ROADWORK EVENT SUMMARY
Eighton Lodge Roundabout, Eighton Banks, Gateshead between 7 and 11 Jan 2025
Works Description for Eighton Lodge Roundabout, Eighton Banks, Gateshead
This is a PAA (Provisional Advance Authorisation) permit that has been granted before final details of an activity have been finalised. A full permit will be required before activities can commence.
National Highways are proposing to carry out Works for road purposes on Eighton Lodge Roundabout, Eighton Banks, Gateshead.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 7 January 2025 and could run through until 11 January 2025. The works will impact the carriageway only.
The information for these works was last updated by National Highways on 11 December 2024 at 15:32.
Works Map for Eighton Lodge Roundabout, Eighton Banks, Gateshead
Works Details
National Highways
Gateshead Metropolitan Borough Council
Works Reference | FN41462897927 |
Permit Number | 01 |
Place Name |
Eighton Lodge Roundabout Eighton Banks Gateshead |
Proposed Start | 7 Jan 2025 |
Proposed End | 11 Jan 2025 |
Actual Start | |
Actual End |
Traffic Management | Road closure |
Impact | Carriageway |
Coordinates Lat, Lon |
54.911581 -1.583298 |
Last Updated | 11 Dec 2024 15:32 |
In the event that you have an issue with these works, please contact National Highways, the works operator in the first instance if details are available, as they are most likely to be able to assist and resolve the issue more quickly.
Should the issue remain, you may also contact the local authority, Gateshead Metropolitan Borough Council that authorised the works.
It would assist the organisations if you quote the work reference number of FN41462897927.
Works Permits for Eighton Lodge Roundabout, Eighton Banks, Gateshead
For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.
Applies to all permits.
For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.
Applies to all permits.
For the activities hereby permitted, it is a condition of this permit that, as agreed, the following [extended] working hours will apply at this site from [start time] until [end time] on weekdays and [start time] and [end time] on (Saturday/Sunday/Bank Holiday).
For the activities hereby permitted, it is a condition of this permit that activities shall only take place when [insert road name] or [insert description of the relevant section of the road] is closed to traffic.
For the activities hereby permitted, it is a condition of this permit that works, or the relevant part of the activity, shall only take place when the following traffic management is deployed by use of x (where x determines type of control i.e. portable signals, stop/go boards etc.)
For the activities hereby permitted, it is a condition of this permit that the works comprised in [specified part A/B] of the activities hereby permitted shall be subject to and shall occur only when the following traffic management measures are in place [or as attached in schedule.].
For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.
Applies to all permits.
Proposed Work Dates
Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.
Problems with roadworks?
On rare occasions, issues may occur during or after the completion of roadworks, such as:
- Poor reinstatement of the footpath or the carriageway.
- Rubbish and mess remaining after the works have completed.
- Traffic management issues during the works.
- Equipment left behind after the works have completed.
- Any other issues or disruption that the works may be causing.
In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.
In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.
Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.
Contains public sector information licensed under the Open Government Licence v3.0.