits. People are going to switch more to pay-as-you-go and be totally in control of the balance. We think that is going to be much more important going forward. Basically, people can take total control over their budget.
Bill Bullen: That is difficult. We are already a long way down the track of delays and cost escalations. Consumers already pay a significant chunk of their bill towards the Government’s smart meter programme.
Bill Bullen: It is going to go up to, I think, £13 per customer from 1 April. That is something like £8 higher than it was a year ago. Once you multiply that by 27 million households, it is a lot of money.
The Government have spent something like more than £1 billion—I think £1.3 billion—on the Data and Communications Company. To put that in perspective, I think the competitive suppliers providing similar services for SMETS 1 generation meters have not spent 10% of that money. They are already out there working, and have been since 2013, so I think there are some real issues.
Clearly, consumers have already seen massive delays and are being stopped from getting the benefits of smart meters because of the Government programme. One of my key concerns, as I said earlier on, is how we will be able to carry on in business over the next couple of years, because of some of the intricate rules about what type of meters we can install when.
We desperately need a lot more flexibility to carry on rolling out smart prepayment meters without any kind of significant hiatus. It is not in the consumer’s interest to have a hiatus, and it is certainly not in the interest of the economy generally to have potentially a lot of qualified meter installers, vans, and warehouses, but no ability to install meters. That is a big problem.
Those problems are with us right now and we have to solve them very soon, because the sheer logistics of managing supply chains—not only ours, but the supply chain to the meter manufacturer, all the component purchases and so on, which stretch out a year in advance—mean that we are already right up against the buffers of maintaining a smooth roll-out programme, given that the SMETS 1 end date is currently stated to be in July next year. That is a really big issue. We are heading at the moment for a massive hiatus in the roll-out of smart meters.
Audrey Gallacher: It would be a huge mistake to underestimate the size of the challenge here with the smart meter roll-out. It is a massive logistical infrastructure programme—53 million meters—so it will be tough. As Bill said, we have already seen some issues around delays and costs overrunning. There is an impact assessment out there—a business case that says there is a net benefit to customers of nearly £6 billion. It is critical that we protect that business case, regardless of how difficult it becomes.
It may well be that the Department for Business, Energy and Industrial Strategy should look at a re-run of that against what we are seeing currently—a new impact assessment to ensure that the benefits case is still alive. There is also a lot of engagement with the Government and energy suppliers on the programme, because we are all working on it together to get it done. You could argue, though, that we might want to see a wee bit more of that. Is there more that we could do to understand what constitutes best practice, within competition rules obviously, and make sure that everybody is doing it as best they possibly can?
Audrey Gallacher: I am suggesting a re-run of what we have done. One analysis was done in 2014; the most recent one is from 2016. Going into next year, it is important that we understand that that benefits case remains intact. Also, we are here today to discuss whether we have to change the regulatory framework to make sure that those benefits are delivered, around the nature of the programme being opt-in versus opt-out, the cost control over the DCC, and the transparency across the control on those costs. There are many things that we need to keep under tight scrutiny.
Bill Bullen: I do not think it is really feasible to re-run the cost-benefit analysis simply because of time. Everybody understands a lot more about smart meters now—the logistics, the costs and the benefits. I think that businesses are in a much better place to just get on and do the job, rather than have another round of consultations wondering what we are going to do. That would soak up most of the next 12 months if we were not careful—a critical time for delivering this benefit to consumers. I differ with Audrey on that point.
Bill Bullen: I would not agree with that.
Bill Bullen: No. There is a set of commercial arrangements around rolling out smart meters. As I say, different suppliers have chosen to engage or not in that. All I can say is that we have built business from scratch that has now got—
Bill Bullen: They are merely providing a funding arrangement to provide the capital, so that suppliers can get meters installed without absorbing that massive hit on their cash flow, or having to charge customers for it. Nobody wants to charge the customer for it, so the meter asset provider will simply provide that capital and then rent that meter to whoever the supplier is over the course of that meter’s life.
Secondly, with the accent on rural areas throughout the UK, I take it that the installers and those who provide the meters are in constant contact with those who provide broadband, wi-fi or the signal to make the system work.
Audrey Gallacher: On the point about consumer awareness, the industry funds an independent communications and marketing campaign—Smart Energy GB—who I think are coming along later today to speak to you. I do not want to steal their thunder. They will give you all sorts of information on what they are doing to ensure that consumers are aware of the smart meter programme and, more importantly, are interested and ready to take one.
My organisation, Energy UK, provides the secretariat, the governance around the performance management framework of that company, so we ensure that we set it sufficiently stretching targets so that it goes out and generates the interest. Over the past year we have done a lot of work with it to try to tighten up those targets to ensure that that messaging is aligned with what we need in terms of customers being ready to accept smart meters.
I think there is probably a role for everybody to play. I would argue that I would like to see more of the Minister promoting the smart meter programme. I think it is movement in this kind of mass roll-out stage, if we can get the Government and the regulator and everybody behind it to really sell the benefits of this. Because smart meters are a great thing for customers and for the future of the energy system.
Your other point was about the system. People coming later today will have much more information about this than I do. The Data Communications Company runs the contracts for the service providers who provide the communication around the smart meter infrastructure, so there are three areas. I think—you can put me right—that those are cellular in the central and south, and a mesh type of communication arrangement in the north of Scotland. There will be challenges getting full penetration there to get the wide area network, which is what the communications hub is called. So there is a lot of work going on to ensure that we do that.
Bill Bullen: I repeat what I said earlier. We are certainly not seeing any problem with engagement of consumers. Consumers are taking up this product. We are getting probably 5,000-plus sets of meters installed every week ourselves. So, we are definitely not seeing any push-back from consumers.
In terms of the technology and some of the difficulties that there will be, mobile phone networks are not 100%, unfortunately. I do again call for a bit of flexibility in terms of the actual technology that supply businesses are allowed to use, because there may just be local spots, whether rural or urban areas, where you simply cannot get a decent enough signal. There will be problems but, at the moment, I really do not think we have enough flexibility in the programme to address every particular case. It is going to be a problem.
Examination of Witnesses
Angus Flett and Rob Salter-Church gave evidence.
Rob Salter-Church: Good morning. My name is Rob Salter-Church. I am a partner in the consumers and competition division at Ofgem, and I have responsibility for our work on smart metering.
Angus Flett: Good morning. My name is Angus Flett. I am the CEO of DCC.
Rob Salter-Church: I might first explain the role of Ofgem and the Government in the roll-out, because that sets out the context for answering that question. To be clear, the roll-out of smart metering is Government policy. The Government have powers, and one of the parts of the Bill we are considering today is to extend their power to put in place the licence arrangements around smart metering. Ofgem’s role is to oversee suppliers and DCC compliance with the policy framework that the Government have put in place.
We are hugely supportive of smart metering, and we think it has real potential to improve consumers’ outcomes. Through regular engagement with suppliers, we are overseeing their compliance with their licence obligations. We do that through regular bilateral engagements, gathering significant information from suppliers and working in partnership with Citizens Advice and the energy ombudsman to gather information about consumers’ experience of smart metering.
We use the data we gather to hold suppliers to account, challenge them and make sure they are doing what they are required to do in terms of installing smart metering—adhering to their roll-out plans and, perhaps more importantly, delivering a good-quality installation, providing energy-efficiency advice to consumers when they do that and making sure consumers are aware of how they can realise the benefits of smart metering.
We have a range of tools in our toolkit that we can use to secure supplier compliance. Ultimately, if we feel that a supplier is not doing what they need to do to stick to the rules and make the programme a success, we can take enforcement action against them—a process that enables us to levy a fine against that organisation if it is failing to meet what is required of them.
Rob Salter-Church: There is a whole range of benefits that consumers—including vulnerable consumers and those on prepayment meters—can get. One of the key ways in which consumers can benefit from smart meters is through being in control and having access to real-time information about their energy usage and what it is costing them. Many people, including vulnerable people, are often worried about getting an unexpected bill—having a bill shock that they are unable to meet—and falling into debt. One of the great things about smart meters is that they give real-time information so people are in control and can manage their energy usage to prevent those kinds of issues from arising.
Another benefit that will accrue to all people, but may well have particular relevance for more vulnerable customers, is the end to estimated billing. They will know exactly what they are being billed and will be able to make sure they are not being over-billed by their supplier.
The last thing I will say is about prepayment meters. Smart metering has the potential to absolutely transform the realities of energy for prepayment customers. People will no longer have to go out in the rain to go down to the shop to put credit on their meter; they will be able to very simply and easily top up the meter when they need to. The functionality also enables suppliers to help customers manage their energy usage. For example, rather than running out of credit overnight, the smart meter technology allows the supplier to offer services to customers that enable them to have a small amount of energy to ensure that the heating and lights are still on in the morning. Those kind of quality of service benefits are huge, and they should accrue to customers through the point at which they get a meter installed.
Rob Salter-Church: Are you referring to the smart meter installation code of practice?
Rob Salter-Church: That is correct. Suppliers have a licence obligation to have that code of practice.
Rob Salter-Church: It is very troubling when we hear things like that, because, as the Committee knows, that is not the case. We are clear to suppliers that they need to try very hard to explain the benefits of smart meters. I struggle to see why someone would not want a smart meter, given the benefits that they offer to consumers. Suppliers do need to be clear that if a customer does not want one, they do not have to have one.
Rob Salter-Church: That is right. We gather data on a regular basis on suppliers’ compliance with the code of practice. If we saw a systematic problem, then we would take action against a supplier.
Rob Salter-Church: The first thing I would do is to reiterate what I said earlier: we expect suppliers to be very clear that there is no compulsion on consumers to have a smart meter. We are driving suppliers to be as clear as they can on what the benefits are, so that customers want to have a smart meter.
In answer to your point about trading standards, we engage with a range of organisations, including Citizen’s Advice, and we do from time to time talk to trading standards to gather information about where there are potential licence breaches. We would take action. I do not believe that I have had a discussion with trading standards, but I can check whether there has been one between the organisations and write in, if that is helpful.
We can all appreciate that there are benefits to smart meters, but can you understand those real concerns of consumers? In addition, there is the fact that the idea of a smart meter has been sold as something free, when it is clearly not.
Rob Salter-Church: Absolutely. I understand that certain consumers would have concerns. What the Government have done in designing a regulatory framework—and what we do in enforcing that regulatory framework—is very important in making sure that the protections are in place and that suppliers adhere to them in order to protect consumers. You referred to data access and security: there is a framework in place, referred to earlier by Audrey, around protections for consumers to make sure that if they do not want to give their data to suppliers, they do not have to. Those rules are important, to give consumers confidence in having a smart meter to make sure that they are in control.
Rob Salter-Church: Yes, I believe they are. Suppliers have clear obligations. What the smart metering installation code of practice does is require those to be explained. There is a quarterly survey that suppliers have to undertake to check compliance with the smart metering installation code of practice. That gathers data to check whether suppliers are indeed being clear to their customers in explaining what options they have got around giving access to data. I believe that that is happening in practice.
Rob Salter-Church: The powers are solely around smart metering. They are an extension of the Government’s existing powers in relation to smart metering and, then, the special administration regime for the DCC.
Rob Salter-Church: No. We are wholly supportive of the Government taking these powers to ensure an orderly conclusion to the programme.
Angus Flett: The financial governance I have makes it highly unlikely that the special administration will be required. The way I am structured is that I invoice my customers and they are required, under licence conditions, to pay me within five days. I also have the facility to take a month’s worth of my invoicing as a credit balance, so I carry cash.
The way I invoice my suppliers is between 20 and 30 days. I also have a £5 million keep well deed from a shareholder and a guaranteed bond of £10 million that I can draw down on. The special administration is set up so that, in the highly unlikely event that we became insolvent, it could administrate and keep the lights on until another organisation could be found to take us over. The costs of that administration can be recovered back on my customer base. So it is a sensible measure, although highly unlikely to be required.
Rob Salter-Church: The 2020 target for completing the roll-out as set by Government was always going to be a challenge, and it remains a challenge, as was said earlier. One of the things Ofgem has done is put in place a framework where we require suppliers to submit to us a plan for the roll-out, setting themselves annual targets that we can enforce against if they do not meet those targets.
We scrutinise the plans that we see from suppliers; if they say, “We will install x number of meters per year”, we do not just take it for granted that that is going to happen. We require them to show us what that will mean for the installer capacity that you might need. What does that mean in terms of the contracts that you are going to have to sign to buy meters, and so on? We scrutinise that to give confidence that the suppliers have got arrangements in place to make their plans deliverable.
The information you are referring to that we publish is our conclusions, having looked across the piece at some of the biggest risks to the programme, which suppliers must remain focused, laser-like, on managing. Indeed, getting hold of enough installers is one of those issues.
Suppliers’ plans for 2017 are broadly on track for meeting their installation targets at the end of this year. A couple of suppliers are slightly behind, but not significantly so. What that tells me is that, yes, there is a real challenge to get to ’20, but suppliers are pretty much on track with the plans that they have set themselves for how they will meet their obligations.
Rob Salter-Church: I would describe them as risks that need to be managed as opposed to problems. On the specifics of installers, some of the tactics of suppliers are to think about their recruitment pipelines, and the Government are involved in work with the relevant national skills academy to ensure that training programmes are in place to develop more installers. The reason why we highlighted that as a risk is that we are expecting suppliers to take more and more action to keep managing it. It will be an ongoing risk throughout the whole programme.
Rob Salter-Church: There are challenges to installing smart meters both in rural areas and in urban areas—equal but different sets of challenges that the suppliers may face. It is not necessarily a given that suppliers would automatically choose to prioritise urban areas for installations ahead of more rural areas.
Rob Salter-Church: I am not saying it is wrong; I am saying that it is not necessarily the case that rural areas will always be delayed because they are more difficult and challenging. There will be a range of challenges that suppliers encounter. The way that the Government have designed the roll-out policy is supplier-driven or supplier-led, and if certain constraints were imposed on suppliers to install smart meters in certain populations ahead of others, that might add cost and complexity and, overall, become a worse deal for GB consumers.
One of the things that we are doing to ensure that rural communities are not left behind is in relation to DCC’s communication networks. DCC is already required to deliver a network that will cover 99.75% of the GB population. It is also required to look continually at how it can extend the reach of its network to get ever closer to 100%, to minimise the chances that anyone is left behind. DCC periodically has to report to us on the progress it is making to ensure that its network is as comprehensive as possible. I would like to think that over time, as technology develops and costs come down, there will be more and more efficient ways for DCC to extend its network to ensure that all consumers can have the benefits of smart metering.
Rob Salter-Church: That might be a question for Angus, in terms of the roll-out and build-out of the network, and where and when it will be reaching different communities in the country.
Angus Flett: We use two technologies, north and south. In the south it is a cellular technology, and that is an established network. In the north it is a radio technology, which gives a higher percentage coverage, particularly for the geographical aspects of Scotland and some aspects of rural areas. You are correct in that the high percentage coverage does not get rolled out until the last part of the programme. However, we have been working with our customers to see if we could speed that up for particular geographic areas. We are also working with Alt HAN, an alternative organisation set up by the Government, to look at that last 1% or 2% and the technologies we could deploy to resolve that. One of the technologies we use is called meshing, which effectively picks up the signal from one house where it is strong and allows that to repeat. So we are reasonably comfortable and confident that we can deliver the coverage footage.
Rob Salter-Church: Suppliers have clear obligations in terms of what they have to explain to their customers. It really, really matters to us that customers get clear information about smart metering—indeed about everything—from their suppliers. It is important that they treat their customers fairly.
In relation to smart metering, suppliers work with the Smart Energy GB organisation to produce common materials and FAQs to make sure that there is clear information for consumers. That information is produced and the suppliers are working to pass that out to individual consumers. There would be potential unintended consequences if either Ofgem or the Government decided that we knew exactly how to speak to customers individually—every single one—and set out very prescriptive rules that suppliers had to follow to the letter. We place clear obligations on suppliers on what they explain to customers. They have clear licence obligations to ensure that they always treat their customers fairly. Suppliers have a programme of work going on, working through Smart Energy GB on common FAQs and information that can be shared with consumers, and they have to do that in a clear way that really engages customers and makes them understand the benefits of smart metering.
Rob Salter-Church: We have a range of tools if we see problems with licence compliance, including ultimately running an enforcement action and imposing fines. We have not had to use our enforcement powers in relation to smart metering as yet.
The roll-out is also an issue. We have touched on the fact that it is obviously delayed. Is it going to happen or is it another initiative that is going to cost an awful lot of money? Who is going to end up paying for that? Will it ultimately be the consumer once again? Those are my two main points, before I get on my high horse.
Rob Salter-Church: You talked about having a traditional prepayment meter and some of the poor quality of service that results from that. One of the most important things that the smart meter roll-out will do is end the prepayment disadvantage, in terms of both cost and quality of service. That is absolutely key and there are real benefits for consumers.
You talked a little bit about privacy. There are very clear rules in place for suppliers; they must obtain customers’ consent if they want to have any data from them.
Rob Salter-Church: That is a good challenge. We gather regular information by engaging with Citizens Advice, which is a good source of information if people are raising concerns or complaints about their smart metering installation. As I mentioned before, we also gather information from the smart metering installation code of practice survey. We gather information from a wide range of sources. If we thought there was a systematic problem and suppliers were not being clear to customers about information consent, we would absolutely do something about it and use all the powers that we have to crack down on those suppliers and make sure that consumers are protected. I hope I can reassure you that we have both the practical arrangements in place to get the data and the will to do something if we see that there is a real problem.
Angus Flett: I can reassure the Committee that DCC is fully operational and ready to scale. If we look at the facts, DCC was born in 2013. Our first release was due in December 2015 and was actually delivered in October 2016—the following year. The latest release, which was due in November, we delivered bang on track. There are subsequent releases to unlock functionality such as prepaid and so on.
We run regular “ready to scale” forums with our suppliers and customers. The forecasts that are coming through from my main customers indicate that I will be doing well over 200,000 installs a week next year, and that number is growing. In fact, one of my main customers issued a press release saying that it was the first to go live with the installation of SMETS 2. We are also putting in place incremental measures to ensure that, as we cut over from SMETS 1 to SMETS 2, we carry a buffer stock of communications hubs so that my customers can ramp down their old stock and ramp up the new stock. We are confident that we can deliver against the scaling requirements.
Angus Flett: Testing is essential. This is a UK national infrastructure project and we will not go live without full integrated testing. We use a range of emulators to simulate testing. As I said, the evidence I have from the main customers that are driving installations is that we are on track. The volumetric forecasts that they are delivering to me indicate well over 200,000 installs a week. I do not have concerns in that sense.
Angus Flett: There are just over 250 out there at the moment.
Angus Flett: Two hundred and fifty installs.
Angus Flett: At this stage it is an acceptable number, as each of my main customers gears up its volumetric installs. As I said, if the forecasts that come through—
Adjourned till this day at Two o’clock.
Contains Parliamentary information licensed under the Open Parliament Licence v3.0.