ROADWORKS SUMMARY
Brow Street, ROCHDALE, OL11 2JZ
Introduction
View current and future planned roadworks and road closures for Brow Street, OL11 2JZ and the surrounding area.
Our roadwork details are constantly updated and reflect the current situation and we offer both a map view and a listing. We also highlight the major and significant roadworks occuring near to you help you avoid the worst of the delays to your journey.
The roadworks shown below show all current and proposed works during the next 90 days and historical data is recorded since July 2020.
Please note that we re-publish this data and cannot provide any additional information pertaining to a roadwork event. If you require more information, please contact the organisation carrying out the work.
Data are provided by the Department for Transport.
Have we helped today?
If we have helped you today, please consider buying us a quick coffee to keep us going!
Major Roadworks near to Brow Street, ROCHDALE, OL11 2JZ
Details of major roadworks, currently in progress or starting soon and resulting in road closures and/or traffic signal management for Brow Street are shown here covering a 5 mile radius. See further down for details of all roadworks in your area.
30 Apr 2025
Oldham Metropolitan Borough Council are carrying out Highway repair and maintenance works on London Road, Oldham.
These works are categorised as Major.
Two-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 1 July 2020 at 14:30 and could run through until 30 April 2025. The works will impact the carriageway only.
This roadwork event was last updated by Oldham Metropolitan Borough Council on 7 May 2024 at 07:37.
31 Jan 2025
Oldham Metropolitan Borough Council are carrying out Section 50 on Southgate Street, Oldham.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 4 January 2022 at 09:31 and could run through until 31 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Oldham Metropolitan Borough Council on 8 Aug 2023 at 10:14.
24 Dec 2024
Oldham Metropolitan Borough Council are carrying out Section 50 on Ascroft Street, Oldham.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 20 March 2023 at 09:00 and could run through until 24 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Oldham Metropolitan Borough Council on 17 Jul 2023 at 09:47.
4 Jun 2023 and 29 Jun 2025
Electricity North West (NorWeb) are proposing to carry out Utility repair and maintenance works on Gipsy Lane, Castleton North, Rochdale.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 4 June 2023 and could run through until 29 June 2025. The works will impact the footway and carriageway.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by Electricity North West (NorWeb) on 3 Apr 2023 at 14:30.
4 Jun 2023 and 29 Jun 2025
Electricity North West (NorWeb) are proposing to carry out Utility repair and maintenance works on Manchester Road, Sparthbottoms & College Bank, Rochdale.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 4 June 2023 and could run through until 29 June 2025. The works will impact the footway and carriageway.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by Electricity North West (NorWeb) on 3 Apr 2023 at 06:59.
20 Dec 2024
Rochdale Borough Council are carrying out Utility asset works on Over Town Lane, Norden North, Rochdale.
These works are categorised as Major.
The works started on 2 April 2024 at 07:30 and could run through until 20 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Rochdale Borough Council on 2 Dec 2024 at 10:47.
30 Apr 2025
Oldham Metropolitan Borough Council are carrying out Highway repair and maintenance works on Priest Hill, Oldham.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 15 April 2024 at 09:00 and could run through until 30 April 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Oldham Metropolitan Borough Council on 12 Nov 2024 at 14:44.
30 Apr 2025
Oldham Metropolitan Borough Council are carrying out Highway repair and maintenance works on Fountain Street, Oldham.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 15 April 2024 at 09:00 and could run through until 30 April 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Oldham Metropolitan Borough Council on 12 Nov 2024 at 14:42.
30 Apr 2025
Oldham Metropolitan Borough Council are carrying out Highway repair and maintenance works on New Radcliffe Street, Oldham.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 15 April 2024 at 09:00 and could run through until 30 April 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Oldham Metropolitan Borough Council on 12 Nov 2024 at 14:43.
15 Nov 2025
Oldham Metropolitan Borough Council are carrying out Highway repair and maintenance works on Market Place, Oldham.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 13 May 2024 at 09:30 and could run through until 15 November 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Oldham Metropolitan Borough Council on 12 Nov 2024 at 14:44.
23 Sep 2024 and 17 Jan 2025
Rochdale Borough Council are proposing to carry out Works for road purposes on St Marys Gate, Cronkeyshaw, Rochdale.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 23 September 2024 and could run through until 17 January 2025. The works will impact the footway, carriageway, verge, cycleway and footpath.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by Rochdale Borough Council on 6 Aug 2024 at 10:10.
27 Mar 2025
Rochdale Borough Council are carrying out Works for road purposes on St Marys Gate, Cronkeyshaw, Rochdale.
These works are categorised as Major.
A lane is closed for some or all of the period and could cause delays to journeys.
The works started on 23 September 2024 at 09:00 and could run through until 27 March 2025. The works will impact the footway, carriageway, verge, cycleway and footpath.
This roadwork event was last updated by Rochdale Borough Council on 16 Oct 2024 at 14:28.
30 Sep 2024 and 31 Jan 2025
Oldham Metropolitan Borough Council were proposing to carry out Highway repair and maintenance works on High Street, Oldham.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 30 September 2024 and run through until 31 January 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Oldham Metropolitan Borough Council on 11 Oct 2024 at 10:43.
30 Sep 2024 and 31 Jan 2025
Oldham Metropolitan Borough Council were proposing to carry out Highway repair and maintenance works on Yorkshire Street, Oldham.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 30 September 2024 and run through until 31 January 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Oldham Metropolitan Borough Council on 11 Oct 2024 at 10:42.
30 Sep 2024 and 31 Jan 2025
Oldham Metropolitan Borough Council were proposing to carry out Highway repair and maintenance works on Church Terrace, Oldham.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 30 September 2024 and run through until 31 January 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Oldham Metropolitan Borough Council on 11 Oct 2024 at 10:43.
30 Sep 2024 and 31 Jan 2025
Oldham Metropolitan Borough Council were proposing to carry out Highway repair and maintenance works on Church Street, Oldham.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 30 September 2024 and run through until 31 January 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Oldham Metropolitan Borough Council on 11 Oct 2024 at 10:42.
30 Sep 2024 and 31 Jan 2025
Oldham Metropolitan Borough Council were proposing to carry out Highway repair and maintenance works on Curzon Street, Oldham.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 30 September 2024 and run through until 31 January 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Oldham Metropolitan Borough Council on 11 Oct 2024 at 10:43.
20 Dec 2024
Cadent Gas are carrying out Utility asset works on Croft Head Drive, Milnrow North & Firgrove, Milnrow.
These works are categorised as Major.
Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 15 October 2024 at 10:30 and could run through until 20 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 3 Dec 2024 at 14:40.
Friday
Cadent Gas are proposing to carry out Utility asset works on Ashworth Street, Oldham.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 21 October 2024 and could run through until 13 December 2024. The works will impact the footway and carriageway.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by Cadent Gas on 19 Jul 2024 at 14:18.
Friday
Cadent Gas are proposing to carry out Utility asset works on Sandy Lane, Royton.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 6 November 2024 and could run through until 13 December 2024. The works will impact the footway and carriageway.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by Cadent Gas on 4 Jul 2024 at 14:15.
11 Nov 2024 and 1 Sep 2025
United Utilities Water (formerly North West Water) are proposing to carry out Utility asset works on Sheepfoot Lane, Oldham.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 1 September 2025. The works will impact the carriageway only.
This roadwork event was last updated by United Utilities Water (formerly North West Water) on 6 Aug 2024 at 14:42.
Friday
Electricity North West (NorWeb) are carrying out Utility asset works on Woodbine Street East, Turf Hill & Lower Place & Buersil, Rochdale.
These works are categorised as Major.
Two-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 11 November 2024 at 10:05 and could run through until 13 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 3 Dec 2024 at 08:16.
Today
Electricity North West (NorWeb) are proposing to carry out Utility asset works on Woodbine Street East, Turf Hill & Lower Place & Buersil, Rochdale.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 14 November 2024 and could run through until 11 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 8 Nov 2024 at 13:18.
20 Dec 2024
Cadent Gas are carrying out Utility asset works on Grafton Street, Newbold, Rochdale.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 18 November 2024 at 09:10 and could run through until 20 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 18 Nov 2024 at 10:33.
20 Dec 2024
Cadent Gas are carrying out Utility asset works on Channing Street, Newbold, Rochdale.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 18 November 2024 at 09:10 and could run through until 20 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 18 Nov 2024 at 10:32.
Friday
Cadent Gas are carrying out Utility asset works on Moss Bridge Road, Newbold, Rochdale.
These works are categorised as Major.
Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 27 November 2024 at 08:33 and could run through until 13 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 3 Dec 2024 at 08:48.
Friday
Cadent Gas are carrying out Utility asset works on Crawford Street, Newbold, Rochdale.
These works are categorised as Major.
Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 28 November 2024 at 13:00 and could run through until 13 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 3 Dec 2024 at 08:11.
27 Nov and 20 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Rochdale Lane, Royton.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 27 November 2024 and could run through until 20 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 29 Aug 2024 at 13:48.
28 Nov 2024 and 9 Jan 2025
Oldham Metropolitan Borough Council are proposing to carry out Highway repair and maintenance works on Vale Drive, Oldham.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 28 November 2024 and could run through until 9 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Oldham Metropolitan Borough Council on 25 Nov 2024 at 13:42.
9 Jan 2025
Oldham Metropolitan Borough Council are carrying out Highway repair and maintenance works on Vale Drive, Oldham.
These works are categorised as Major.
Two-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 28 November 2024 at 09:30 and could run through until 9 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Oldham Metropolitan Borough Council on 2 Dec 2024 at 13:41.
2 and 20 Dec 2024
Electricity North West (NorWeb) are proposing to carry out Remedial works on Langley Lane, Langley North And West, Middleton.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 20 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 13 Nov 2024 at 12:41.
2 and 20 Dec 2024
Electricity North West (NorWeb) were proposing to carry out Remedial works on Langley Lane, Langley North And West, Middleton.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 2 December 2024 and run through until 20 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 28 Nov 2024 at 16:17.
2 and 20 Dec 2024
Electricity North West (NorWeb) are proposing to carry out Remedial works on Langley Lane, Langley North And West, Middleton.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 20 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 29 Nov 2024 at 07:25.
2 and 20 Dec 2024
Electricity North West (NorWeb) were proposing to carry out Remedial works on Langley Lane, Langley North And West, Middleton.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 2 December 2024 and run through until 20 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 13 Nov 2024 at 10:56.
2 and 20 Dec 2024
Electricity North West (NorWeb) were proposing to carry out Remedial works on Langley Lane, Langley North And West, Middleton.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 2 December 2024 and run through until 20 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 28 Nov 2024 at 16:14.
2 and 20 Dec 2024
Electricity North West (NorWeb) are proposing to carry out Remedial works on Langley Lane, Langley North And West, Middleton.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 20 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 29 Nov 2024 at 07:25.
2 and 20 Dec 2024
Electricity North West (NorWeb) were proposing to carry out Remedial works on Langley Lane, Langley North And West, Middleton.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 2 December 2024 and run through until 20 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 22 Nov 2024 at 10:41.
2 and 20 Dec 2024
Electricity North West (NorWeb) were proposing to carry out Remedial works on Langley Lane, Langley North And West, Middleton.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 2 December 2024 and run through until 20 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 13 Nov 2024 at 11:01.
2 and 20 Dec 2024
Electricity North West (NorWeb) are proposing to carry out Remedial works on Langley Lane, Langley North And West, Middleton.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 20 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 13 Nov 2024 at 12:55.
2 and 20 Dec 2024
Electricity North West (NorWeb) were proposing to carry out Remedial works on Langley Lane, Langley North And West, Middleton.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 2 December 2024 and run through until 20 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 28 Nov 2024 at 16:18.
2 and 20 Dec 2024
Electricity North West (NorWeb) are proposing to carry out Remedial works on Langley Lane, Langley North And West, Middleton.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 20 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 29 Nov 2024 at 07:24.
2 and 20 Dec 2024
Rochdale Borough Council are proposing to carry out Section 50 on Tower Street, Heywood West And Central, Heywood.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 20 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Rochdale Borough Council on 22 Oct 2024 at 11:34.
Monday
Rochdale Borough Council are carrying out Highway improvement works on Osborne Street, Deeplish, Rochdale.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 3 December 2024 at 15:00 and could run through until 16 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Rochdale Borough Council on 4 Dec 2024 at 08:14.
Tuesday
Cadent Gas are carrying out Utility repair and maintenance works on Shaw Road, Oldham.
Two-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 4 December 2024 at 10:45 and could run through until 17 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Cadent Gas on 6 Dec 2024 at 12:28.
4 and 24 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Rochdale Lane, Royton.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 4 December 2024 and could run through until 24 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 1 Oct 2024 at 17:07.
4 and 20 Dec 2024
Electricity North West (NorWeb) are proposing to carry out New service connection on James Street, Littleborough West, Littleborough.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 4 December 2024 and could run through until 20 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 21 Oct 2024 at 15:21.
Tomorrow
Electricity North West (NorWeb) are proposing to carry out New service connection on Hillcrest Road, Castleton South, Rochdale.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 December 2024 and could run through until 12 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 11 Oct 2024 at 08:49.
Today
Electricity North West (NorWeb) were proposing to carry out New service connection on Chadderton Way, Oldham.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 9 December 2024 and run through until 11 December 2024. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 17 Sep 2024 at 18:32.
Friday
Rochdale Borough Council are proposing to carry out Remedial works on Queens Park Road, Back O Th Moss & Ashworth, Heywood.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 9 December 2024 and could run through until 13 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Rochdale Borough Council on 12 Nov 2024 at 09:43.
20 Dec 2024
Rochdale Borough Council are carrying out Highway improvement works on Osborne Street, Deeplish, Rochdale.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 9 December 2024 at 07:30 and could run through until 20 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Rochdale Borough Council on 9 Dec 2024 at 09:10.
9 Dec 2024 and 19 Jan 2025
Electricity North West (NorWeb) were proposing to carry out Utility asset works on Woodbine Street East, Turf Hill & Lower Place & Buersil, Rochdale.
These works were categorised as Major.
Two-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 9 December 2024 and run through until 19 January 2025. The works were due to impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 6 Nov 2024 at 10:10.
10 Dec 2024 and 3 Jan 2025
Cadent Gas are proposing to carry out Utility asset works on Grafton Street, Newbold, Rochdale.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 10 December 2024 and could run through until 3 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 15 Oct 2024 at 10:07.
10 Dec 2024 and 17 Jan 2025
Cadent Gas are proposing to carry out Utility asset works on Channing Street, Newbold, Rochdale.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 10 December 2024 and could run through until 17 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 15 Oct 2024 at 10:05.
16 and 19 Dec 2024
Cadent Gas are proposing to carry out New service connection on Retiro Street, Oldham.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 16 December 2024 and could run through until 19 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 20 Sep 2024 at 14:40.
16 and 19 Dec 2024
Cadent Gas are proposing to carry out New service connection on Retiro Street, Oldham.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 16 December 2024 and could run through until 19 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 23 Sep 2024 at 09:58.
25 Dec 2024 and 3 Jan 2025
Electricity North West (NorWeb) are proposing to carry out New service connection on Oak Hill, Littleborough West, Littleborough.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 25 December 2024 and could run through until 3 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 7 Oct 2024 at 14:51.
30 Dec 2024 and 10 Jan 2025
Rochdale Borough Council are proposing to carry out Highway improvement works on Castlemere Street, Milkstone, Rochdale.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 30 December 2024 and could run through until 10 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Rochdale Borough Council on 18 Oct 2024 at 10:21.
30 Dec 2024 and 10 Jan 2025
Rochdale Borough Council are proposing to carry out Highway improvement works on Mere Street, Milkstone, Rochdale.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 30 December 2024 and could run through until 10 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Rochdale Borough Council on 2 Oct 2024 at 15:12.
1 and 15 Jan 2025
Rochdale Borough Council are proposing to carry out Highway improvement works on Ashfield Road, Deeplish, Rochdale.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 1 January 2025 and could run through until 15 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Rochdale Borough Council on 1 Oct 2024 at 15:10.
1 and 15 Jan 2025
Rochdale Borough Council are proposing to carry out Highway improvement works on Kensington Street, Deeplish, Rochdale.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 1 January 2025 and could run through until 15 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Rochdale Borough Council on 1 Oct 2024 at 15:13.
1 and 15 Jan 2025
Rochdale Borough Council are proposing to carry out Highway improvement works on Ashfield Road, Deeplish, Rochdale.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 1 January 2025 and could run through until 15 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Rochdale Borough Council on 1 Oct 2024 at 15:11.
1 and 15 Jan 2025
Rochdale Borough Council are proposing to carry out Highway improvement works on Osborne Street, Deeplish, Rochdale.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 1 January 2025 and could run through until 15 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Rochdale Borough Council on 1 Oct 2024 at 15:18.
1 and 15 Jan 2025
Rochdale Borough Council are proposing to carry out Highway improvement works on Osborne Street, Deeplish, Rochdale.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 1 January 2025 and could run through until 15 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Rochdale Borough Council on 29 Oct 2024 at 08:25.
1 and 24 Jan 2025
Cadent Gas are proposing to carry out Utility asset works on Silver Hill, Milnrow North & Firgrove, Milnrow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 1 January 2025 and could run through until 24 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 4 Oct 2024 at 09:58.
2 and 31 Jan 2025
Cadent Gas are proposing to carry out Utility asset works on Rochdale Road, Royton.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 2 January 2025 and could run through until 31 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 3 Dec 2024 at 10:13.
2 and 31 Jan 2025
Cadent Gas are proposing to carry out Utility asset works on Rochdale Road, Royton.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 2 January 2025 and could run through until 31 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 4 Dec 2024 at 14:26.
2 Jan and 22 Feb 2025
Cadent Gas are proposing to carry out Utility asset works on George Street, Shaw.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 2 January 2025 and could run through until 22 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 13 Nov 2024 at 16:03.
2 and 18 Jan 2025
Cadent Gas are proposing to carry out Utility asset works on Cook Terrace, Belfield & Howarth Cross, Rochdale.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 2 January 2025 and could run through until 18 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 7 Oct 2024 at 09:45.
2 and 19 Jan 2025
Electricity North West (NorWeb) were proposing to carry out New service connection on Featherstall Road, Littleborough East, Littleborough.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 2 January 2025 and run through until 19 January 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 5 Nov 2024 at 13:50.
6 Jan and 14 Feb 2025
Oldham Metropolitan Borough Council are proposing to carry out Highway repair and maintenance works on Oldham Way, Oldham.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 14 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Oldham Metropolitan Borough Council on 29 Oct 2024 at 08:29.
6 Jan and 25 Apr 2025
Rochdale Borough Council were proposing to carry out Highway improvement works on Starkey Street, Back O Th Moss & Ashworth, Heywood.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 6 January 2025 and run through until 25 April 2025. The works were due to impact the footway, carriageway and verge.
This roadwork event was last updated by Rochdale Borough Council on 8 Nov 2024 at 13:25.
6 Jan and 25 Apr 2025
Rochdale Borough Council were proposing to carry out Highway improvement works on West Starkey Street, Back O Th Moss & Ashworth, Heywood.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 6 January 2025 and run through until 25 April 2025. The works were due to impact the footway, carriageway and verge.
This roadwork event was last updated by Rochdale Borough Council on 8 Nov 2024 at 13:26.
6 Jan and 25 Apr 2025
Rochdale Borough Council were proposing to carry out Highway improvement works on Bamford Road, Back O Th Moss & Ashworth, Heywood.
These works were categorised as Major.
Two-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 6 January 2025 and run through until 25 April 2025. The works were due to impact the footway, carriageway and verge.
This roadwork event was last updated by Rochdale Borough Council on 8 Nov 2024 at 13:23.
6 and 31 Jan 2025
Electricity North West (NorWeb) were proposing to carry out Utility asset works on Gipsy Lane, Castleton North, Rochdale.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 6 January 2025 and run through until 31 January 2025. The works were due to impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 10 Dec 2024 at 12:47.
6 and 19 Jan 2025
Rochdale Borough Council are proposing to carry out Highway improvement works on Kensington Street, Deeplish, Rochdale.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 19 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Rochdale Borough Council on 11 Dec 2024 at 08:59.
6 and 19 Jan 2025
Rochdale Borough Council are proposing to carry out Highway improvement works on Osborne Street, Deeplish, Rochdale.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 19 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Rochdale Borough Council on 11 Dec 2024 at 09:00.
6 Jan and 11 Apr 2025
Electricity North West (NorWeb) are proposing to carry out Utility asset works on Kingsway, Newbold, Rochdale.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 11 April 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 24 Sep 2024 at 15:07.
6 Jan and 11 Apr 2025
Electricity North West (NorWeb) were proposing to carry out Utility asset works on Albert Royds Street, Belfield & Howarth Cross, Rochdale.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 6 January 2025 and run through until 11 April 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 10 Oct 2024 at 08:12.
6 Jan and 11 Apr 2025
Electricity North West (NorWeb) were proposing to carry out Utility asset works on Albert Royds Street, Belfield & Howarth Cross, Rochdale.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 6 January 2025 and run through until 11 April 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 24 Sep 2024 at 13:35.
6 Jan and 11 Apr 2025
Electricity North West (NorWeb) were proposing to carry out Utility asset works on Albert Royds Street, Belfield & Howarth Cross, Rochdale.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 6 January 2025 and run through until 11 April 2025. The works were due to impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 18 Nov 2024 at 11:53.
6 Jan and 11 Apr 2025
Electricity North West (NorWeb) were proposing to carry out Utility repair and maintenance works on Halifax Road, Belfield & Howarth Cross, Rochdale.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 6 January 2025 and run through until 11 April 2025. The works were due to impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 18 Nov 2024 at 11:54.
6 Jan and 30 Mar 2025
Rochdale Borough Council are proposing to carry out Highway improvement works on Shawclough Road, Shawclough, Rochdale.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 30 March 2025. The works will impact the footway, carriageway, verge, cycleway and footpath.
This roadwork event was last updated by Rochdale Borough Council on 6 Nov 2024 at 13:35.
6 Jan and 27 Apr 2025
Rochdale Borough Council are proposing to carry out Highway improvement works on Shawclough Road, Shawclough, Rochdale.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 27 April 2025. The works will impact the footway, carriageway, verge, cycleway and footpath.
This roadwork event was last updated by Rochdale Borough Council on 26 Nov 2024 at 14:01.
6 Jan and 11 Apr 2025
Electricity North West (NorWeb) were proposing to carry out Utility asset works on Halifax Road, Wardle, Rochdale.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 6 January 2025 and run through until 11 April 2025. The works were due to impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 18 Nov 2024 at 11:54.
6 Jan and 11 Apr 2025
Electricity North West (NorWeb) were proposing to carry out Utility asset works on New Road, Littleborough East, Littleborough.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 6 January 2025 and run through until 11 April 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 18 Nov 2024 at 11:54.
6 Jan and 11 Apr 2025
Electricity North West (NorWeb) are proposing to carry out Utility asset works on William Street, Littleborough East, Littleborough.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 11 April 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 25 Sep 2024 at 10:21.
6 and 26 Jan 2025
Electricity North West (NorWeb) are proposing to carry out New service connection on Featherstall Road, Littleborough East, Littleborough.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 26 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 5 Dec 2024 at 14:04.
8 and 21 Jan 2025
United Utilities Water (formerly North West Water) are proposing to carry out Remedial works on Chapel Gate, Milnrow North & Firgrove, Milnrow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 8 January 2025 and could run through until 21 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by United Utilities Water (formerly North West Water) on 8 Oct 2024 at 11:39.
13 and 17 Jan 2025
Cadent Gas are proposing to carry out Disconnection or alteration of supply on Beal Lane, Shaw.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 13 January 2025 and could run through until 17 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Cadent Gas on 9 Oct 2024 at 15:00.
13 and 17 Jan 2025
Cadent Gas are proposing to carry out Disconnection or alteration of supply on Beal Lane, Shaw.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 13 January 2025 and could run through until 17 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Cadent Gas on 11 Oct 2024 at 08:37.
14 and 16 Jan 2025
United Utilities Water (formerly North West Water) were proposing to carry out New service connection on Hillcrest Road, Castleton South, Rochdale.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 14 January 2025 and run through until 16 January 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by United Utilities Water (formerly North West Water) on 14 Nov 2024 at 14:16.
14 and 27 Jan 2025
Electricity North West (NorWeb) are proposing to carry out New service connection on William Street, Littleborough East, Littleborough.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 14 January 2025 and could run through until 27 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 25 Nov 2024 at 12:21.
15 Jan and 14 Feb 2025
Cadent Gas are proposing to carry out Utility asset works on The Meadows, Alkrington East, Middleton.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 15 January 2025 and could run through until 14 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 9 Sep 2024 at 11:26.
15 Jan and 14 Feb 2025
Cadent Gas are proposing to carry out Utility asset works on The Meadows, Alkrington East, Middleton.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 15 January 2025 and could run through until 14 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 10 Dec 2024 at 12:01.
15 and 31 Jan 2025
Cadent Gas are proposing to carry out Utility asset works on Kingsway, Alkrington West, Middleton.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 15 January 2025 and could run through until 31 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 10 Dec 2024 at 12:00.
16 Jan and 4 Feb 2025
Oldham Metropolitan Borough Council are proposing to carry out Highway repair and maintenance works on Dingle Avenue, Shaw.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 16 January 2025 and could run through until 4 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Oldham Metropolitan Borough Council on 18 Nov 2024 at 10:01.
16 Jan and 4 Feb 2025
Oldham Metropolitan Borough Council are proposing to carry out Highway repair and maintenance works on Dingle Avenue, Shaw.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 16 January 2025 and could run through until 4 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Oldham Metropolitan Borough Council on 18 Nov 2024 at 10:13.
16 Jan and 4 Feb 2025
Oldham Metropolitan Borough Council are proposing to carry out Highway repair and maintenance works on Shore Avenue, Shaw.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 16 January 2025 and could run through until 4 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Oldham Metropolitan Borough Council on 18 Nov 2024 at 10:00.
16 Jan and 4 Feb 2025
Oldham Metropolitan Borough Council are proposing to carry out Highway repair and maintenance works on Shore Avenue, Shaw.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 16 January 2025 and could run through until 4 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Oldham Metropolitan Borough Council on 18 Nov 2024 at 10:16.
16 and 22 Jan 2025
Electricity North West (NorWeb) are proposing to carry out New service connection on Oak Hill, Littleborough West, Littleborough.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 16 January 2025 and could run through until 22 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 26 Nov 2024 at 14:39.
17 and 30 Jan 2025
Electricity North West (NorWeb) were proposing to carry out New service connection on William Street, Littleborough East, Littleborough.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 17 January 2025 and run through until 30 January 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 25 Nov 2024 at 12:50.
17 and 30 Jan 2025
Electricity North West (NorWeb) are proposing to carry out New service connection on William Street, Littleborough East, Littleborough.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 January 2025 and could run through until 30 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 26 Nov 2024 at 14:41.
17 and 30 Jan 2025
Electricity North West (NorWeb) are proposing to carry out New service connection on William Street, Littleborough East, Littleborough.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 January 2025 and could run through until 30 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 9 Dec 2024 at 15:12.
18 Jan and 7 Mar 2025
Electricity North West (NorWeb) are proposing to carry out Utility asset works on Kingsway, Newbold, Rochdale.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 18 January 2025 and could run through until 7 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 29 Nov 2024 at 10:42.
18 Jan and 7 Mar 2025
Electricity North West (NorWeb) are proposing to carry out Utility asset works on Kingsway, Newbold, Rochdale.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 18 January 2025 and could run through until 7 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 3 Dec 2024 at 14:46.
18 Jan and 7 Mar 2025
Electricity North West (NorWeb) are proposing to carry out Utility asset works on Kingsway, Newbold, Rochdale.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 18 January 2025 and could run through until 7 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 11 Dec 2024 at 08:44.
20 Jan and 11 May 2025
Rochdale Borough Council are proposing to carry out Highway improvement works on Oldham Road, Middleton East, Middleton.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 20 January 2025 and could run through until 11 May 2025. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by Rochdale Borough Council on 22 Nov 2024 at 09:32.
20 Jan and 2 Feb 2025
Rochdale Borough Council are proposing to carry out Highway improvement works on Ashfield Road, Deeplish, Rochdale.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 20 January 2025 and could run through until 2 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Rochdale Borough Council on 3 Dec 2024 at 13:12.
20 Jan and 2 Feb 2025
Rochdale Borough Council are proposing to carry out Highway improvement works on Ashfield Road, Deeplish, Rochdale.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 20 January 2025 and could run through until 2 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Rochdale Borough Council on 3 Dec 2024 at 13:12.
20 Jan and 7 Feb 2025
Electricity North West (NorWeb) are proposing to carry out Utility asset works on Albert Royds Street, Belfield & Howarth Cross, Rochdale.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 20 January 2025 and could run through until 7 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 16 Sep 2024 at 08:47.
20 and 26 Jan 2025
Electricity North West (NorWeb) are proposing to carry out New service connection on James Street, Littleborough West, Littleborough.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 20 January 2025 and could run through until 26 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 4 Nov 2024 at 16:46.
20 and 23 Jan 2025
Electricity North West (NorWeb) were proposing to carry out New service connection on James Street, Littleborough West, Littleborough.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 20 January 2025 and run through until 23 January 2025. The works were due to impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 6 Nov 2024 at 10:49.
20 and 23 Jan 2025
Electricity North West (NorWeb) are proposing to carry out New service connection on James Street, Littleborough West, Littleborough.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 20 January 2025 and could run through until 23 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 6 Nov 2024 at 12:10.
24 Jan and 14 Mar 2025
Cadent Gas are proposing to carry out Utility asset works on George Street, Shaw.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 24 January 2025 and could run through until 14 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 25 Oct 2024 at 11:31.
27 Jan and 16 Feb 2025
Electricity North West (NorWeb) are proposing to carry out Diversionary works on Railway Street, Hopwood West, Heywood.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 27 January 2025 and could run through until 16 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 11 Dec 2024 at 08:40.
27 Jan and 16 Feb 2025
Electricity North West (NorWeb) are proposing to carry out Diversionary works on Railway Street, Hopwood West, Heywood.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 27 January 2025 and could run through until 16 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 11 Dec 2024 at 09:55.
27 Jan and 11 Feb 2025
Telefonica UK are proposing to carry out Utility asset works on Ruskin Road, Kirkholt, Rochdale.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 27 January 2025 and could run through until 11 February 2025. The works will impact the carriageway and verge.
This roadwork event was last updated by Telefonica UK on 26 Nov 2024 at 14:39.
27 Jan and 11 Feb 2025
Telefonica UK were proposing to carry out Utility asset works on Ruskin Road, Kirkholt, Rochdale.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 27 January 2025 and run through until 11 February 2025. The works were due to impact the carriageway and verge.
This roadwork event was last updated by Telefonica UK on 4 Dec 2024 at 15:14.
27 Jan and 14 Feb 2025
Electricity North West (NorWeb) are proposing to carry out New service connection on Old Road, Wardle, Rochdale.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 27 January 2025 and could run through until 14 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 21 Oct 2024 at 15:19.
27 Jan and 14 Feb 2025
Electricity North West (NorWeb) were proposing to carry out New service connection on Old Road, Wardle, Rochdale.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 27 January 2025 and run through until 14 February 2025. The works were due to impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 6 Nov 2024 at 11:18.
27 Jan and 2 Feb 2025
Electricity North West (NorWeb) are proposing to carry out New service connection on Paddock Head, Littleborough East, Littleborough.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 27 January 2025 and could run through until 2 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 6 Nov 2024 at 12:12.
29 Jan and 28 Feb 2025
Cadent Gas are proposing to carry out Utility asset works on The Meadows, Alkrington East, Middleton.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 29 January 2025 and could run through until 28 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 14 Oct 2024 at 11:51.
29 Jan and 14 Feb 2025
Cadent Gas are proposing to carry out Utility asset works on Kingsway, Alkrington West, Middleton.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 29 January 2025 and could run through until 14 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 18 Oct 2024 at 13:16.
29 Jan and 28 Feb 2025
Cadent Gas are proposing to carry out Utility asset works on Flake Lane, Royton.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 29 January 2025 and could run through until 28 February 2025. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by Cadent Gas on 24 Sep 2024 at 16:22.
29 Jan and 20 Feb 2025
Cadent Gas are proposing to carry out Utility asset works on Marlfield Road, Shaw.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 29 January 2025 and could run through until 20 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 19 Nov 2024 at 13:19.
29 Jan and 20 Feb 2025
Cadent Gas are proposing to carry out Utility asset works on Rochdale Road, Shaw.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 29 January 2025 and could run through until 20 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 19 Nov 2024 at 13:18.
5 and 21 Feb 2025
Cadent Gas are proposing to carry out Utility asset works on Calf Hey Road, Shaw.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 5 February 2025 and could run through until 21 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 6 Nov 2024 at 11:27.
12 Feb and 7 Mar 2025
Cadent Gas are proposing to carry out Utility asset works on Buckstones Road, Shaw.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 12 February 2025 and could run through until 7 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 6 Nov 2024 at 11:26.
13 Feb and 14 Mar 2025
Cadent Gas are proposing to carry out Utility asset works on Rochdale Road, Royton.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 13 February 2025 and could run through until 14 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 15 Nov 2024 at 15:40.
19 Feb and 14 Mar 2025
Cadent Gas are proposing to carry out Utility asset works on Church Road, Shaw.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 19 February 2025 and could run through until 14 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 26 Nov 2024 at 14:48.
19 Feb and 14 Mar 2025
Cadent Gas are proposing to carry out Utility asset works on Church Road, Shaw.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 19 February 2025 and could run through until 14 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 9 Dec 2024 at 10:10.
19 Feb and 7 Mar 2025
Cadent Gas are proposing to carry out Utility asset works on Buckstones Road, Shaw.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 19 February 2025 and could run through until 7 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 6 Nov 2024 at 11:21.
20 Feb and 7 Mar 2025
Cadent Gas are proposing to carry out Utility asset works on Church Road, Shaw.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 20 February 2025 and could run through until 7 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 27 Nov 2024 at 16:08.
24 Feb and 20 Apr 2025
Electricity North West (NorWeb) are proposing to carry out Diversionary works on Manchester Road, Hopwood East & Birch, Heywood.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 24 February 2025 and could run through until 20 April 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 11 Dec 2024 at 08:40.
24 Feb and 20 Apr 2025
Electricity North West (NorWeb) are proposing to carry out Diversionary works on Manchester Road, Hopwood East & Birch, Heywood.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 24 February 2025 and could run through until 20 April 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 11 Dec 2024 at 10:05.
26 Feb and 14 Mar 2025
Cadent Gas are proposing to carry out Utility asset works on Marlfield Road, Shaw.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 26 February 2025 and could run through until 14 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 4 Oct 2024 at 15:03.
26 Feb and 20 Mar 2025
Cadent Gas are proposing to carry out Utility asset works on Rochdale Road, Shaw.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 26 February 2025 and could run through until 20 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 4 Oct 2024 at 14:57.
26 Feb and 20 Mar 2025
Cadent Gas are proposing to carry out Utility asset works on Rochdale Road, Shaw.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 26 February 2025 and could run through until 20 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 8 Oct 2024 at 08:50.
5 Mar and 11 Apr 2025
Cadent Gas are proposing to carry out Utility asset works on Sandy Lane, Royton.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 5 March 2025 and could run through until 11 April 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 3 Oct 2024 at 12:20.
10 and 12 Mar 2025
Cadent Gas are proposing to carry out New service connection on Bow Lane, Heywood West And Central, Heywood.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 10 March 2025 and could run through until 12 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 11 Dec 2024 at 08:39.
Roadworks Map near to Brow Street, ROCHDALE, OL11 2JZ
- Any red lines indicate the extent of the works.
- Clicking on the map will re-centre to the selected point.
- Within 1 mile, all roadworks are displayed.
- Within 2-3 miles, standard, urgent and major roadworks are displayed.
- For 3-5 miles, only major roadworks are shown.
- The higher the marker number, the further away the roadworks are from the centre of the postcode.
- Where traffic camera videos or images are shown, no historical versions are retained. Once a new image or video becomes available it overwrites the previous version.
Roadworks Listing near to Brow Street, ROCHDALE, OL11 2JZ (33 Events)
(Scheduled Dates)
(miles)
(Scheduled: 11 Dec 2024 - 16 Dec 2024)
(Scheduled: 10 Dec 2024 - 13 Dec 2024)
(Scheduled: 11 Dec 2024 - 13 Dec 2024)
(Scheduled: 5 Dec 2024 - 11 Dec 2024)
(Scheduled: 5 Dec 2024 - 13 Dec 2024)
(Scheduled: 9 Dec 2024 - 20 Dec 2024)
Contains public sector information licensed under the Open Government Licence v3.0.