ROADWORKS SUMMARY
Bridge Street, WARWICK, CV35 9QP
Introduction
View current and future planned roadworks and road closures for Bridge Street, CV35 9QP and the surrounding area.
Our roadwork details are constantly updated and reflect the current situation and we offer both a map view and a listing. We also highlight the major and significant roadworks occuring near to you help you avoid the worst of the delays to your journey.
The roadworks shown below show all current and proposed works during the next 90 days and historical data is recorded since July 2020.
Please note that we re-publish this data and cannot provide any additional information pertaining to a roadwork event. If you require more information, please contact the organisation carrying out the work.
Data are provided by the Department for Transport.
Have we helped today?
If we have helped you today, please consider buying us a quick coffee to keep us going!
Major Roadworks near to Bridge Street, WARWICK, CV35 9QP
Details of major roadworks, currently in progress or starting soon and resulting in road closures and/or traffic signal management for Bridge Street are shown here covering a 5 mile radius. See further down for details of all roadworks in your area.
4 Nov and 21 Dec 2024
Warwickshire County Council are proposing to carry out Section 50 on Harbury Lane, Bishops Tachbrook.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 4 November 2024 and could run through until 21 December 2024. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by Warwickshire County Council on 8 Oct 2024 at 12:30.
11 Nov 2024 and 15 Jan 2025
Cadent Gas are proposing to carry out Utility asset works on Sand Barn Lane, Black Hill, Snitterfield.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 15 January 2025. The works will impact the footway, carriageway and footpath.
This roadwork event was last updated by Cadent Gas on 5 Sep 2024 at 12:20.
17 Nov 2024 and 31 Jul 2025
Warwickshire County Council were proposing to carry out Highway improvement works on Banbury Road, Bishops Tachbrook.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 17 November 2024 and run through until 31 July 2025. The works were due to impact the carriageway and verge.
This roadwork event was last updated by Warwickshire County Council on 22 Oct 2024 at 11:22.
18 Nov 2024 and 9 May 2025
Warwickshire County Council were proposing to carry out Highway improvement works on Europa Way, Warwick.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 18 November 2024 and run through until 9 May 2025. The works were due to impact the carriageway and verge.
This roadwork event was last updated by Warwickshire County Council on 16 Oct 2024 at 08:30.
18 Nov 2024 and 5 Jan 2025
Warwickshire County Council are proposing to carry out Section 50 on Harbury Lane, Bishops Tachbrook.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 18 November 2024 and could run through until 5 January 2025. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by Warwickshire County Council on 14 Nov 2024 at 09:06.
13 Dec 2024
Cadent Gas are carrying out Utility asset works on Snitterfield Road, Hampton Lucy.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 18 November 2024 at 10:59 and could run through until 13 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 18 Nov 2024 at 11:05.
18 Nov and 13 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Snitterfield Road, Hampton Lucy.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 18 November 2024 and could run through until 13 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 22 Aug 2024 at 15:31.
18 Nov and 6 Dec 2024
Warwickshire County Council are proposing to carry out Remedial works on Banbury Road, Lighthorne.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 18 November 2024 and could run through until 6 December 2024. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by Warwickshire County Council on 29 Oct 2024 at 10:32.
Wednesday
Severn Trent Water were proposing to carry out Utility repair and maintenance works on Lighthorne Road, Kineton.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 25 November 2024 and run through until 27 November 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by Severn Trent Water on 28 Aug 2024 at 15:11.
2 and 4 Dec 2024
Cadent Gas were proposing to carry out New service connection on Church Street, Wellesbourne.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 2 December 2024 and run through until 4 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by Cadent Gas on 4 Sep 2024 at 14:17.
16 and 18 Dec 2024
Western Power Distribution (East Midlands) are proposing to carry out New service connection on Church Street, Wellesbourne.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 16 December 2024 and could run through until 18 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Western Power Distribution (East Midlands) on 16 Sep 2024 at 15:22.
2 Jan and 1 Dec 2025
Warwickshire County Council are proposing to carry out roadworks on High Street, Stratford-upon-avon.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 2 January 2025 and could run through until 1 December 2025. The works will impact the carriageway and footpath.
This roadwork event was last updated by Warwickshire County Council on 20 Nov 2024 at 13:44.
6 Jan and 4 Mar 2025
Severn Trent Water were proposing to carry out Utility asset works on Banbury Road, Lighthorne.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 6 January 2025 and run through until 4 March 2025. The works were due to impact the footway, carriageway and verge.
This roadwork event was last updated by Severn Trent Water on 16 Oct 2024 at 11:53.
6 and 31 Jan 2025
Cadent Gas were proposing to carry out Utility asset works on Snitterfield Street, Hampton Lucy.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 6 January 2025 and run through until 31 January 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 28 Aug 2024 at 12:54.
6 and 31 Jan 2025
Cadent Gas are proposing to carry out Utility asset works on Snitterfield Street, Hampton Lucy.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 31 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 23 Sep 2024 at 12:08.
6 and 8 Jan 2025
Cadent Gas are proposing to carry out New service connection on Church Street, Wellesbourne.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 8 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Cadent Gas on 5 Sep 2024 at 13:36.
7 and 9 Jan 2025
Severn Trent Water are proposing to carry out Utility repair and maintenance works on Lighthorne Road, Kineton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 7 January 2025 and could run through until 9 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Severn Trent Water on 30 Sep 2024 at 11:48.
7 and 9 Jan 2025
Severn Trent Water are proposing to carry out Utility repair and maintenance works on Lighthorne Road, Kineton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 7 January 2025 and could run through until 9 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Severn Trent Water on 15 Oct 2024 at 14:20.
8 Jan 2025 and 8 Jan 2026
Warwickshire County Council are proposing to carry out Highway improvement works on Keytes Lane, Barford.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 8 January 2025 and could run through until 8 January 2026. The works will impact the carriageway only.
This roadwork event was last updated by Warwickshire County Council on 20 Nov 2024 at 11:44.
8 Jan 2025 and 8 Jan 2026
Warwickshire County Council are proposing to carry out Highway improvement works on Keytes Lane, Barford.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 8 January 2025 and could run through until 8 January 2026. The works will impact the carriageway only.
This roadwork event was last updated by Warwickshire County Council on 20 Sep 2024 at 11:29.
13 Jan and 14 Feb 2025
ESP Electricity were proposing to carry out Utility asset works on Edgehill Drive, Warwick.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 13 January 2025 and run through until 14 February 2025. The works were due to impact the footway, carriageway and verge.
This roadwork event was last updated by ESP Electricity on 20 Nov 2024 at 12:30.
13 Jan and 16 Oct 2025
Warwickshire County Council are proposing to carry out Highway improvement works on Clifford Road, Stratford-upon-avon.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 13 January 2025 and could run through until 16 October 2025. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by Warwickshire County Council on 4 Oct 2023 at 14:22.
13 Jan and 14 Feb 2025
ESP Electricity are proposing to carry out Utility asset works on Edgehill Drive, Warwick.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 13 January 2025 and could run through until 14 February 2025. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by ESP Electricity on 20 Nov 2024 at 12:32.
13 Jan and 16 Oct 2025
Warwickshire County Council are proposing to carry out Highway improvement works on Seven Meadows Road, Stratford-upon-avon.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 13 January 2025 and could run through until 16 October 2025. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by Warwickshire County Council on 4 Oct 2023 at 14:23.
13 Jan and 16 Oct 2025
Warwickshire County Council are proposing to carry out Highway improvement works on Trinity Way, Stratford-upon-avon.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 13 January 2025 and could run through until 16 October 2025. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by Warwickshire County Council on 4 Oct 2023 at 14:22.
13 Jan and 16 Oct 2025
Warwickshire County Council are proposing to carry out Highway improvement works on Shipston Road, Stratford-upon-avon.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 13 January 2025 and could run through until 16 October 2025. The works will impact the footway, carriageway, verge and cycleway.
This roadwork event was last updated by Warwickshire County Council on 4 Oct 2023 at 14:22.
19 Jan and 30 Nov 2025
Warwickshire County Council are proposing to carry out Highway improvement works on Birmingham Road, Stratford-upon-avon.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 19 January 2025 and could run through until 30 November 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Warwickshire County Council on 20 Aug 2024 at 10:07.
20 and 22 Jan 2025
Severn Trent Water are proposing to carry out New service connection on The Bank, Lighthorne.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 20 January 2025 and could run through until 22 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Severn Trent Water on 17 Oct 2024 at 13:47.
20 and 22 Jan 2025
Severn Trent Water are proposing to carry out New service connection on The Bank, Lighthorne.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 20 January 2025 and could run through until 22 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Severn Trent Water on 17 Oct 2024 at 10:19.
27 Jan and 21 Feb 2025
Cadent Gas are proposing to carry out Utility asset works on Hatton Bank Lane, Hampton Lucy.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 27 January 2025 and could run through until 21 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 22 Aug 2024 at 15:26.
27 Jan and 21 Feb 2025
Cadent Gas are proposing to carry out Utility asset works on Snitterfield Road, Hampton Lucy.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 27 January 2025 and could run through until 21 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 22 Aug 2024 at 15:26.
27 Jan and 31 Jul 2025
Warwickshire County Council are proposing to carry out Highway improvement works on Banbury Road, Bishops Tachbrook.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 27 January 2025 and could run through until 31 July 2025. The works will impact the carriageway and verge.
This roadwork event was last updated by Warwickshire County Council on 22 Oct 2024 at 13:57.
3 Feb and 29 Mar 2025
National Highways were proposing to carry out Highway improvement works on Warwick Road, Upper Fulbrook.
These works were categorised as Major.
A lane was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 3 February 2025 and run through until 29 March 2025. The works were due to impact the carriageway only.
This roadwork event was last updated by National Highways on 11 Oct 2024 at 08:10.
3 Feb and 29 Mar 2025
National Highways are proposing to carry out Highway improvement works on Warwick Road, Upper Fulbrook.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 3 February 2025 and could run through until 29 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by National Highways on 8 Nov 2024 at 15:28.
3 and 16 Feb 2025
Severn Trent Water are proposing to carry out Utility asset works on Heath End, Snitterfield.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 3 February 2025 and could run through until 16 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Severn Trent Water on 6 Nov 2024 at 08:25.
10 and 21 Feb 2025
Warwickshire County Council are proposing to carry out Highway improvement works on Southern Lane, Stratford-upon-avon.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 10 February 2025 and could run through until 21 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Warwickshire County Council on 7 Nov 2024 at 15:55.
10 Feb and 21 Mar 2025
Severn Trent Water are proposing to carry out Utility asset works on Banbury Road, Lighthorne.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 10 February 2025 and could run through until 21 March 2025. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by Severn Trent Water on 12 Nov 2024 at 08:26.
12 and 14 Feb 2025
Severn Trent Water were proposing to carry out Utility repair and maintenance works on Oxhill Bridle Road, Pillerton Hersey.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 12 February 2025 and run through until 14 February 2025. The works were due to impact the verge only.
This roadwork event was last updated by Severn Trent Water on 21 Nov 2024 at 10:41.
17 and 20 Feb 2025
Severn Trent Water are proposing to carry out Utility repair and maintenance works on Stratford Road, Lighthorne.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 February 2025 and could run through until 20 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Severn Trent Water on 20 Nov 2024 at 12:21.
Roadworks Map near to Bridge Street, WARWICK, CV35 9QP
- Any red lines indicate the extent of the works.
- Clicking on the map will re-centre to the selected point.
- Within 1 mile, all roadworks are displayed.
- Within 2-3 miles, standard, urgent and major roadworks are displayed.
- For 3-5 miles, only major roadworks are shown.
- The higher the marker number, the further away the roadworks are from the centre of the postcode.
- Where traffic camera videos or images are shown, no historical versions are retained. Once a new image or video becomes available it overwrites the previous version.
Roadworks Listing near to Bridge Street, WARWICK, CV35 9QP (1 Events)
(Scheduled Dates)
(miles)
Contains public sector information licensed under the Open Government Licence v3.0.