PARLIAMENTARY DEBATE
Flammable Cladding Removal - 14 July 2020 (Commons/Commons Chamber)
Debate Detail
There are still an estimated 60,000 people living in homes with similar ACM cladding on the outside of their buildings, and many more living in buildings that are dangerous. According to the Fire Brigades Union, some 500,000 people are at risk from living in unsafe housing across the UK. Each night, they are going to bed, knowing that, if their building caught fire, it would spread quickly because of the flammable cladding, and they know, too, that their chances of survival are seriously lessened in that context. They know that progress to remove that cladding has been slow and has slowed further because of the pandemic. I have called for this debate because I think that it is vital that Ministers step up and make sure that the cladding and other dangerous materials on those blocks are removed as a matter of urgency.
It took a year for the Government to agree to fund the removal of ACM cladding from high-rise social housing blocks and then two years for private blocks, and three years for other commitments to be made. That happened because of the actions of campaign groups such as Grenfell United, the UK Cladding Action Group and Inside Housing, as well as Members of Parliament and charities and housing organisations. It is not good enough that the Government have been forced kicking and screaming into doing these things, rather than taking responsibility, as was promised at the time of the fire. Although £1.6 billion of Government funding is welcome, they estimate themselves that between £3 billion and £3.5 billion is required to make all buildings safe.
Residents feel like prisoners in their homes. They cannot sell or remortgage their flats, and the external wall fire review and EWS1 form process is not sufficient, is costly and takes too long. They are trapped.
The Government’s latest release in June revealed that 155 of the 455 high-rise buildings identified as covered in ACM by the Ministry of Housing, Communities and Local Government have had cladding removed, but another 300 are yet to be remediated. That is a lot of housing that needs to be remediated.
The Government have repeatedly missed their own deadlines of 2019 for social sector blocks and June 2020 for private sector blocks. Despite the major fires in 2019 at student accommodation blocks with high-pressure laminate cladding in Bolton and at the flats in the constituency of my right hon. Friend the Member for Barking (Dame Margaret Hodge), where flames quickly spread up the timber balconies, progress has been painfully slow, and the coronavirus pandemic has hampered progress even more, as I have said.
The Housing, Communities and Local Government Committee found that the £1 billion building safety fund would pay for only 600 of the buildings, when actually we need billions to ensure that all buildings in the country that are in this unsafe state can be addressed.
We are finding that the small-print requirements that housing associations and local authorities are having to pass are excluding them from accessing funding. They are then having to pass on the bill to the leaseholders, as hon. Members have said. Our leaseholder constituents cannot afford tens of thousands of pounds when right now their jobs are on the line, when they are struggling to make ends meet and struggling to feed their kids. Middle-class families are having to rely on food banks in this crisis, and now they are worried about what will happen to their housing.
My own local authority has 49 ACM-clad high-rise blocks, which is one of the highest figures in the country. I have had representations from many of my constituents over the past few years. It has been years now, and the leaseholders have had to pay for the fire safety wardens. They were originally told that this would take a few months, but it has been years. They are worried about their safety, and there is no end in sight with the work being completed. It has been done for some blocks but not for others.
A number of people have been told that the housing providers will not be able to provide the fire service reports. I hope that the Minister can give me some clarity on the need for transparency here, because whether they are private developers who own the freehold or housing associations, they should provide the fire safety reports. Without them, it is difficult for our residents to know how much they will have to pay if there is no Government funding, or to make plans for their future.
One of my constituents said:
“I spend all day stressed at the thought of losing my home. At night I am anxious about the possibility of fire. I haven’t slept well for months and do not see any end in the situation. I am trapped. I cannot sell and I am not allowed to rent the flat out. I am forced to stay here. It now feels like a prison.”
Another said: “I feel suicidal.” Another said:
“I can’t sleep from worry. Because of covid-19 I could lose my job any day now, and when that happens I won’t be able to pay my mortgage or sell my flat. Because of the cladding, I will end up losing everything I have worked for. It’s a big worry that affects my mental health and sleep. It is not fair for the Government to allow housing associations and construction companies to sell us unsafe houses, and we are now getting punished for their mistakes.”
Housing providers have an obligation to ensure that they are doing everything they can to make buildings safe, but the Government have the ultimate responsibility to ensure that they have access to the funds needed for them to do so. The Government took a long time before providing the funds and gave private developers and freeholders plenty of time to get their act together, but they have not done so. It is time the Government used their powers to make this happen. Ministers have said repeatedly that private owners of buildings have the responsibility to act, but the Government are shirking their responsibility by leaving it to the good will of building owners—many with complex ownership structures based in other countries, including for tax avoidance purposes—to apply for a limited first come, first served fund or to pay for the works themselves. Many have found cunning ways to avoid paying anything, leaving our constituents high and dry, unable to live safely in their homes. This is unacceptable. It has to stop. Our Government must act and go after those owners. We have said this time and again, and it has not happened.
I call on the Minister to address the following questions. Will he explain what powers he will use to make private developers and freeholders end the delays and remove the cladding? Will he increase the building safety fund to cover the costs of removing cladding and other fire risks to all buildings in that position? Will he provide a clear timeline for remediation that the Government will stick to? What plans does he have for ensuring that upcoming legislation improves fire safety and building regulation? Will he consider primary legislation that goes far enough to prevent another tragedy, as well as increased funding and resources for the fire services to carry out vital preventive inspection work?
Finally, I draw the Minister’s attention to the recommendation of the Housing, Communities and Local Government Committee that the Government should give urgent consideration to the establishment of a new national body whose sole purpose is to purchase the freehold and manage the remediation of buildings with serious fire safety defects. Any residential building where works have not commenced by December 2020 should be subject to a compulsory purchase order. The national body would step in where overburdened local authorities are unable to act. Once remediated, buildings should be converted to commonhold and returned to leaseholders. In my view, that is a reasonable and proportionate way forward if companies do not act. I hope the Minister will consider that suggestion. If he will not, we just need action. If he comes up with another creative way to make things happen to keep our constituents safe, now is the moment to set out his plans, and I hope he will.
After Grenfell, the then Prime Minister said:
“My Government will do whatever it takes to…keep our people safe.”
Three years on, this Government have been found wanting. I implore the Minister and the Government to honour the commitments that were made by his party in government when this tragedy happened. It was a man-made disaster that should have been avoided. We need to learn from that and make sure that we all do everything we can to keep people safe. The Government must honour their commitments and honour those who lost their lives, make the funds available, and create the legal framework and the requirements to make sure that our constituents can live without fear safely in their homes.
We established our building safety programme within days of the Grenfell Tower fire. Its aim remains to ensure that residents of high-rise buildings are safe, now and in the future. Our aim has been clear from the outset: unsafe ACM cladding of the type found on Grenfell Tower and other dangerous cladding must be removed from high-rise residential buildings. It is therefore our priority to ensure that unsafe ACM cladding is removed and replaced swiftly, at no cost to leaseholders.
While many responsible building owners have taken action, some—as the hon. Lady says—have not. Too many building owners and managing agents in the private sector have been too slow in getting remediation work started.
By the end of May, of the 455 identified high-rise buildings with ACM cladding, 209 had either completed remediation or had their ACM cladding systems removed, while a further 86 had started remediation but not yet had ACM cladding removed. However, although there has been progress, there is much more to be done. We are under no illusion about that. For the removal of unsafe ACM cladding, we are aiming for all building owners to have works on site by the end of 2020, with completion of remedial works by the end of 2021. It is a challenge, but one that we are determined to meet.
Even with public funding available, the pace has been much too slow. We recognise that remediation is a complex undertaking and that every building is different; we also understand that building owners do not always have the requisite expertise or experience to advance the work. We have therefore recently appointed Faithful+Gould as specialist construction consultants to help responsible entities to increase capacity and capability, and to support them directly through the remediation process. F+G is currently working with those buildings identified as most at risk of missing the end-of-year date. It is examining project plans and seeking ways to reduce timescales to mobilise projects.
Overall, the Government have set aside £1.6 billion in funding for the remediation of ACM and other types of unsafe cladding from high-rise residential buildings in the private and social housing sectors. We made that money available to support the remediation of unsafe cladding, and a large proportion of that support will protect leaseholders from costs. We recognise that there are wider remediation costs that will need to be met to ensure the safety of existing blocks of flats, but the public funding does not absolve the industry from taking responsibility for any failures that led to unsafe cladding materials being put on those buildings in the first place. We expect developers, investors and building owners who have the means to pay to take responsibility and cover the cost of remediation themselves, without passing on costs to leaseholders.
The Government have committed £600 million to remediate buildings in the public, social and private sectors and speed up the pace of remediation of ACM cladding. In the private sector, although some developers said that they would meet the costs, it became clear that a significant number of building owners could not or would not do so, and therefore funding needed to be made available to enable progress. That is why in May 2019 we announced that £200 million of funding would be available for ACM remediation in private sector buildings, and the fund was opened for applications in September that year. As of May 2020, the Department expects to pay for 94 projects in the private sector where the developer or building owner has not agreed to fund remediation work themselves. The owners of 84 private sector residential buildings have committed to funding the remediation works themselves, with a further 23 self- funded through accepted warranty claims. We are working with a handful of other buildings where a funding route has yet to be agreed. The availability of funding and a direct package of support for building owners means that there can be no excuses for further delays. For those who fail to make acceptable progress, tougher sanctions are coming, first through our Fire Safety Bill, currently before Parliament, and subsequently when our new building safety regime comes into place.
We have always acknowledged that there are materials other than ACM cladding that are of concern. We have been providing advice on their removal to building owners since 2017. The highest priority has been the removal of the type of ACM used on Grenfell Tower because it poses the most severe safety risk, but there are other unsafe cladding materials that must also be removed. That is why in March this year we announced an additional £1 billion of funding for the remediation of unsafe non-ACM cladding in the social and private residential sectors. We expect this funding to be fully committed by the end of March 2021. The new building safety fund will cover high-rise buildings with unsafe non-ACM cladding, such as some types of high-pressure laminate.
The issue of waking watch was raised by the hon. Member for Bethnal Green and Bow and by other hon. and right hon. Members. I know that leaseholders have concerns about costs of interim measures—costs that have been heightened owing to the covid-19 emergency. These interim measures include waking watches. Waking watch is meant to be a short-term tool: it is no substitute for remediation. But the only way to remove the need for interim measures is to remove unsafe cladding as quickly as possible. That is why we are prioritising £1.6 billion of public subsidy for remediation of unsafe cladding. That said, my noble Friend Lord Greenhalgh, the Minister with responsibility for building safety, is investigating what we can do to reduce the cost of waking watch. This includes publishing data on the costs of waking watch to ensure greater transparency on costs. Moreover, the National Fire Chiefs Council is updating its guidance. We have asked the fire protection boards to advise fire and rescue services on how best to operationalise the revised guidance, including looking to measures such as installing building-wide fire alarm systems.
Our landmark building safety Bill, announced in December, will bring the biggest change in our building safety regime for a generation. It will build on the recommendations of Dame Judith Hackitt’s independent review of building regulations and fire safety. It contains provisions to help to remedy the systemic failings that resulted in the Grenfell Tower fire. The new regime will give residents a stronger voice in an improved system of fire safety, overseen by a more effective regulatory framework, including stronger powers to inspect high-rise buildings and sanctions to tackle irresponsible behaviour.
Much progress has been made since the hon. Member secured a similar debate in April last year. We have set aside £1.6 billion of funding to support the issue and resolve it; we have appointed specialist consultants to increase the pace of remediation; and we have introduced the Fire Safety Bill to strengthen enforcement action. But the hard work must continue, and it will.
We will shortly publish the draft building safety Bill, a once-in-a-generation change to the building safety regime that will be instrumental not only in shaping future policy to allow the new regime to prevent fire safety defects from occurring in the first place, but also in ensuring that people are safe and feel safe in their homes. We will continue to work tirelessly to bring about the lasting change we need for the future of building safety and the future of all the people living in towers in this country.
Question put and agreed to.
Contains Parliamentary information licensed under the Open Parliament Licence v3.0.