PARLIAMENTARY DEBATE
Onshore Wind Farm Cables - 16 January 2024 (Commons/Commons Chamber)

Debate Detail

Contributions from Graham Stuart, are highlighted with a yellow border.
Con
Duncan Baker
North Norfolk
3. What recent assessment the Government have made of the environmental impact of onshore wind farm cables.
Graham Stuart
The Minister for Energy Security and Net Zero
The environmental impact of onshore windfarm cables is assessed through the consenting process. Minimising potential environmental impacts of new infrastructure is a Government priority. We are committed to ensuring that new electricity network projects mitigate environmental impacts at every opportunity.
Duncan Baker
Although I am a huge supporter of offshore wind, there is no doubt that the trenching through my beautiful countryside is not without its own set of problems. Flooding, agricultural run-off and pollution have all been hugely exacerbated since the summer with what has happened in North Norfolk. What measures do we really have to force wind companies to clean up and repair the countryside after the damage they cause when they trench through it?
Graham Stuart
I thank my hon. Friend for his question and for persistently raising these issues to make sure that we get the transmission infrastructure that we need, but in a way that has the minimum negative impact on his constituents and others. I will follow up his question today by looking specifically at the regime, making sure that the companies concerned not only go through all the correct permissioning ahead of time, but are properly followed up to ensure that they deliver it in a way that does not leave the problems that he has itemised.
Dame Eleanor Laing
Madam Deputy Speaker
I call the shadow Minister.
Lab
  11:58:50
Dr Alan Whitehead
Southampton, Test
On 28 November, I asked the Minister how many planning applications for onshore wind had been lodged in England since the alleged loosening of planning restrictions on onshore wind in September. The answer then was zero. Even now that the policy has had more time to bed down, the answer, I am afraid, is still zero, and I predict that it will be zero the next time we meet. In September last year, the Secretary of State said that the changes made in September

“will help speed up the delivery of onshore wind projects”.

Does the Minister think that the Government have succeeded?
Graham Stuart
I thank the hon. Gentleman for his question. As he will be aware, in the last contracts for difference round, a great deal of onshore wind was successfully brought forward and it still constitutes the largest single form of renewable energy in the United Kingdom—the Under-Secretary of State for Energy Security and Net Zero, my hon. Friend the Member for West Aberdeenshire and Kincardine (Andrew Bowie) will correct me if I have got that wrong. I share with the hon. Gentleman a frustration in making sure that we see that pulled forward, so that we see more projects in England as well as in the rest of the UK.
  12:00:01
Dr Whitehead
I am glad the Minister is frustrated about the complete failure of this alleged policy turnaround, but I am frustrated because if we had not had the absurd ban in the first place, the onshore wind development that would have taken place would have saved each family £180 on their energy bills. All Labour is suggesting is that onshore wind is treated like any other development. How long will it be before the Minister accepts the reality and concludes that he needs to go back and properly repeal the ban?
Graham Stuart
I thank the hon. Gentleman for his question and his personal commitment to this area, but he knows as well as anyone the parlous performance of the previous Government, which his right hon. Friend the Member for Doncaster North (Edward Miliband) was a leading figure in. Less than 7% of our electricity came from renewables as recently as 2010. It is this Government that have led the world after a flatlining in carbon emissions from our electricity sector under Labour. We have seen renewables grow and, by October, we will see coal entirely removed from our mix.
  12:00:45
Dame Eleanor Laing
Madam Deputy Speaker
I call the SNP spokesman.
SNP
  12:01:19
Dave Doogan
Angus
New renewable energy generation demands new transmission infrastructure. This Government have been asleep at the wheel for 14 years, showing zero pace, ambition or grip in delivering that energy infrastructure, and that is why bills are so high. Nevertheless, we are where we are. Will the Minister confirm to the House for the record what National Grid has said: that UK Government policy is that when constructing new transmission infrastructure, overhead lines are the starting position?
  12:04:39
Graham Stuart
I thank the hon. Gentleman for his question. Of course, we have been moving at pace. We have had the Winser review and the connections plan. In the autumn statement and, indeed, the Prime Minister’s speech in September, there was so much to drive forward and change the transmission infrastructure, including halving the 14-year timeline to seven years. We are working flat out.

It should be noted that the reason overhead lines are preferred is the cost of undergrounding. Not only is it vastly disruptive, as my hon. Friend the Member for North Norfolk (Duncan Baker) said; either undergrounding or offshore is five to ten times more expensive than having overhead infrastructure, and sometimes even more than that. That is why it is the starting presumption. We want to power Britain from Britain and in a low-cost manner, so that when we get to the 2030s and we have decarbonised our electricity system, we have a low-cost electricity system, while ensuring that we install the infrastructure in a way that is friendly and supportive to communities.

Contains Parliamentary information licensed under the Open Parliament Licence v3.0.