ROADWORK EVENT SUMMARY
Moor Lane, Wilmslow between 21 and 25 Nov 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Moor Lane, Wilmslow

Nexfibre Networks Limited are carrying out Utility asset works on Moor Lane, Wilmslow.

The works started on 21 November 2024 at 11:36 and could run through until 25 November 2024. The works will impact the footway and verge.

The information for these works was last updated by Nexfibre Networks Limited on 21 November 2024 at 11:37.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Moor Lane, Wilmslow

Works Details

WORKS IN PROGRESS
Nexfibre Networks Limited logo
These works are handled by:
Nexfibre Networks Limited
Cheshire East Council logo
Local Authority:
Cheshire East Council
Works Reference N7150NBU700230AD04-01
Permit Number 01
Place Name Moor Lane
Wilmslow
Proposed Start 21 Nov 2024
Proposed End 25 Nov 2024
Actual Start 21 Nov 2024 11:36
Actual End
Traffic Management Some carriageway incursion
Impact Footway, Verge
Coordinates
Lat, Lon
53.318522
-2.257343
Last Updated 21 Nov 2024 11:37
Works History for Activity N7150NBU700230AD04-01 (Moor Lane, Wilmslow)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
14 Nov 2024
15:45
Permit Submitted
21 Nov 2024
00:00
25 Nov 2024
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
14 Nov 2024
15:46
Permit Alteration Granted
21 Nov 2024
00:00
25 Nov 2024
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
14 Nov 2024
16:34
Permit Alteration Granted
21 Nov 2024
00:00
25 Nov 2024
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
15 Nov 2024
08:35
Permit Granted
21 Nov 2024
00:00
25 Nov 2024
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
15 Nov 2024
08:35
Permit Alteration Granted
21 Nov 2024
00:00
25 Nov 2024
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
21 Nov 2024
11:37
Work Started
21 Nov 2024
00:00
25 Nov 2024
00:00
21 Nov 2024
11:36
In Progress

Works Permits for Moor Lane, Wilmslow

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.