In politics there is often a sense of déjà vu. Back in April 2012 I led a similar Adjournment debate on proposals to upgrade and electrify the midland main line between Bedford and Sheffield. The line serves the cities of Derby, Leicester, Nottingham and Sheffield, my own constituency of Loughborough, and a number of other growing towns across the east midlands, including Chesterfield, Market Harborough, Corby, Kettering and Wellingborough. Together, those places are home to more than 5 million people and 2.1 million jobs; we believe that they comprise the economic backbone of England.
The east midlands in particular has helped to lead the United Kingdom out of recession, with strong private sector job growth over the past five years. We have huge potential for export-led growth, already accounting for 20% of gross value added. Latest projections from the Office for National Statistics suggest the population of the east midlands will rise by half a million people by 2030 to 5.1 million, which will be the fastest growth outside London and the wider south-east.
The midland main line itself has been a huge success story. As those of us who are frequent travellers on the line know all too well, passenger numbers have increased by 130% in the past 15 years—I can probably say on behalf of colleagues that there are times when it feels like all 130% are on the particular train I have caught from London St Pancras—and a further 30% rise is expected in the next 10 years. Rail freight is also booming, showing a 70% increase since the mid-1990s, but the line has suffered from years of under-investment. It is the only north-south rail route yet to be electrified. It has some of the slowest mainline speeds in the country, meaning that trains are rarely able to go at their top speed.
Some of the rolling stock is more than 40 years old, so I was delighted when in July 2012, the then Secretary of State for Transport announced that the upgrade and electrification scheme, which had been promoted by councils, local enterprise partnerships and business groups in the east midlands and south Yorkshire, was to be delivered in full by 2020. Since then, there has been progress on implementation, but not everything has gone according to plan. The pausing of the electrification elements in 2015 resulted in the demobilisation of a high-skilled technical team within Network Rail, which has taken time to reassemble. The pause also had a considerable financial impact on local companies in the supply chain.
I mentioned the pausing and how it led to the technical team that Network Rail put together being demobilised. The extended completion date of 2023 is not ideal, but the decision of the previous Secretary of State to press ahead gave certainty to passengers, local communities, businesses and investors. I am reassured that the main upgrade measures remain on track to be delivered by 2019, and by recent public statements from Network Rail that work on electrification is also progressing. The reason for holding this debate is that colleagues in the industry tell me that there is no such thing as a committed transport scheme until it is actually built. A number of local interests have contacted me and other Members to say that another pause, or worse, could be in the offing.
The debate gives the Government the opportunity to set the record straight and confirm support for the whole scheme. The economic, environmental and practical arguments for electrification remain as strong as ever. In addition, I draw the Minister’s attention to the impact that any further delay or uncertainty over the electrification of the midland main line would have.
Rolling stock has already been mentioned. As we have heard, the current fleet of high-speed trains is approaching 40 years old and will have to be replaced by 2020. Currently, there is no clear plan for that. While I understand that the Government’s stated preference is to procure new rolling stock through the forthcoming franchise competition, as the new franchise is not planned to commence until July 2018, it is unclear whether that can be achieved. Without certainty over the electrification process, it will be difficult for the private sector to make that investment, unless the Government specify electric-diesel bi-mode rolling stock.
It has been mentioned that the plan for re-letting the east midlands franchise already falls mid-way through electrification and track upgrades, and that the revised completion for electrification to Sheffield already falls mid-way within the next franchise period. Both of those will present significant challenges for the next operator.
HS2 has been mentioned, too. The east midlands has developed a strong local consensus in support of HS2 and a hub station at Toton. Key to unlocking wider connectivity via HS2 is the ability to run so-called “classic compatible services” via the hub station, which will require an electrified midland main line. HS2 Ltd’s recent proposals for serving Sheffield midland station via Chesterfield will also require an electrified railway.
We have also talked about the impact on the local supply chain. Any further delay or uncertainty will fundamentally undermine business confidence in the Government’s ability to deliver major investment. We have also heard about the potential impact on apprenticeships. For our residents and constituents, electric trains offer a quieter, smoother and more reliable passenger experience. They have a positive impact on air quality and thus on people’s health, which is becoming a major issue in many areas along the midland main line.
In conclusion, the midland main line is a major driver of local economic growth and a key asset, as we have heard, for the Government’s midlands engine initiative. The upgrade and electrification scheme was conceived as an integrated package. Only by implementing the whole scheme can the benefits to passengers, freight operators and local businesses be delivered in full. It remains vital that the Government deliver the upgrade and electrification scheme in full by 2023 at the latest. I hope that the Minister will acknowledge the concerns of Members and give his commitment to the whole scheme. We heard the invitation of my hon. Friend the Member for Kettering (Mr Hollobone) for the Minister to agree to facilitate a meeting between himself, the Secretary of State and Members present today.
Let me talk first about why this Government have chosen to invest in our rail network and why we chose to invest in it for the future. We are making journeys better, simpler, faster and more reliable. Most importantly, we want to make transport not just safer, but more sustainable. I thus entirely agree with my right hon. Friend that the investment we are making today will help prepare our country for tomorrow. Our national plan will support jobs, enable business growth and bring our country closer together.
That is why we are supporting a record £70 billion investment in rail, roads, ports and airports, and we are undertaking the biggest rail modernisation since Victorian times. We are ensuring that every part of Britain benefits from a growing economy, and that all those who work hard have the opportunities that they need in order to succeed. As Members have pointed out tonight, the midland main line services provided for passengers today are compromised. The attempt to serve all passengers with inter-city trains means that, as my right hon. Friend has said, long-distance passengers suffer from slow peak journeys, and commuters to London have to board already crowded inter-city trains.
To solve the problem, as we design and build the next franchise, we will create two distinct services, one for commuters from Corby, Kettering and other stations to London and one for long-distance travellers, in order to serve both more effectively. That will significantly reduce journey times from Sheffield and Nottingham to London by reducing the number of stops on those long-distance services, as well as speeding up the trains themselves. On average, the slow Sheffield morning peak services will be reduced by between 20 and 30 minutes to about two hours, and the Nottingham services will be reduced, on average, by between 10 and 20 minutes to about an hour and a half.
It is vital for the first steps of the capacity work to be completed, and I am delighted to say that we are making good progress in delivering that. We will make the whole route between Bedford and Kettering four-track, and the whole route between Kettering and Corby two-track. The stops between Corby, Kettering and other stations and London, mainly used by commuters, would then be served by electric trains up to 12 carriages long.
That proposed approach will be consulted on as part of the upcoming East Midlands franchise competition, ahead of a planned invitation to tender in May 2017. I would greatly welcome engagement and input from Members to help us to achieve the right balance between journey time and connectivity on the route, and I am more than happy to accept the offer from my hon. Friend the Member for Kettering (Mr Hollobone) to meet the Secretary of State and me to discuss such matters further. I look forward particularly to seeing bidders’ innovative proposals to improve services for passengers and other users of the railway, building on the Government’s substantial investment.
We are committed to electrification on the midland main line. We will deliver electrification from London to Kettering and Corby by 2019. Electric train services taking advantage of those improvements will begin as soon as possible after the completion of the infrastructure works, providing passengers with better trains, more seats, and better facilities on board. Those enhancements will provide increased capacity to relieve congestion on the railway.
The move to electric services to Corby will mean that we are able to deliver a third more carriage miles than today across the route. I can also assure Members on both sides of the House that development work is continuing on further electrification of the route to Sheffield and Nottingham. I am keen to ensure that the scheme delivers value for money for the taxpayer, and a better experience for the passenger.
We recognise that this is a challenging programme, with many difficult engineering hurdles to overcome, but we are determined to work with Network Rail to face the challenges and deliver the best possible railway for the people of this country. Work has already started to deliver the programme. If one travels from Corby to Kettering, one can see that the track-doubling and electrification are already in delivery. A major blockade to deliver those enhancements has just finished where work on strengthening bridges and viaducts was successful. Tens of millions of pounds are being spent on the project, which is laying the foundation for the new electric services.
We will remove the long-standing bottleneck at Derby station in 2018, to speed up midland main line, CrossCountry and freight services. We are improving the line speed between Derby and Sheffield, and at both Leicester and Market Harborough. Platform-lengthening work is going on throughout the network to enable longer trains to run. Overall, the programme will nearly double capacity into London in the morning peak, giving passengers a significantly quieter and smoother ride as well as a shorter journey. I believe that there will be a much better service for both current and future passengers.
“we will have a deliverable and affordable set of improvements.”—[Official Report, 16 September 2015; Vol. 599, c. 330WH.]
When the project was unpaused, the chairman of Network Rail assured us that
“the line north of Kettering to Derby/Nottingham and Sheffield can be electrified in stages by 2023.”
Will this Minister commit to that timescale?
Let me stress again that I recognise what my right hon. Friend the Member for Loughborough has said about the ageing rolling stock on the midland main line, but I remind her that although the HSTs are 40 years old, about three quarters of the inter-city fleet is made up of the Meridians, which are only 10 years old and are performing relatively well. Through the franchise competition, we will look to improve the rolling stock on the long-distance inter-city services. Across the country, rail passengers today are seeing the fruits of this approach to improving rail services. We need only look at the new stations at Manchester Victoria, Birmingham New Street and elsewhere across the country to see that.
My right hon. Friend also referred to freight, which I just want to touch on because it is very important to consider this in the context of the midland main line. The movement of freight is vital to the economic prosperity of the regions that export and manufacture. Indeed, a number of upgrade projects across the region, such as on the great northern great eastern line, have been specifically designed and delivered to improve freight paths for manufacturers in the region. Investment in transport across the UK—
Our enhancements are already being delivered, and we will be running an additional passenger train per hour on the midland main line into St Pancras as well as opening up additional capacity for crucial freight services. This will provide much needed extra capacity for passenger services on the stops from Kettering and Corby and other stations into London used by regular commuters into London, as well as allowing a reduction in journey times for passengers travelling from Sheffield and Nottingham via Derby and Loughborough into London.
I always welcome fact-filled debates and submissions from Members on both sides of the House. I thank them for their attention today, and I look forward to discussing this in more detail in the weeks to come.