ROADWORKS SUMMARY
SE18 9ED

Introduction

Image of petrol pumps

View current and future planned roadworks and road closures for SE18 9ED and the surrounding area.

Our roadwork details are constantly updated and reflect the current situation and we offer both a map view and a listing. We also highlight the major and significant roadworks occuring near to you help you avoid the worst of the delays to your journey.

The roadworks shown below show all current and proposed works during the next 90 days and historical data is recorded since July 2020.

Please note that we re-publish this data and cannot provide any additional information pertaining to a roadwork event. If you require more information, please contact the organisation carrying out the work.

Data are provided by the Department for Transport.

Have we helped today?

If we have helped you today, please consider buying us a quick coffee to keep us going!

Major Roadworks near to SE18 9ED

Details of major roadworks, currently in progress or starting soon and resulting in road closures and/or traffic signal management for are shown here covering a 5 mile radius. See further down for details of all roadworks in your area.

Thames Tideway Tunnel logo

LONG TERM
Until
30 Mar 2025
Details
View Map
Share
Norman Road

Thames Tideway Tunnel are carrying out Statutory Infrastructure Works on Norman Road, Greenwich.

These works are categorised as Major.

Two-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 13 July 2020 at 08:00 and could run through until 30 March 2025. The works will impact the carriageway only.

This roadwork event was last updated by Thames Tideway Tunnel on 20 Jul 2023 at 13:25.

Thames Tideway Tunnel logo

LONG TERM
Until
31 Oct 2024
Details
View Map
Share
Deptford Church Street

Thames Tideway Tunnel are carrying out Statutory Infrastructure Works on Deptford Church Street, London.

These works are categorised as Major.

A lane is closed for some or all of the period and could cause delays to journeys.

The works started on 17 July 2020 at 08:00 and could run through until 31 October 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Tideway Tunnel on 20 Jul 2023 at 09:27.

Thames Tideway Tunnel logo

LONG TERM
Until
30 May 2024
Details
View Map
Share
Deptford Church Street

Thames Tideway Tunnel are carrying out Statutory Infrastructure Works on Deptford Church Street, London.

These works are categorised as Major.

The works started on 17 July 2020 at 08:00 and could run through until 30 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Tideway Tunnel on 20 Jul 2023 at 09:28.

Thames Tideway Tunnel logo

LONG TERM
Until
30 Aug 2024
Details
View Map
Share
Yeoman Street

Thames Tideway Tunnel are carrying out Statutory Infrastructure Works on Yeoman Street, London.

These works are categorised as Major.

The works started on 17 July 2020 at 08:00 and could run through until 30 August 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Tideway Tunnel on 4 Nov 2021 at 15:19.

Thames Tideway Tunnel logo

LONG TERM
Until
30 Aug 2024
Details
View Map
Share
Croft Street

Thames Tideway Tunnel are carrying out Statutory Infrastructure Works on Croft Street, London.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 27 July 2020 at 07:00 and could run through until 30 August 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Tideway Tunnel on 8 Nov 2021 at 12:02.

Thames Tideway Tunnel logo

LONG TERM
Until
31 Oct 2024
Details
View Map
Share
Coffey Road

Thames Tideway Tunnel are carrying out Statutory Infrastructure Works on Coffey Road, London.

These works are categorised as Major.

The works started on 4 August 2020 at 07:00 and could run through until 31 October 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Tideway Tunnel on 20 Jul 2023 at 09:29.

Thames Water logo

LONG TERM
Finishing
Sunday
Details
View Map
Share
Vesta Road

Thames Water are carrying out Utility asset works on Vesta Road, London.

These works are categorised as Major.

Two-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 30 June 2021 at 09:00 and could run through until 31 March 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 22 Dec 2023 at 14:47.

Thames Water logo

LONG TERM
Until
30 Jun 2024
Details
View Map
Share
Vulcan Road

Thames Water are carrying out roadworks on Vulcan Road, London.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 18 August 2021 at 09:00 and could run through until 30 June 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 28 Mar 2024 at 10:50.

London Borough Of Southwark logo

LONG TERM
Until
1 Jan 2025
Details
View Map
Share
Croft Street

London Borough Of Southwark are carrying out Highway improvement works on Croft Street, London.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 2 January 2022 at 00:00 and could run through until 1 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Southwark on 7 Mar 2024 at 23:15.

Thames Water logo

LONG TERM
Between
31 Oct 2022 and 30 Jan 2025
Details
View Map
Share
Millennium Way

Thames Water are proposing to carry out Utility asset works on Millennium Way, Greenwich.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 31 October 2022 and could run through until 30 January 2025. The works will impact the footway, carriageway and verge.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

This roadwork event was last updated by Thames Water on 25 Oct 2022 at 05:47.

Transport for London (TfL) logo

LONG TERM
Finishing
Wednesday
Details
View Map
Share
Lower Lea Crossing

Transport for London (TfL) are carrying out Utility asset works on Lower Lea Crossing, Canning Town, London.

These works are categorised as Major.

The works started on 9 January 2023 at 08:53 and could run through until 3 April 2024. The works will impact the footway, carriageway and cycleway.

This roadwork event was last updated by Transport for London (TfL) on 18 Mar 2024 at 14:33.

LONG TERM
Until
31 Aug 2024
Details
View Map
Share
Silvertown Way

London Borough Of Newham are carrying out Highway improvement works on Silvertown Way, Canning Town, London.

These works are categorised as Major.

Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 27 March 2023 at 07:00 and could run through until 31 August 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by London Borough Of Newham on 1 Mar 2024 at 12:19.

Transport for London (TfL) logo

LONG TERM
Until
27 Sep 2024
Details
View Map
Share
Millennium Way

Transport for London (TfL) are carrying out Highway improvement works on Millennium Way, Greenwich.

These works are categorised as Major.

A lane is closed for some or all of the period and could cause delays to journeys.

The works started on 31 March 2023 at 17:00 and could run through until 27 September 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Transport for London (TfL) on 19 Jul 2023 at 13:31.

LONG TERM
Until
30 Apr 2024
Details
View Map
Share
Romford Road

London Borough Of Newham are carrying out Highway improvement works on Romford Road, Stratford, London.

These works are categorised as Major.

Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 12 June 2023 at 07:00 and could run through until 30 April 2024. The works will impact the footway, carriageway and cycleway.

This roadwork event was last updated by London Borough Of Newham on 19 Mar 2024 at 14:57.

Transport for London (TfL) logo

LONG TERM
Until
4 May 2024
Details
View Map
Share
Tunnel Avenue

Transport for London (TfL) are carrying out Highway improvement works on Tunnel Avenue, Greenwich.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 28 June 2023 at 05:00 and could run through until 4 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 3 Nov 2023 at 06:50.

Thames Water logo

LONG TERM
Between
24 Jul 2023 and 13 Jan 2025
Details
View Map
Share
Willersley Avenue

Thames Water are proposing to carry out New service connection on Willersley Avenue, Sidcup.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 24 July 2023 and could run through until 13 January 2025. The works will impact the carriageway only.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

This roadwork event was last updated by Thames Water on 14 Mar 2023 at 18:23.

Thames Water logo

LONG TERM
Between
24 Jul 2023 and 31 Jan 2026
Details
View Map
Share
Westwood Lane

Thames Water are proposing to carry out New service connection on Westwood Lane, Welling.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 24 July 2023 and could run through until 31 January 2026. The works will impact the carriageway only.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

This roadwork event was last updated by Thames Water on 14 Mar 2023 at 17:35.

Thames Water logo

LONG TERM
Until
19 Sep 2024
Details
View Map
Share
Barking Road

Thames Water are carrying out Utility asset works on Barking Road, East Ham, London.

These works are categorised as Major.

Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 25 July 2023 at 17:03 and could run through until 19 September 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 7 Dec 2023 at 09:11.

Thames Water logo

LONG TERM
Between
30 Jul 2023 and 7 Apr 2024
Details
View Map
Share
Grangewood Street

Thames Water are proposing to carry out Utility asset works on Grangewood Street, East Ham, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 30 July 2023 and could run through until 7 April 2024. The works will impact the footway and carriageway.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

This roadwork event was last updated by Thames Water on 27 Apr 2023 at 14:22.

Thames Water logo

LONG TERM
Between
28 Aug 2023 and 12 Aug 2024
Details
View Map
Share
Wellington Avenue

Thames Water are proposing to carry out New service connection on Wellington Avenue, Sidcup.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 28 August 2023 and could run through until 12 August 2024. The works will impact the carriageway only.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

This roadwork event was last updated by Thames Water on 14 Mar 2023 at 18:01.

Southern Gas Networks logo

LONG TERM
Until
29 Apr 2024
Details
View Map
Share
Nathan Way

Southern Gas Networks are carrying out Utility repair and maintenance works on Nathan Way, Thamesmead.

These works are categorised as Major.

Two-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 8 September 2023 at 08:30 and could run through until 29 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Southern Gas Networks on 27 Feb 2024 at 14:47.

LONG TERM
Until
8 Jul 2024
Details
View Map
Share
North Woolwich Road

London Borough Of Newham are carrying out Highway improvement works on North Woolwich Road, Silvertown, London.

These works are categorised as Major.

Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 3 September 2023 at 07:00 and could run through until 8 July 2024. The works will impact the footway, carriageway, verge, cycleway and footpath.

This roadwork event was last updated by London Borough Of Newham on 5 Sep 2023 at 11:00.

LONG TERM
Until
13 Aug 2024
Details
View Map
Share
Queens Market

London Borough Of Newham are carrying out Highway improvement works on Queens Market, Upton Park, London.

These works are categorised as Major.

The works should not impact the carriageway.

The works started on 12 September 2023 at 21:00 and could run through until 13 August 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Newham on 5 Mar 2024 at 12:41.

LONG TERM
Until
31 Aug 2024
Details
View Map
Share
North Woolwich Road

London Borough Of Newham are carrying out Highway repair and maintenance works on North Woolwich Road, Silvertown, London.

These works are categorised as Major.

A lane is closed for some or all of the period and could cause delays to journeys.

The works started on 18 September 2023 at 12:00 and could run through until 31 August 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by London Borough Of Newham on 30 Jan 2024 at 09:28.

London Borough Of Southwark logo

LONG TERM
Until
22 Jun 2024
Details
View Map
Share
Lower Road

London Borough Of Southwark are carrying out Highway improvement works on Lower Road, London.

These works are categorised as Major.

A lane is closed for some or all of the period and could cause delays to journeys.

The works started on 22 September 2023 at 23:00 and could run through until 22 June 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Southwark on 13 Oct 2023 at 05:52.

Transport for London (TfL) logo

LONG TERM
Between
1 Oct 2023 and 10 Oct 2025
Details
View Map
Share
East India Dock Road

Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on East India Dock Road, Canning Town, London.

These works are categorised as Major.

The works will start on or after 1 October 2023 and could run through until 10 October 2025. The works will impact the carriageway and verge.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

This roadwork event was last updated by Transport for London (TfL) on 25 May 2023 at 08:39.

Transport for London (TfL) logo

LONG TERM
Until
4 May 2024
Details
View Map
Share
Blackwall Tunnel Southern Approach

Transport for London (TfL) are carrying out Highway improvement works on Blackwall Tunnel Southern Approach, Greenwich.

These works are categorised as Major.

A lane is closed for some or all of the period and could cause delays to journeys.

The works started on 9 October 2023 at 04:00 and could run through until 4 May 2024. The works will impact the footway, carriageway and verge.

This roadwork event was last updated by Transport for London (TfL) on 25 Oct 2023 at 07:29.

Thames Water logo

LONG TERM
Until
23 May 2024
Details
View Map
Share
Southchurch Road

Thames Water are carrying out Utility asset works on Southchurch Road, East Ham, London.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 23 October 2023 at 08:00 and could run through until 23 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 21 Nov 2023 at 11:38.

London Borough Of Bexley logo

LONG TERM
Until
30 Apr 2024
Details
View Map
Share
Bull Alley

London Borough Of Bexley are carrying out Section 50 on Bull Alley, Welling.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 30 October 2023 at 10:00 and could run through until 30 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Bexley on 25 Jan 2024 at 16:01.

Thames Water logo

LONG TERM
Between
30 Oct 2023 and 10 May 2024
Details
View Map
Share
Welling Way

Thames Water are proposing to carry out New service connection on Welling Way, Welling.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 30 October 2023 and could run through until 10 May 2024. The works will impact the carriageway only.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

This roadwork event was last updated by Thames Water on 12 Apr 2023 at 11:02.

Royal Borough Of Greenwich logo

LONG TERM
Until
6 Nov 2024
Details
View Map
Share
Plumstead High Street

Royal Borough Of Greenwich are carrying out Highway repair and maintenance works on Plumstead High Street, Plumstead.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 6 November 2023 at 11:00 and could run through until 6 November 2024. The works will impact the carriageway only.

This roadwork event was last updated by Royal Borough Of Greenwich on 15 Mar 2024 at 17:35.

LONG TERM
Between
6 Nov 2023 and 5 May 2024
Details
View Map
Share
North Woolwich Road

London Borough Of Newham are proposing to carry out Highway improvement works on North Woolwich Road, Silvertown, London.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 6 November 2023 and could run through until 5 May 2024. The works will impact the footway, carriageway and verge.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

This roadwork event was last updated by London Borough Of Newham on 14 Aug 2023 at 17:57.

LONG TERM
Until
31 Aug 2024
Details
View Map
Share
Connaught Bridge

London Borough Of Newham are carrying out Highway improvement works on Connaught Bridge, Silvertown, London.

These works are categorised as Major.

A lane is closed for some or all of the period and could cause delays to journeys.

The works started on 6 November 2023 at 08:00 and could run through until 31 August 2024. The works will impact the carriageway and verge.

This roadwork event was last updated by London Borough Of Newham on 30 Jan 2024 at 09:56.

LONG TERM
Between
6 Nov 2023 and 5 May 2024
Details
View Map
Share
Connaught Bridge

London Borough Of Newham are proposing to carry out Highway improvement works on Connaught Bridge, Silvertown, London.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 6 November 2023 and could run through until 5 May 2024. The works will impact the footway, carriageway and verge.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

This roadwork event was last updated by London Borough Of Newham on 14 Aug 2023 at 17:58.

LONG TERM
Between
6 Nov 2023 and 5 May 2024
Details
View Map
Share
Connaught Bridge

London Borough Of Newham are proposing to carry out Highway improvement works on Connaught Bridge, Silvertown, London.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 6 November 2023 and could run through until 5 May 2024. The works will impact the footway, carriageway and verge.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

This roadwork event was last updated by London Borough Of Newham on 14 Aug 2023 at 18:01.

LONG TERM
Between
6 Nov 2023 and 5 May 2024
Details
View Map
Share
Connaught Road

London Borough Of Newham are proposing to carry out Highway improvement works on Connaught Road, Silvertown, London.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 6 November 2023 and could run through until 5 May 2024. The works will impact the footway, carriageway and verge.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

This roadwork event was last updated by London Borough Of Newham on 14 Aug 2023 at 18:01.

LONG TERM
Until
31 May 2024
Details
View Map
Share
High Street

London Borough Of Newham are carrying out Highway improvement works on High Street, Plaistow, London.

These works are categorised as Major.

Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 13 November 2023 at 08:00 and could run through until 31 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by London Borough Of Newham on 24 Jan 2024 at 16:21.

LONG TERM
Until
31 Aug 2024
Details
View Map
Share
Silvertown Way

London Borough Of Newham are carrying out Highway improvement works on Silvertown Way, Canning Town, London.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 27 November 2023 at 08:00 and could run through until 31 August 2024. The works will impact the footway, carriageway and cycleway.

This roadwork event was last updated by London Borough Of Newham on 30 Jan 2024 at 14:19.

Transport for London (TfL) logo

LONG TERM
Until
30 Jun 2024
Details
View Map
Share
Tunnel Avenue

Transport for London (TfL) are carrying out Highway improvement works on Tunnel Avenue, Greenwich.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 1 December 2023 at 06:00 and could run through until 30 June 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 1 Dec 2023 at 09:20.

Transport for London (TfL) logo

LONG TERM
Until
26 Apr 2024
Details
View Map
Share
Tunnel Avenue

Transport for London (TfL) are carrying out Highway improvement works on Tunnel Avenue, Greenwich.

These works are categorised as Major.

Two-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 2 January 2024 at 07:00 and could run through until 26 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 28 Mar 2024 at 07:38.

LONG TERM
Between
2 Jan and 19 Dec 2024
Details
View Map
Share
Thames Road

London Borough Of Newham are proposing to carry out Section 50 on Thames Road, Silvertown, London.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 2 January 2024 and could run through until 19 December 2024. The works will impact the footway, carriageway and verge.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

This roadwork event was last updated by London Borough Of Newham on 4 Jan 2024 at 09:37.

LONG TERM
Between
2 Jan and 19 Dec 2024
Details
View Map
Share
Booth Road

London Borough Of Newham are proposing to carry out Section 50 on Booth Road, Silvertown, London.

These works are categorised as Major.

Two-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 2 January 2024 and could run through until 19 December 2024. The works will impact the footway and carriageway.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

This roadwork event was last updated by London Borough Of Newham on 3 Jan 2024 at 11:22.

LONG TERM
Until
19 Dec 2024
Details
View Map
Share
North Woolwich Road

London Borough Of Newham are carrying out Section 50 on North Woolwich Road, Silvertown, London.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 4 January 2024 at 08:00 and could run through until 19 December 2024. The works will impact the footway, carriageway and verge.

This roadwork event was last updated by London Borough Of Newham on 10 Jan 2024 at 09:24.

LONG TERM
Until
23 Dec 2024
Details
View Map
Share
Burt Road

London Borough Of Newham are carrying out Section 50 on Burt Road, Silvertown, London.

These works are categorised as Major.

Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 4 January 2024 at 08:00 and could run through until 23 December 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by London Borough Of Newham on 10 Jan 2024 at 09:26.

LONG TERM
Between
2 Jan and 19 Dec 2024
Details
View Map
Share
Charles Street

London Borough Of Newham are proposing to carry out Section 50 on Charles Street, Silvertown, London.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 2 January 2024 and could run through until 19 December 2024. The works will impact the footway, carriageway and verge.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

This roadwork event was last updated by London Borough Of Newham on 3 Jan 2024 at 11:20.

LONG TERM
Until
30 Apr 2024
Details
View Map
Share
Dyson Road

London Borough Of Newham are carrying out Highway improvement works on Dyson Road, Stratford, London.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 2 January 2024 at 08:00 and could run through until 30 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Newham on 13 Mar 2024 at 13:17.

Thames Water logo

LONG TERM
Until
14 Apr 2024
Details
View Map
Share
New Cross Road

Thames Water are carrying out Utility repair and maintenance works on New Cross Road, London.

These works are categorised as Major.

A lane is closed for some or all of the period and could cause delays to journeys.

The works started on 3 January 2024 at 10:00 and could run through until 14 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 18 Mar 2024 at 13:47.

Thames Water logo

LONG TERM
Until
29 Sep 2024
Details
View Map
Share
High Street North

Thames Water are carrying out Utility asset works on High Street North, East Ham, London.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 8 January 2024 at 10:00 and could run through until 29 September 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 6 Mar 2024 at 12:06.

UK Power Networks Eastern & London logo

LONG TERM
Until
12 Apr 2024
Details
View Map
Share
Quebec Way

UK Power Networks Eastern & London are carrying out Statutory Infrastructure Works on Quebec Way, London.

These works are categorised as Major.

Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 9 January 2024 at 08:00 and could run through until 12 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by UK Power Networks Eastern & London on 26 Mar 2024 at 08:34.

LONG TERM
Between
11 Jan and 31 May 2024
Details
View Map
Share
Claps Gate Lane

London Borough Of Newham are proposing to carry out Highway repair and maintenance works on Claps Gate Lane, Beckton, London.

These works are categorised as Major.

The works will start on or after 11 January 2024 and could run through until 31 May 2024. The works will impact the carriageway only.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

This roadwork event was last updated by London Borough Of Newham on 22 Sep 2023 at 12:49.

LONG TERM
Until
1 May 2024
Details
View Map
Share
Bidder Street

London Borough Of Newham are carrying out Section 50 on Bidder Street, Canning Town, London.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 15 January 2024 at 09:00 and could run through until 1 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by London Borough Of Newham on 15 Jan 2024 at 11:28.

LONG TERM
Until
29 Apr 2024
Details
View Map
Share
Park Road

London Borough Of Newham are carrying out Highway improvement works on Park Road, East Ham, London.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 15 January 2024 at 08:00 and could run through until 29 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Newham on 27 Feb 2024 at 09:24.

LONG TERM
Until
31 Dec 2024
Details
View Map
Share
Westfield Avenue

London Borough Of Newham are carrying out Highway improvement works on Westfield Avenue, Stratford, London.

These works are categorised as Major.

A lane is closed for some or all of the period and could cause delays to journeys.

The works started on 15 January 2024 at 08:00 and could run through until 31 December 2024. The works will impact the footway, carriageway and cycleway.

This roadwork event was last updated by London Borough Of Newham on 16 Feb 2024 at 10:14.

Thames Water logo

LONG TERM
Between
22 Jan and 6 May 2024
Details
View Map
Share
Stephenson Close

Thames Water are proposing to carry out New service connection on Stephenson Close, Welling.

These works are categorised as Major.

There will be no traffic signals or road closures necessary for these works and traffic will operate on a give-and-take basis.

The works will start on or after 22 January 2024 and could run through until 6 May 2024. The works will impact the carriageway only.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

This roadwork event was last updated by Thames Water on 14 Mar 2023 at 18:49.

Thames Water logo

LONG TERM
Until
4 Apr 2024
Details
View Map
Share
Poulett Road

Thames Water are carrying out Utility asset works on Poulett Road, East Ham, London.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 24 January 2024 at 09:00 and could run through until 4 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 27 Mar 2024 at 09:09.

London Borough Of Lewisham logo

LONG TERM
Until
19 Aug 2024
Details
View Map
Share
Creekside

London Borough Of Lewisham are carrying out Highway improvement works on Creekside, London.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 29 January 2024 at 09:10 and could run through until 19 August 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Lewisham on 29 Jan 2024 at 09:10.

Thames Water logo

LONG TERM
Between
29 Jan and 19 May 2024
Details
View Map
Share
High Street South

Thames Water are proposing to carry out Utility asset works on High Street South, East Ham, London.

These works are categorised as Major.

Two-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 29 January 2024 and could run through until 19 May 2024. The works will impact the footway and carriageway.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

This roadwork event was last updated by Thames Water on 24 Nov 2023 at 09:11.

Thames Water logo

LONG TERM
Until
19 May 2024
Details
View Map
Share
High Street South

Thames Water are carrying out Utility asset works on High Street South, East Ham, London.

These works are categorised as Major.

Two-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 29 January 2024 at 08:00 and could run through until 19 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 28 Feb 2024 at 23:05.

Thames Water logo

LONG TERM
Today
Details
View Map
Share
Grove Park Road

Thames Water carried out Utility repair and maintenance works on Grove Park Road, Mottingham.

The road was closed for some or all of the period.

The works were originally planned between 5 Feb 2024 and 28 Mar 2024 and were actually completed between 5 Feb 2024 (11:30) and 28 Mar 2024 (13:25). The works impacted the carriageway only.

This roadwork event was last updated by Thames Water on 28 Mar 2024 at 13:26.

LONG TERM
Finishing
Today
Details
View Map
Share
Chequers Lane

Essex And Suffolk Water are carrying out Utility repair and maintenance works on Chequers Lane, Dagenham.

These works are categorised as Major.

Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 6 February 2024 at 09:00 and could run through until 28 March 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Essex And Suffolk Water on 27 Mar 2024 at 16:30.

Thames Water logo

LONG TERM
Until
4 Apr 2024
Details
View Map
Share
Wakefield Street

Thames Water are carrying out Utility asset works on Wakefield Street, East Ham, London.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 12 February 2024 at 10:00 and could run through until 4 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 27 Mar 2024 at 11:08.

LONG TERM
Until
29 Apr 2024
Details
View Map
Share
Romford Road

London Borough Of Newham are carrying out Highway improvement works on Romford Road, Manor Park, London.

These works are categorised as Major.

A lane is closed for some or all of the period and could cause delays to journeys.

The works started on 25 March 2024 at 16:30 and could run through until 29 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by London Borough Of Newham on 27 Mar 2024 at 09:20.

Thames Water logo

LONG TERM
Between
13 Feb and 2 Jun 2024
Details
View Map
Share
Pilgrims Way

Thames Water carried out Utility asset works on Pilgrims Way, East Ham, London.

These works were categorised as Major.

The road was closed for some or all of the period.

The works were originally planned between 13 Feb 2024 and 2 Jun 2024 and were actually completed between 13 Feb 2024 (11:55) and 28 Mar 2024 (10:10). The works impacted the footway and carriageway.

This roadwork event was last updated by Thames Water on 28 Mar 2024 at 10:10.

Thames Water logo

LONG TERM
Until
3 May 2024
Details
View Map
Share
Landstead Road

Thames Water are carrying out Utility asset works on Landstead Road, Plumstead.

These works are categorised as Major.

Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 15 February 2024 at 08:40 and could run through until 3 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 15 Feb 2024 at 09:21.

Transport for London (TfL) logo

LONG TERM
Until
5 Apr 2024
Details
View Map
Share
Brownhill Road

Transport for London (TfL) are carrying out Highway improvement works on Brownhill Road, London.

These works are categorised as Major.

Two-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 19 February 2024 at 08:00 and could run through until 5 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 19 Feb 2024 at 08:06.

Transport for London (TfL) logo

LONG TERM
Until
5 Apr 2024
Details
View Map
Share
Torridon Road

Transport for London (TfL) are carrying out Highway repair and maintenance works on Torridon Road, London.

These works are categorised as Major.

Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 19 February 2024 at 07:00 and could run through until 5 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 19 Feb 2024 at 07:04.

LONG TERM
Finishing
Saturday
Details
View Map
Share
Rayleigh Road

London Borough Of Newham are carrying out Section 50 on Rayleigh Road, Silvertown, London.

These works are categorised as Major.

Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 19 February 2024 at 09:00 and could run through until 30 March 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by London Borough Of Newham on 20 Mar 2024 at 14:43.

Thames Water logo

LONG TERM
Between
19 Feb and 8 Sep 2024
Details
View Map
Share
Barking Road

Thames Water are proposing to carry out Utility asset works on Barking Road, East Ham, London.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 19 February 2024 and could run through until 8 September 2024. The works will impact the footway and carriageway.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

This roadwork event was last updated by Thames Water on 17 Nov 2023 at 09:11.

Thames Water logo

LONG TERM
Between
19 Feb and 14 Apr 2024
Details
View Map
Share
Wellington Road

Thames Water are proposing to carry out Utility asset works on Wellington Road, East Ham, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 19 February 2024 and could run through until 14 April 2024. The works will impact the footway and carriageway.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

This roadwork event was last updated by Thames Water on 17 Nov 2023 at 09:12.

Transport for London (TfL) logo

LONG TERM
Between
20 Feb 2024 and 20 Feb 2025
Details
View Map
Share
Lakeside Close

Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Lakeside Close, Sidcup.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 20 February 2024 and could run through until 20 February 2025. The works will impact the footway, carriageway and verge.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

This roadwork event was last updated by Transport for London (TfL) on 23 Feb 2024 at 11:06.

Southern Gas Networks logo

LONG TERM
Until
4 Apr 2024
Details
View Map
Share
Filston Road

Southern Gas Networks are carrying out Utility repair and maintenance works on Filston Road, Erith.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 23 February 2024 at 12:00 and could run through until 4 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Southern Gas Networks on 27 Mar 2024 at 11:35.

Thames Water logo

LONG TERM
Between
26 Feb and 4 Apr 2024
Details
View Map
Share
Hornet Way

Thames Water carried out Utility asset works on Hornet Way, Beckton, London.

These works were categorised as Major.

Two-way signals were in place for some or all of the period.

The works were originally planned between 26 Feb 2024 and 4 Apr 2024 and were actually completed between 29 Feb 2024 (11:30) and 28 Mar 2024 (14:00). The works impacted the footway and carriageway.

This roadwork event was last updated by Thames Water on 28 Mar 2024 at 14:54.

LONG TERM
Between
26 Feb and 26 Apr 2024
Details
View Map
Share
Great Eastern Road

London Borough Of Newham are proposing to carry out Highway repair and maintenance works on Great Eastern Road, Stratford, London.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 26 February 2024 and could run through until 26 April 2024. The works will impact the footway and cycleway.

This roadwork event was last updated by London Borough Of Newham on 7 Feb 2024 at 16:31.

Thames Water logo

LONG TERM
Finishing
Saturday
Details
View Map
Share
Lewis Road

Thames Water are carrying out Utility repair and maintenance works on Lewis Road, Sidcup.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 27 February 2024 at 11:00 and could run through until 30 March 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 13 Mar 2024 at 11:39.

London Borough Of Bexley logo

LONG TERM
Finishing
Wednesday
Details
View Map
Share
Woolwich Road

London Borough Of Bexley are proposing to carry out Highway improvement works on Woolwich Road, Belvedere.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 27 February 2024 and could run through until 3 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Bexley on 14 Feb 2024 at 14:46.

LONG TERM
Between
28 Feb and 30 May 2024
Details
View Map
Share
Clegg Street

London Borough Of Newham are proposing to carry out Highway repair and maintenance works on Clegg Street, Plaistow, London.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 28 February 2024 and could run through until 30 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by London Borough Of Newham on 28 Feb 2024 at 16:06.

Transport for London (TfL) logo

LONG TERM
Between
1 Mar and 1 May 2024
Details
View Map
Share
Bow Road

Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Bow Road, London.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 1 March 2024 and could run through until 1 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 10 Oct 2023 at 11:05.

Transport for London (TfL) logo

LONG TERM
Until
1 May 2024
Details
View Map
Share
High Street

Transport for London (TfL) are carrying out Highway repair and maintenance works on High Street, Stratford, London.

These works are categorised as Major.

A lane is closed for some or all of the period and could cause delays to journeys.

The works started on 1 March 2024 at 08:00 and could run through until 1 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 5 Mar 2024 at 12:58.

Transport for London (TfL) logo

LONG TERM
Between
1 Mar and 1 May 2024
Details
View Map
Share
Blackwall Tunnel Northern Approach

Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Blackwall Tunnel Northern Approach, London.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 1 March 2024 and could run through until 1 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 10 Oct 2023 at 11:31.

Transport for London (TfL) logo

LONG TERM
Between
1 Mar and 1 May 2024
Details
View Map
Share
Blackwall Tunnel Northern Approach

Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Blackwall Tunnel Northern Approach, London.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 1 March 2024 and could run through until 1 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 10 Oct 2023 at 11:39.

Transport for London (TfL) logo

LONG TERM
Until
1 May 2024
Details
View Map
Share
High Street

Transport for London (TfL) are carrying out Highway repair and maintenance works on High Street, Stratford, London.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 1 March 2024 at 08:00 and could run through until 1 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 5 Mar 2024 at 12:57.

Southern Gas Networks logo

LONG TERM
Between
4 Mar and 14 Apr 2024
Details
View Map
Share
Calderwood Street

Southern Gas Networks are proposing to carry out Utility repair and maintenance works on Calderwood Street, Woolwich.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 4 March 2024 and could run through until 14 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Southern Gas Networks on 2 Nov 2023 at 12:29.

LONG TERM
Between
4 Mar and 23 Apr 2024
Details
View Map
Share
Poplar High Street

London Borough Of Tower Hamlets are proposing to carry out Highway improvement works on Poplar High Street, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 4 March 2024 and could run through until 23 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by London Borough Of Tower Hamlets on 15 Jan 2024 at 11:11.

Thames Water logo

Finishing
Wednesday
Details
View Map
Share
Lloyd Road

Thames Water are carrying out Utility asset works on Lloyd Road, East Ham, London.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 6 March 2024 at 10:00 and could run through until 3 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 6 Mar 2024 at 10:08.

Southern Gas Networks logo

Until
4 Apr 2024
Details
View Map
Share
Holly Hill Road

Southern Gas Networks are carrying out Utility repair and maintenance works on Holly Hill Road, Erith.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 7 March 2024 at 05:00 and could run through until 4 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Southern Gas Networks on 27 Mar 2024 at 11:44.

LONG TERM
Between
7 Mar and 3 May 2024
Details
View Map
Share
Barking Road

London Borough Of Newham are proposing to carry out Section 50 on Barking Road, East Ham, London.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 7 March 2024 and could run through until 3 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by London Borough Of Newham on 7 Mar 2024 at 15:58.

Southern Gas Networks logo

LONG TERM
Until
19 May 2024
Details
View Map
Share
Blendon Road

Southern Gas Networks are carrying out Utility repair and maintenance works on Blendon Road, Bexley.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 12 March 2024 at 09:15 and could run through until 19 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Southern Gas Networks on 12 Mar 2024 at 09:30.

Southern Gas Networks logo

Finishing
Tuesday
Details
View Map
Share
Banwell Road

Southern Gas Networks are carrying out Utility repair and maintenance works on Banwell Road, Bexley.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 15 March 2024 at 10:00 and could run through until 2 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Southern Gas Networks on 15 Mar 2024 at 10:32.

UK Power Networks Eastern & London logo

LONG TERM
Until
11 Apr 2024
Details
View Map
Share
Kidbrooke Park Road

UK Power Networks Eastern & London are carrying out New service connection on Kidbrooke Park Road, Kidbrooke.

These works are categorised as Major.

Two-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 11 March 2024 at 08:00 and could run through until 11 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by UK Power Networks Eastern & London on 11 Mar 2024 at 14:49.

UK Power Networks Eastern & London logo

LONG TERM
Until
11 Apr 2024
Details
View Map
Share
Woolacombe Road

UK Power Networks Eastern & London are carrying out New service connection on Woolacombe Road, Kidbrooke.

These works are categorised as Major.

Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 11 March 2024 at 08:00 and could run through until 11 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by UK Power Networks Eastern & London on 11 Mar 2024 at 09:50.

Southern Gas Networks logo

Until
4 Apr 2024
Details
View Map
Share
Holly Hill Road

Southern Gas Networks are carrying out Utility repair and maintenance works on Holly Hill Road, Erith.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 11 March 2024 at 11:00 and could run through until 4 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Southern Gas Networks on 20 Mar 2024 at 12:51.

Thames Water logo

Until
7 Apr 2024
Details
View Map
Share
Davis Street

Thames Water are carrying out Utility repair and maintenance works on Davis Street, Plaistow, London.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 11 March 2024 at 18:00 and could run through until 7 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 21 Mar 2024 at 11:20.

Cadent Gas logo

Finishing
Tuesday
Details
View Map
Share
Woolwich Manor Way

Cadent Gas are carrying out Utility repair and maintenance works on Woolwich Manor Way, Beckton, London.

A lane is closed for some or all of the period and could cause delays to journeys.

The works started on 13 March 2024 at 09:33 and could run through until 2 April 2024. The works will impact the carriageway and footpath.

This roadwork event was last updated by Cadent Gas on 25 Mar 2024 at 09:22.

Thames Water logo

LONG TERM
Between
14 Mar and 8 May 2024
Details
View Map
Share
Clova Road

Thames Water are proposing to carry out Disconnection or alteration of supply on Clova Road, Forest Gate, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 14 March 2024 and could run through until 8 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 18 Dec 2023 at 11:15.

Cadent Gas logo

Finishing
Wednesday
Details
View Map
Share
Clements Lane

Cadent Gas are carrying out Utility repair and maintenance works on Clements Lane, Ilford.

A lane is closed for some or all of the period and could cause delays to journeys.

The works started on 14 March 2024 at 15:15 and could run through until 3 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Cadent Gas on 27 Mar 2024 at 16:30.

London Borough Of Redbridge logo

LONG TERM
Between
14 Mar and 5 May 2024
Details
View Map
Share
Balfour Road

London Borough Of Redbridge are proposing to carry out Highway repair and maintenance works on Balfour Road, Ilford.

These works are categorised as Major.

The works will start on or after 14 March 2024 and could run through until 5 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by London Borough Of Redbridge on 19 Mar 2024 at 11:09.

Thames Water logo

Until
7 Apr 2024
Details
View Map
Share
Ingledew Road

Thames Water are carrying out Utility repair and maintenance works on Ingledew Road, Plumstead.

The works started on 15 March 2024 at 20:00 and could run through until 7 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 25 Mar 2024 at 16:17.

Thames Water logo

LONG TERM
Between
15 Mar and 15 Apr 2024
Details
View Map
Share
Vicarage Road

Thames Water are proposing to carry out Disconnection or alteration of supply on Vicarage Road, Stratford, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 15 March 2024 and could run through until 15 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 15 Dec 2023 at 14:34.

LONG TERM
Until
10 May 2024
Details
View Map
Share
Romford Road

London Borough Of Newham are carrying out Highway improvement works on Romford Road, Manor Park, London.

These works are categorised as Major.

A lane is closed for some or all of the period and could cause delays to journeys.

The works started on 15 March 2024 at 08:00 and could run through until 10 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by London Borough Of Newham on 21 Mar 2024 at 10:09.

Until
6 Apr 2024
Details
View Map
Share
Thames Road

Essex And Suffolk Water are carrying out Utility repair and maintenance works on Thames Road, Barking.

These works are categorised as Major.

Two-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 17 March 2024 at 08:30 and could run through until 6 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Essex And Suffolk Water on 27 Mar 2024 at 16:30.

Thames Water logo

Until
9 Apr 2024
Details
View Map
Share
Bournbrook Road

Thames Water are carrying out Utility asset works on Bournbrook Road, Kidbrooke.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 19 March 2024 at 12:00 and could run through until 9 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 19 Mar 2024 at 12:56.

Thames Water logo

Until
15 Apr 2024
Details
View Map
Share
Hinstock Road

Thames Water are carrying out Utility asset works on Hinstock Road, Plumstead.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 21 March 2024 at 11:00 and could run through until 15 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 28 Mar 2024 at 08:50.

LONG TERM
Between
18 Mar and 19 Jul 2024
Details
View Map
Share
Frobisher Road

London Borough Of Newham are proposing to carry out Highway improvement works on Frobisher Road, Beckton, London.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 18 March 2024 and could run through until 19 July 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Newham on 1 Mar 2024 at 14:47.

LONG TERM
Between
20 Mar and 3 May 2024
Details
View Map
Share
Worcester Road

London Borough Of Newham are proposing to carry out Highway improvement works on Worcester Road, Manor Park, London.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 20 March 2024 and could run through until 3 May 2024. The works will impact the footway, carriageway and cycleway.

This roadwork event was last updated by London Borough Of Newham on 20 Dec 2023 at 10:03.

Thames Water logo

Until
6 Apr 2024
Details
View Map
Share
Bellegrove Road

Thames Water are carrying out Utility repair and maintenance works on Bellegrove Road, Welling.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 21 March 2024 at 10:06 and could run through until 6 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 21 Mar 2024 at 10:55.

Thames Water logo

Until
14 Apr 2024
Details
View Map
Share
Garland Road

Thames Water are carrying out Utility asset works on Garland Road, Plumstead.

These works are categorised as Major.

Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 22 March 2024 at 14:30 and could run through until 14 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 22 Mar 2024 at 16:19.

Until
6 Apr 2024
Details
View Map
Share
Romford Road

London Borough Of Newham are carrying out Highway improvement works on Romford Road, Stratford, London.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 21 March 2024 at 13:00 and could run through until 6 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by London Borough Of Newham on 21 Mar 2024 at 13:07.

Network Rail logo

Today
Details
View Map
Share
Trundleys Road

Network Rail carried out Works for Rail Purposes on Trundleys Road, London.

These works were categorised as Major.

The road was closed for some or all of the period.

The works were originally planned between 22 Mar 2024 and 28 Mar 2024 and were actually completed between 22 Mar 2024 (22:00) and 28 Mar 2024 (06:00). The works impacted the footway and carriageway.

This roadwork event was last updated by Network Rail on 28 Mar 2024 at 07:52.

Thames Water logo

Finishing
Monday
Details
View Map
Share
Station Road

Thames Water are carrying out Utility repair and maintenance works on Station Road, Sidcup.

Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 25 March 2024 at 13:18 and could run through until 1 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 26 Mar 2024 at 09:02.

Southern Gas Networks logo

LONG TERM
Until
6 May 2024
Details
View Map
Share
Blendon Drive

Southern Gas Networks are carrying out Utility repair and maintenance works on Blendon Drive, Bexley.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 26 March 2024 at 09:00 and could run through until 6 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Southern Gas Networks on 26 Mar 2024 at 09:25.

Thames Water logo

Finishing
Monday
Details
View Map
Share
Courthill Road

Thames Water are carrying out Utility repair and maintenance works on Courthill Road, Hither Green, London.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 25 March 2024 at 09:32 and could run through until 1 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 25 Mar 2024 at 10:10.

London Borough Of Bexley logo

Until
4 Apr 2024
Details
View Map
Share
Upper Park Road

London Borough Of Bexley are carrying out Highway repair and maintenance works on Upper Park Road, Belvedere.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 25 March 2024 at 08:00 and could run through until 4 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Bexley on 25 Mar 2024 at 10:42.

Southern Gas Networks logo

Between
25 Mar and 8 Apr 2024
Details
View Map
Share
Wilmount Street

Southern Gas Networks are proposing to carry out New service connection on Wilmount Street, Woolwich.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 25 March 2024 and could run through until 8 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Southern Gas Networks on 7 Mar 2024 at 11:13.

Transport for London (TfL) logo

LONG TERM
Until
30 Aug 2024
Details
View Map
Share
Blackwall Tunnel Southern Approach

Transport for London (TfL) are carrying out Highway improvement works on Blackwall Tunnel Southern Approach, Greenwich.

These works are categorised as Major.

A lane is closed for some or all of the period and could cause delays to journeys.

The works started on 25 March 2024 at 05:00 and could run through until 30 August 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 25 Mar 2024 at 16:15.

London Borough Of Bexley logo

Until
4 Apr 2024
Details
View Map
Share
Lower Park Road

London Borough Of Bexley are carrying out Highway repair and maintenance works on Lower Park Road, Belvedere.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 25 March 2024 at 08:00 and could run through until 4 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Bexley on 25 Mar 2024 at 10:42.

Thames Water logo

Finishing
Tomorrow
Details
View Map
Share
Egham Road

Thames Water are proposing to carry out Utility repair and maintenance works on Egham Road, Plaistow, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 25 March 2024 and could run through until 29 March 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 8 Dec 2023 at 10:06.

Transport for London (TfL) logo

Between
25 Mar and 16 Apr 2024
Details
View Map
Share
Ripple Road

Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Ripple Road, Dagenham.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 25 March 2024 and could run through until 16 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 26 Mar 2024 at 14:31.

Thames Water logo

Until
18 Apr 2024
Details
View Map
Share
Cabot Way

Thames Water are carrying out Utility asset works on Cabot Way, East Ham, London.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 25 March 2024 at 09:00 and could run through until 18 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 25 Mar 2024 at 09:26.

Thames Water logo

LONG TERM
Until
12 May 2024
Details
View Map
Share
Arragon Road

Thames Water are carrying out Utility asset works on Arragon Road, East Ham, London.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 25 March 2024 at 09:00 and could run through until 12 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 25 Mar 2024 at 09:27.

Between
25 Mar and 5 Apr 2024
Details
View Map
Share
Cridland Street

Last Mile Electricity (formerly Global Utility Connections) carried out Utility repair and maintenance works on Cridland Street, Stratford, London.

These works were categorised as Major.

The road was closed for some or all of the period.

The works were originally planned between 25 Mar 2024 and 5 Apr 2024 and were actually completed between 25 Mar 2024 (08:00) and 28 Mar 2024 (10:15). The works impacted the footway and carriageway.

This roadwork event was last updated by Last Mile Electricity (formerly Global Utility Connections) on 28 Mar 2024 at 10:26.

Thames Water logo

Between
25 Mar and 22 Apr 2024
Details
View Map
Share
Leonard Road

Thames Water are proposing to carry out Disconnection or alteration of supply on Leonard Road, Forest Gate, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 25 March 2024 and could run through until 22 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 3 Jan 2024 at 11:34.

LONG TERM
Between
25 Mar and 3 May 2024
Details
View Map
Share
Romford Road

London Borough Of Newham are proposing to carry out Highway improvement works on Romford Road, Manor Park, London.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 25 March 2024 and could run through until 3 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by London Borough Of Newham on 20 Dec 2023 at 10:03.

Royal Borough Of Greenwich logo

Until
7 Apr 2024
Details
View Map
Share
Footscray Road

Royal Borough Of Greenwich are carrying out Highway repair and maintenance works on Footscray Road, Eltham.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 26 March 2024 at 15:38 and could run through until 7 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Royal Borough Of Greenwich on 27 Mar 2024 at 08:27.

Thames Water logo

Monday
Details
View Map
Share
Radford Road

Thames Water carried out Utility repair and maintenance works on Radford Road, Hither Green, London.

These works were categorised as Major.

The road was closed for some or all of the period.

The works were originally planned between 26 Mar 2024 and 1 Apr 2024 and were actually completed between 26 Mar 2024 (09:05) and 28 Mar 2024 (19:58). The works impacted the footway and carriageway.

This roadwork event was last updated by Thames Water on 28 Mar 2024 at 21:46.

Cadent Gas logo

Until
9 Apr 2024
Details
View Map
Share
Lonsdale Close

Cadent Gas are carrying out Utility asset works on Lonsdale Close, East Ham, London.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 27 March 2024 at 09:53 and could run through until 9 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 27 Mar 2024 at 09:56.

Finishing
Tuesday
Details
View Map
Share
Tanner Street

Essex And Suffolk Water are carrying out Utility repair and maintenance works on Tanner Street, Barking.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 26 March 2024 at 11:44 and could run through until 2 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Essex And Suffolk Water on 26 Mar 2024 at 13:22.

Thames Water logo

Finishing
Wednesday
Details
View Map
Share
Woodlands Street

Thames Water are proposing to carry out Utility repair and maintenance works on Woodlands Street, Hither Green, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 27 March 2024 and could run through until 3 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 15 Jan 2024 at 10:07.

Thames Water logo

Finishing
Monday
Details
View Map
Share
Hither Green Lane

Thames Water are proposing to carry out Utility repair and maintenance works on Hither Green Lane, Hither Green, London.

These works are categorised as Major.

Two-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 27 March 2024 and could run through until 1 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 14 Mar 2024 at 14:46.

Thames Water logo

Until
10 Apr 2024
Details
View Map
Share
Footscray Road

Thames Water are carrying out Utility repair and maintenance works on Footscray Road, Eltham.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 27 March 2024 at 15:28 and could run through until 10 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 27 Mar 2024 at 16:37.

Thames Water logo

Finishing
Tuesday
Details
View Map
Share
Davenport Road

Thames Water are carrying out Utility repair and maintenance works on Davenport Road, London.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 27 March 2024 at 09:28 and could run through until 2 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 28 Mar 2024 at 16:10.

Electricity Network Company logo

Until
4 Apr 2024
Details
View Map
Share
Sherwood Road

Electricity Network Company are carrying out Utility asset works on Sherwood Road, Welling.

Two-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 27 March 2024 at 08:00 and could run through until 4 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Electricity Network Company on 27 Mar 2024 at 13:22.

Electricity Network Company logo

Until
4 Apr 2024
Details
View Map
Share
Wickham Street

Electricity Network Company are carrying out Utility asset works on Wickham Street, Welling.

Two-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 27 March 2024 at 08:00 and could run through until 4 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Electricity Network Company on 27 Mar 2024 at 13:23.

Electricity Network Company logo

Between
27 Mar and 4 Apr 2024
Details
View Map
Share
Edison Road

Electricity Network Company were proposing to carry out Utility asset works on Edison Road, Welling.

Two-way signals were planned to be in use for some or all of the period. However, the works were cancelled.

The works were originally planned to start 27 March 2024 and run through until 4 April 2024. The works were due to impact the carriageway only.

This roadwork event was last updated by Electricity Network Company on 27 Mar 2024 at 08:39.

Thames Water logo

Today
Details
View Map
Share
Erith High Street

Thames Water carried out Utility asset works on Erith High Street, Erith.

The road was closed for some or all of the period.

The works were originally planned between 27 Mar 2024 and 28 Mar 2024 and were actually completed between 27 Mar 2024 (22:00) and 28 Mar 2024 (05:30). The works impacted the carriageway only.

This roadwork event was last updated by Thames Water on 28 Mar 2024 at 08:24.

Thames Water logo

Finishing
Wednesday
Details
View Map
Share
Sprowston Road

Thames Water are carrying out Utility repair and maintenance works on Sprowston Road, Forest Gate, London.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 27 March 2024 at 08:15 and could run through until 3 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 27 Mar 2024 at 11:31.

Thames Water logo

Between
28 Mar and 9 Apr 2024
Details
View Map
Share
Eltham Road

Thames Water are proposing to carry out Utility asset works on Eltham Road, Eltham.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 28 March 2024 and could run through until 9 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 12 Mar 2024 at 16:23.

Thames Water logo

Between
28 Mar and 9 Apr 2024
Details
View Map
Share
Kidbrooke Park Road

Thames Water are proposing to carry out Utility asset works on Kidbrooke Park Road, Kidbrooke.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 28 March 2024 and could run through until 9 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 13 Mar 2024 at 15:17.

Electricity Network Company logo

Between
28 Mar and 5 Apr 2024
Details
View Map
Share
Edison Road

Electricity Network Company carried out Utility asset works on Edison Road, Welling.

Two-way signals were in place for some or all of the period.

The works were originally planned between 28 Mar 2024 and 5 Apr 2024 and were actually completed on 28 Mar 2024 between 08:00 and 10:13. The works impacted the carriageway only.

This roadwork event was last updated by Electricity Network Company on 28 Mar 2024 at 10:13.

Southern Gas Networks logo

Until
7 Apr 2024
Details
View Map
Share
Woolwich Road

Southern Gas Networks are carrying out Utility repair and maintenance works on Woolwich Road, Greenwich.

Two-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 28 March 2024 at 15:30 and could run through until 7 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Southern Gas Networks on 28 Mar 2024 at 17:40.

Southern Gas Networks logo

Until
7 Apr 2024
Details
View Map
Share
Woolwich New Road

Southern Gas Networks are carrying out Utility repair and maintenance works on Woolwich New Road, Woolwich.

Two-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 28 March 2024 at 13:15 and could run through until 7 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Southern Gas Networks on 28 Mar 2024 at 14:20.

Southern Gas Networks logo

Between
29 Mar and 13 Apr 2024
Details
View Map
Share
Pelham Road

Southern Gas Networks are proposing to carry out Utility repair and maintenance works on Pelham Road, Bexleyheath.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 29 March 2024 and could run through until 13 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Southern Gas Networks on 30 Oct 2023 at 15:39.

UK Power Networks Eastern & London logo

LONG TERM
Between
29 Mar and 1 Jul 2024
Details
View Map
Share
Bedonwell Road

UK Power Networks Eastern & London are proposing to carry out New service connection on Bedonwell Road, Bexleyheath.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 29 March 2024 and could run through until 1 July 2024. The works will impact the carriageway only.

This roadwork event was last updated by UK Power Networks Eastern & London on 20 Mar 2024 at 14:46.

UK Power Networks Eastern & London logo

Finishing
Wednesday
Details
View Map
Share
Ightham Road

UK Power Networks Eastern & London are proposing to carry out New service connection on Ightham Road, Erith.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 29 March 2024 and could run through until 3 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by UK Power Networks Eastern & London on 27 Mar 2024 at 07:36.

Thames Water logo

Between
29 Mar and 7 Apr 2024
Details
View Map
Share
Newham Way

Thames Water are proposing to carry out Utility repair and maintenance works on Newham Way, East Ham, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 29 March 2024 and could run through until 7 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 7 Mar 2024 at 07:34.

Thames Water logo

Between
29 Mar and 14 Apr 2024
Details
View Map
Share
High Street South

Thames Water are proposing to carry out Utility asset works on High Street South, East Ham, London.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 29 March 2024 and could run through until 14 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 22 Mar 2024 at 11:54.

Thames Water logo

Between
29 Mar and 14 Apr 2024
Details
View Map
Share
Barking Road

Thames Water are proposing to carry out roadworks on Barking Road, East Ham, London.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 29 March 2024 and could run through until 14 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 28 Feb 2024 at 23:07.

Thames Water logo

Between
30 Mar and 15 Apr 2024
Details
View Map
Share
Lakedale Road

Thames Water are proposing to carry out Utility repair and maintenance works on Lakedale Road, Plumstead.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 30 March 2024 and could run through until 15 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 20 Mar 2024 at 14:44.

Thames Water logo

Finishing
Wednesday
Details
View Map
Share
Green Lane

Thames Water are proposing to carry out Utility repair and maintenance works on Green Lane, Chislehurst.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 31 March 2024 and could run through until 3 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 21 Nov 2023 at 08:39.

Cadent Gas logo

LONG TERM
Between
31 Mar and 5 May 2024
Details
View Map
Share
Movers Lane

Cadent Gas are proposing to carry out Utility asset works on Movers Lane, Barking.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 31 March 2024 and could run through until 5 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 27 Feb 2024 at 15:14.

Southern Gas Networks logo

Between
1 and 9 Apr 2024
Details
View Map
Share
Shrapnel Road

Southern Gas Networks are proposing to carry out New service connection on Shrapnel Road, Eltham.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 1 April 2024 and could run through until 9 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Southern Gas Networks on 10 Jan 2024 at 10:53.

Between
1 and 12 Apr 2024
Details
View Map
Share
Bexley Road

Riverside Energy Park are proposing to carry out Utility asset works on Bexley Road, Erith.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 1 April 2024 and could run through until 12 April 2024. The works will impact the footway, carriageway and verge.

This roadwork event was last updated by Riverside Energy Park on 27 Feb 2024 at 09:48.

LONG TERM
Between
1 Apr and 22 Jun 2024
Details
View Map
Share
Queens Road

Riverside Energy Park are proposing to carry out Utility asset works on Queens Road, Erith.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 1 April 2024 and could run through until 22 June 2024. The works will impact the footway, carriageway and verge.

This roadwork event was last updated by Riverside Energy Park on 26 Mar 2024 at 12:34.

Between
1 and 20 Apr 2024
Details
View Map
Share
Commercial Road

Last Mile Electricity (formerly Global Utility Connections) are proposing to carry out Utility repair and maintenance works on Commercial Road, London.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 1 April 2024 and could run through until 20 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Last Mile Electricity (formerly Global Utility Connections) on 4 Mar 2024 at 10:16.

Between
1 and 11 Apr 2024
Details
View Map
Share
Link Road Kent Avenue

Essex And Suffolk Water are proposing to carry out Utility repair and maintenance works on Link Road Kent Avenue, Dagenham.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 1 April 2024 and could run through until 11 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex And Suffolk Water on 13 Mar 2024 at 16:21.

Between
1 and 11 Apr 2024
Details
View Map
Share
New Road

Essex And Suffolk Water are proposing to carry out Utility repair and maintenance works on New Road, Dagenham.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 1 April 2024 and could run through until 11 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Essex And Suffolk Water on 14 Mar 2024 at 14:03.

Thames Water logo

Between
1 and 14 Apr 2024
Details
View Map
Share
Bisson Road

Thames Water are proposing to carry out Utility repair and maintenance works on Bisson Road, Stratford, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 1 April 2024 and could run through until 14 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 21 Feb 2024 at 17:38.

Thames Water logo

Between
1 and 13 Apr 2024
Details
View Map
Share
School Road

Thames Water are proposing to carry out Utility repair and maintenance works on School Road, Dagenham.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 1 April 2024 and could run through until 13 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 17 Oct 2023 at 09:07.

Thames Water logo

LONG TERM
Between
1 Apr and 5 May 2024
Details
View Map
Share
Clements Road

Thames Water are proposing to carry out Utility asset works on Clements Road, East Ham, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 1 April 2024 and could run through until 5 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 28 Mar 2024 at 09:00.

Telefonica UK logo

Between
2 and 14 Apr 2024
Details
View Map
Share
Hurst Road

Telefonica UK are proposing to carry out Utility asset works on Hurst Road, Sidcup.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 2 April 2024 and could run through until 14 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Telefonica UK on 29 Nov 2023 at 17:06.

Transport for London (TfL) logo

LONG TERM
Between
2 Apr and 3 May 2024
Details
View Map
Share
Highland Road

Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Highland Road, Bexleyheath.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 2 April 2024 and could run through until 3 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Transport for London (TfL) on 8 Dec 2023 at 07:33.

Transport for London (TfL) logo

LONG TERM
Between
2 Apr and 3 May 2024
Details
View Map
Share
Arnsberg Way

Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Arnsberg Way, Bexleyheath.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 2 April 2024 and could run through until 3 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 8 Dec 2023 at 07:31.

London Borough Of Bexley logo

Between
2 and 4 Apr 2024
Details
View Map
Share
Haldane Road

London Borough Of Bexley are proposing to carry out Highway improvement works on Haldane Road, Thamesmead.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 2 April 2024 and could run through until 4 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Bexley on 11 Mar 2024 at 12:48.

London Borough Of Bexley logo

Between
2 and 4 Apr 2024
Details
View Map
Share
Bernal Close

London Borough Of Bexley are proposing to carry out Highway improvement works on Bernal Close, Thamesmead.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 2 April 2024 and could run through until 4 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Bexley on 11 Mar 2024 at 12:48.

London Borough Of Barking And Dagenham logo

LONG TERM
Between
2 Apr and 24 May 2024
Details
View Map
Share
Thames Road

London Borough Of Barking And Dagenham are proposing to carry out roadworks on Thames Road, Barking.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 2 April 2024 and could run through until 24 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by London Borough Of Barking And Dagenham on 22 Mar 2024 at 12:24.

Thames Water logo

Between
3 and 9 Apr 2024
Details
View Map
Share
Timbercroft Lane

Thames Water are proposing to carry out Utility repair and maintenance works on Timbercroft Lane, Plumstead.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 April 2024 and could run through until 9 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 15 Mar 2024 at 09:17.

UK Power Networks Eastern & London logo

LONG TERM
Between
3 Apr and 29 May 2024
Details
View Map
Share
Blackwall Tunnel Northern Approach

UK Power Networks Eastern & London are proposing to carry out Statutory Infrastructure Works on Blackwall Tunnel Northern Approach, London.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 April 2024 and could run through until 29 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by UK Power Networks Eastern & London on 16 Feb 2024 at 13:42.

UK Power Networks Eastern & London logo

LONG TERM
Between
3 Apr and 29 May 2024
Details
View Map
Share
Lochnagar Street

UK Power Networks Eastern & London are proposing to carry out Statutory Infrastructure Works on Lochnagar Street, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 April 2024 and could run through until 29 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by UK Power Networks Eastern & London on 7 Mar 2024 at 09:04.

UK Power Networks Eastern & London logo

Between
4 and 11 Apr 2024
Details
View Map
Share
Little Heath Road

UK Power Networks Eastern & London are proposing to carry out New service connection on Little Heath Road, Bexleyheath.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 4 April 2024 and could run through until 11 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by UK Power Networks Eastern & London on 27 Mar 2024 at 07:37.

Transport for London (TfL) logo

Between
5 Apr and 1 May 2024
Details
View Map
Share
Millennium Way

Transport for London (TfL) are proposing to carry out Highway improvement works on Millennium Way, Greenwich.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 5 April 2024 and could run through until 1 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 19 Mar 2024 at 13:10.

Transport for London (TfL) logo

Between
5 and 8 Apr 2024
Details
View Map
Share
Blackwall Tunnel

Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Blackwall Tunnel, Greenwich.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 5 April 2024 and could run through until 8 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 27 Mar 2024 at 15:36.

Transport for London (TfL) logo

Between
5 and 8 Apr 2024
Details
View Map
Share
Blackwall Tunnel

Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Blackwall Tunnel, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 5 April 2024 and could run through until 8 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 27 Mar 2024 at 15:07.

Transport for London (TfL) logo

Between
5 and 8 Apr 2024
Details
View Map
Share
Blackwall Tunnel

Transport for London (TfL) are proposing to carry out Highway improvement works on Blackwall Tunnel, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 5 April 2024 and could run through until 8 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 25 Mar 2024 at 13:13.

Transport for London (TfL) logo

Between
5 and 8 Apr 2024
Details
View Map
Share
Blackwall Tunnel Approach

Transport for London (TfL) are proposing to carry out Highway improvement works on Blackwall Tunnel Approach, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 5 April 2024 and could run through until 8 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 25 Mar 2024 at 11:34.

Transport for London (TfL) logo

Between
5 and 8 Apr 2024
Details
View Map
Share
Blackwall Tunnel Northern Approach

Transport for London (TfL) are proposing to carry out Highway improvement works on Blackwall Tunnel Northern Approach, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 5 April 2024 and could run through until 8 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 25 Mar 2024 at 11:35.

Thames Water logo

Between
5 and 11 Apr 2024
Details
View Map
Share
Manor Road

Thames Water are proposing to carry out New service connection on Manor Road, Canning Town, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 5 April 2024 and could run through until 11 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 28 Mar 2024 at 09:27.

Thames Water logo

Between
7 and 18 Apr 2024
Details
View Map
Share
Castleton Avenue

Thames Water are proposing to carry out Utility repair and maintenance works on Castleton Avenue, Bexleyheath.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 7 April 2024 and could run through until 18 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 13 Mar 2024 at 13:39.

Thames Water logo

Between
7 and 11 Apr 2024
Details
View Map
Share
Berkeley Avenue

Thames Water are proposing to carry out Utility repair and maintenance works on Berkeley Avenue, Bexleyheath.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 7 April 2024 and could run through until 11 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 18 Dec 2023 at 16:08.

London Borough Of Bexley logo

LONG TERM
Between
7 Apr and 16 May 2024
Details
View Map
Share
Church Manorway

London Borough Of Bexley are proposing to carry out Section 50 on Church Manorway, Erith.

These works are categorised as Major.

Two-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 7 April 2024 and could run through until 16 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by London Borough Of Bexley on 5 Mar 2024 at 15:32.

Between
7 and 11 Apr 2024
Details
View Map
Share
Tudor Road

London Borough Of Newham are proposing to carry out Highway improvement works on Tudor Road, East Ham, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 7 April 2024 and could run through until 11 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Newham on 26 Mar 2024 at 08:41.

Thames Water logo

LONG TERM
Between
7 Apr and 16 May 2024
Details
View Map
Share
Thorpe Road

Thames Water are proposing to carry out Utility asset works on Thorpe Road, East Ham, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 7 April 2024 and could run through until 16 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 27 Mar 2024 at 13:46.

Thames Water logo

LONG TERM
Between
7 Apr and 16 May 2024
Details
View Map
Share
Myrtle Road

Thames Water are proposing to carry out Utility asset works on Myrtle Road, East Ham, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 7 April 2024 and could run through until 16 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 27 Mar 2024 at 13:46.

Between
7 and 11 Apr 2024
Details
View Map
Share
Redclyffe Road

London Borough Of Newham are proposing to carry out Highway improvement works on Redclyffe Road, East Ham, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 7 April 2024 and could run through until 11 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Newham on 26 Mar 2024 at 08:40.

Thames Water logo

LONG TERM
Between
8 Apr and 25 May 2024
Details
View Map
Share
Chinbrook Road

Thames Water are proposing to carry out Disconnection or alteration of supply on Chinbrook Road, Grove Park, London.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 8 April 2024 and could run through until 25 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 8 Mar 2024 at 09:12.

Thames Water logo

LONG TERM
Between
8 Apr and 25 May 2024
Details
View Map
Share
Grove Park Road

Thames Water are proposing to carry out Disconnection or alteration of supply on Grove Park Road, Grove Park, London.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 8 April 2024 and could run through until 25 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 8 Mar 2024 at 09:11.

Thames Water logo

LONG TERM
Between
8 Apr and 25 May 2024
Details
View Map
Share
Marvels Lane

Thames Water are proposing to carry out Disconnection or alteration of supply on Marvels Lane, Grove Park, London.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 8 April 2024 and could run through until 25 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 8 Mar 2024 at 09:12.

Thames Water logo

Between
8 and 28 Apr 2024
Details
View Map
Share
Admaston Road

Thames Water are proposing to carry out Utility asset works on Admaston Road, Plumstead.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 8 April 2024 and could run through until 28 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 6 Mar 2024 at 08:42.

Thames Water logo

Between
8 and 11 Apr 2024
Details
View Map
Share
Forty Acre Lane

Thames Water are proposing to carry out Utility repair and maintenance works on Forty Acre Lane, Canning Town, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 8 April 2024 and could run through until 11 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 27 Mar 2024 at 15:00.

Thames Water logo

Between
8 and 12 Apr 2024
Details
View Map
Share
Hermit Road

Thames Water are proposing to carry out Utility repair and maintenance works on Hermit Road, Canning Town, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 8 April 2024 and could run through until 12 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 22 Mar 2024 at 15:41.

Thames Water logo

Between
8 and 12 Apr 2024
Details
View Map
Share
Boundary Road

Thames Water are proposing to carry out Utility repair and maintenance works on Boundary Road, Plaistow, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 8 April 2024 and could run through until 12 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 13 Mar 2024 at 14:41.

LONG TERM
Between
8 Apr and 10 May 2024
Details
View Map
Share
Eighth Avenue

London Borough Of Newham are proposing to carry out Highway improvement works on Eighth Avenue, Manor Park, London.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 8 April 2024 and could run through until 10 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Newham on 8 Jan 2024 at 11:00.

LONG TERM
Between
8 Apr and 10 May 2024
Details
View Map
Share
Romford Road

London Borough Of Newham are proposing to carry out Highway improvement works on Romford Road, Manor Park, London.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 8 April 2024 and could run through until 10 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by London Borough Of Newham on 8 Jan 2024 at 12:31.

LONG TERM
Between
8 Apr and 10 May 2024
Details
View Map
Share
Romford Road

London Borough Of Newham are proposing to carry out Highway improvement works on Romford Road, Manor Park, London.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 8 April 2024 and could run through until 10 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by London Borough Of Newham on 8 Jan 2024 at 11:00.

LONG TERM
Between
8 Apr and 10 May 2024
Details
View Map
Share
Romford Road

London Borough Of Newham are proposing to carry out Highway improvement works on Romford Road, Manor Park, London.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 8 April 2024 and could run through until 10 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by London Borough Of Newham on 8 Jan 2024 at 12:32.

Thames Water logo

LONG TERM
Between
9 Apr and 13 May 2024
Details
View Map
Share
Wellington Road

Thames Water are proposing to carry out Disconnection or alteration of supply on Wellington Road, Forest Gate, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 9 April 2024 and could run through until 13 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 18 Dec 2023 at 10:24.

UK Power Networks Eastern & London logo

Between
12 Apr and 11 May 2024
Details
View Map
Share
Church Road

UK Power Networks Eastern & London are proposing to carry out New service connection on Church Road, Bexleyheath.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 12 April 2024 and could run through until 11 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by UK Power Networks Eastern & London on 13 Mar 2024 at 06:35.

Transport for London (TfL) logo

Between
12 and 15 Apr 2024
Details
View Map
Share
Blackwall Tunnel

Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Blackwall Tunnel, Greenwich.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 12 April 2024 and could run through until 15 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 27 Mar 2024 at 15:37.

Transport for London (TfL) logo

Between
12 and 15 Apr 2024
Details
View Map
Share
Blackwall Tunnel

Transport for London (TfL) are proposing to carry out Highway improvement works on Blackwall Tunnel, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 12 April 2024 and could run through until 15 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 25 Mar 2024 at 12:10.

Transport for London (TfL) logo

Between
12 and 15 Apr 2024
Details
View Map
Share
Blackwall Tunnel Approach

Transport for London (TfL) are proposing to carry out Highway improvement works on Blackwall Tunnel Approach, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 12 April 2024 and could run through until 15 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 25 Mar 2024 at 11:39.

Transport for London (TfL) logo

Between
12 and 15 Apr 2024
Details
View Map
Share
Blackwall Tunnel Northern Approach

Transport for London (TfL) are proposing to carry out Highway improvement works on Blackwall Tunnel Northern Approach, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 12 April 2024 and could run through until 15 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 25 Mar 2024 at 12:12.

Transport for London (TfL) logo

Between
13 and 15 Apr 2024
Details
View Map
Share
Blackwall Tunnel

Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Blackwall Tunnel, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 13 April 2024 and could run through until 15 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 25 Mar 2024 at 13:44.

Southern Gas Networks logo

Between
14 Apr and 5 May 2024
Details
View Map
Share
Camden Road To The South Glade Footpath205

Southern Gas Networks are proposing to carry out Utility repair and maintenance works on Camden Road To The South Glade Footpath205, Bexley.

These works are categorised as Major.

There will be no traffic signals or road closures necessary for these works and traffic will operate on a give-and-take basis.

The works will start on or after 14 April 2024 and could run through until 5 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Southern Gas Networks on 21 Mar 2024 at 09:17.

Southern Gas Networks logo

Between
14 Apr and 12 May 2024
Details
View Map
Share
Riverdale Road

Southern Gas Networks are proposing to carry out Utility repair and maintenance works on Riverdale Road, Bexley.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 14 April 2024 and could run through until 12 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Southern Gas Networks on 27 Mar 2024 at 13:09.

Thames Water logo

Between
14 and 18 Apr 2024
Details
View Map
Share
Vambery Road

Thames Water are proposing to carry out Utility repair and maintenance works on Vambery Road, Plumstead.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 14 April 2024 and could run through until 18 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 19 Jan 2024 at 09:49.

London Borough Of Southwark logo

Between
14 and 22 Apr 2024
Details
View Map
Share
Redriff Road

London Borough Of Southwark are proposing to carry out Highway improvement works on Redriff Road, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 14 April 2024 and could run through until 22 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Southwark on 20 Dec 2023 at 14:04.

London Borough Of Southwark logo

Between
14 and 22 Apr 2024
Details
View Map
Share
Canada Street

London Borough Of Southwark are proposing to carry out Highway improvement works on Canada Street, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 14 April 2024 and could run through until 22 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Southwark on 20 Dec 2023 at 14:03.

London Borough Of Southwark logo

Between
14 and 22 Apr 2024
Details
View Map
Share
Quebec Way

London Borough Of Southwark are proposing to carry out Highway improvement works on Quebec Way, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 14 April 2024 and could run through until 22 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Southwark on 20 Dec 2023 at 13:51.

Between
14 and 18 Apr 2024
Details
View Map
Share
Carr Street

London Borough Of Tower Hamlets are proposing to carry out Highway improvement works on Carr Street, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 14 April 2024 and could run through until 18 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Tower Hamlets on 26 Feb 2024 at 10:06.

Thames Water logo

Between
15 and 19 Apr 2024
Details
View Map
Share
Vambery Road

Thames Water are proposing to carry out Utility repair and maintenance works on Vambery Road, Plumstead.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 15 April 2024 and could run through until 19 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 28 Mar 2024 at 12:44.

Vodafone logo

Between
15 and 19 Apr 2024
Details
View Map
Share
Thermopylae Gate

Vodafone are proposing to carry out Utility asset works on Thermopylae Gate, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 15 April 2024 and could run through until 19 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Vodafone on 27 Mar 2024 at 14:03.

Thames Water logo

Between
15 and 17 Apr 2024
Details
View Map
Share
Godwin Road

Thames Water are proposing to carry out Utility repair and maintenance works on Godwin Road, Forest Gate, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 15 April 2024 and could run through until 17 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 25 Jan 2024 at 14:41.

Thames Water logo

Between
16 and 22 Apr 2024
Details
View Map
Share
Coleraine Road

Thames Water are proposing to carry out Utility repair and maintenance works on Coleraine Road, Blackheath.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 16 April 2024 and could run through until 22 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 18 Jan 2024 at 06:22.

Thames Water logo

Between
16 and 22 Apr 2024
Details
View Map
Share
Coleraine Road

Thames Water are proposing to carry out Utility repair and maintenance works on Coleraine Road, Blackheath.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 16 April 2024 and could run through until 22 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 28 Mar 2024 at 13:21.

Thames Water logo

Between
16 Apr and 12 May 2024
Details
View Map
Share
Avenue Road

Thames Water are proposing to carry out Disconnection or alteration of supply on Avenue Road, Forest Gate, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 16 April 2024 and could run through until 12 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 18 Dec 2023 at 10:25.

Southern Gas Networks logo

LONG TERM
Between
17 Apr and 30 May 2024
Details
View Map
Share
Alanthus Close

Southern Gas Networks are proposing to carry out Utility repair and maintenance works on Alanthus Close, London.

These works are categorised as Major.

There will be no traffic signals or road closures necessary for these works and traffic will operate on a give-and-take basis.

The works will start on or after 17 April 2024 and could run through until 30 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Southern Gas Networks on 18 Jan 2024 at 10:06.

Between
19 and 24 Apr 2024
Details
View Map
Share
Lanrick Road

Nextgenaccess are proposing to carry out Utility asset works on Lanrick Road, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 19 April 2024 and could run through until 24 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by Nextgenaccess on 9 Feb 2024 at 10:05.

LONG TERM
Between
21 Apr and 13 Jun 2024
Details
View Map
Share
Green Street

London Borough Of Newham are proposing to carry out Highway improvement works on Green Street, Forest Gate, London.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 21 April 2024 and could run through until 13 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by London Borough Of Newham on 27 Mar 2024 at 07:35.

UK Power Networks Eastern & London logo

Between
22 and 24 Apr 2024
Details
View Map
Share
Gallions Road

UK Power Networks Eastern & London are proposing to carry out New service connection on Gallions Road, Charlton.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 22 April 2024 and could run through until 24 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by UK Power Networks Eastern & London on 19 Mar 2024 at 09:45.

Royal Borough Of Greenwich logo

Between
22 Apr and 13 May 2024
Details
View Map
Share
Bellot Street

Royal Borough Of Greenwich are proposing to carry out Highway repair and maintenance works on Bellot Street, Greenwich.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 22 April 2024 and could run through until 13 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by Royal Borough Of Greenwich on 22 Mar 2024 at 12:23.

UK Power Networks Eastern & London logo

LONG TERM
Between
22 Apr and 31 May 2024
Details
View Map
Share
Timber Pond Road

UK Power Networks Eastern & London are proposing to carry out Statutory Infrastructure Works on Timber Pond Road, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 22 April 2024 and could run through until 31 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by UK Power Networks Eastern & London on 28 Feb 2024 at 12:28.

UK Power Networks Eastern & London logo

Between
22 Apr and 12 May 2024
Details
View Map
Share
Fords Park Road

UK Power Networks Eastern & London are proposing to carry out New service connection on Fords Park Road, Canning Town, London.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 22 April 2024 and could run through until 12 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by UK Power Networks Eastern & London on 27 Mar 2024 at 11:27.

Thames Water logo

LONG TERM
Between
22 Apr and 5 Jun 2024
Details
View Map
Share
Pevensey Road

Thames Water are proposing to carry out Disconnection or alteration of supply on Pevensey Road, Forest Gate.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 22 April 2024 and could run through until 5 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 30 Jan 2024 at 14:04.

Thames Water logo

Between
23 and 26 Apr 2024
Details
View Map
Share
Fairway

Thames Water are proposing to carry out New service connection on Fairway, Bexleyheath.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 23 April 2024 and could run through until 26 April 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 25 Jan 2024 at 17:54.

London Borough Of Lewisham logo

Between
24 and 28 Apr 2024
Details
View Map
Share
Adelaide Avenue

London Borough Of Lewisham are proposing to carry out Highway improvement works on Adelaide Avenue, Ladywell, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 24 April 2024 and could run through until 28 April 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Lewisham on 27 Mar 2024 at 16:20.

Thames Water logo

Between
28 Apr and 18 May 2024
Details
View Map
Share
Hinstock Road

Thames Water are proposing to carry out Utility asset works on Hinstock Road, Plumstead.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 28 April 2024 and could run through until 18 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 7 Mar 2024 at 11:01.

Cadent Gas logo

Between
28 Apr and 19 May 2024
Details
View Map
Share
Kennedy Road

Cadent Gas are proposing to carry out Utility asset works on Kennedy Road, Barking.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 28 April 2024 and could run through until 19 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 23 Feb 2024 at 10:46.

Cadent Gas logo

Between
28 Apr and 19 May 2024
Details
View Map
Share
Ripple Road

Cadent Gas are proposing to carry out Utility asset works on Ripple Road, Barking.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 28 April 2024 and could run through until 19 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 27 Feb 2024 at 15:20.

London Borough Of Lewisham logo

Between
29 Apr and 1 May 2024
Details
View Map
Share
Harefield Road

London Borough Of Lewisham are proposing to carry out Highway improvement works on Harefield Road, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 29 April 2024 and could run through until 1 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Lewisham on 27 Mar 2024 at 16:21.

Between
29 Apr and 11 May 2024
Details
View Map
Share
Manilla Street

Last Mile Electricity (formerly Global Utility Connections) are proposing to carry out Utility repair and maintenance works on Manilla Street, London.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 29 April 2024 and could run through until 11 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Last Mile Electricity (formerly Global Utility Connections) on 13 Mar 2024 at 09:33.

Between
29 Apr and 11 May 2024
Details
View Map
Share
Cuba Street

Last Mile Electricity (formerly Global Utility Connections) are proposing to carry out Utility repair and maintenance works on Cuba Street, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 29 April 2024 and could run through until 11 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by Last Mile Electricity (formerly Global Utility Connections) on 13 Mar 2024 at 09:36.

Thames Water logo

Between
29 Apr and 8 May 2024
Details
View Map
Share
Saltwell Street

Thames Water are proposing to carry out Utility repair and maintenance works on Saltwell Street, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 29 April 2024 and could run through until 8 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 26 Feb 2024 at 12:46.

Cadent Gas logo

Between
29 Apr and 20 May 2024
Details
View Map
Share
Movers Lane

Cadent Gas are proposing to carry out Utility asset works on Movers Lane, Barking.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 29 April 2024 and could run through until 20 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 15 Feb 2024 at 12:49.

Thames Water logo

Between
29 Apr and 5 May 2024
Details
View Map
Share
Windmill Lane

Thames Water are proposing to carry out New service connection on Windmill Lane, Stratford, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 29 April 2024 and could run through until 5 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 30 Jan 2024 at 15:46.

LONG TERM
Between
30 Apr 2024 and 30 Apr 2025
Details
View Map
Share
North Woolwich Road

London Borough Of Newham are proposing to carry out Highway repair and maintenance works on North Woolwich Road, Silvertown, London.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 30 April 2024 and could run through until 30 April 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by London Borough Of Newham on 2 Feb 2024 at 12:23.

Thames Water logo

LONG TERM
Between
30 Apr and 19 Jun 2024
Details
View Map
Share
St James Road

Thames Water are proposing to carry out Disconnection or alteration of supply on St James Road, Stratford, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 30 April 2024 and could run through until 19 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 15 Dec 2023 at 14:38.

London Borough Of Lewisham logo

Between
1 and 3 May 2024
Details
View Map
Share
Pepys Road

London Borough Of Lewisham are proposing to carry out Highway improvement works on Pepys Road, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 1 May 2024 and could run through until 3 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Lewisham on 27 Mar 2024 at 16:16.

Transport for London (TfL) logo

Between
1 and 30 May 2024
Details
View Map
Share
East India Dock Road

Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on East India Dock Road, London.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 1 May 2024 and could run through until 30 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 12 Oct 2023 at 13:34.

Transport for London (TfL) logo

Between
1 and 30 May 2024
Details
View Map
Share
St Leonards Road

Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on St Leonards Road, London.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 1 May 2024 and could run through until 30 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 12 Oct 2023 at 13:42.

LONG TERM
Between
1 May and 26 Jun 2024
Details
View Map
Share
Choats Road

Last Mile Electricity (formerly Global Utility Connections) are proposing to carry out Utility repair and maintenance works on Choats Road, Barking.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 1 May 2024 and could run through until 26 June 2024. The works will impact the footway, carriageway and verge.

This roadwork event was last updated by Last Mile Electricity (formerly Global Utility Connections) on 28 Feb 2024 at 16:08.

Thames Water logo

LONG TERM
Between
5 May and 13 Jul 2024
Details
View Map
Share
Chaucer Road

Thames Water are proposing to carry out Utility asset works on Chaucer Road, Welling.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 5 May 2024 and could run through until 13 July 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 20 Feb 2024 at 18:39.

Thames Water logo

LONG TERM
Between
6 May 2024 and 13 May 2025
Details
View Map
Share
Longmead Drive

Thames Water are proposing to carry out New service connection on Longmead Drive, Sidcup.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 6 May 2024 and could run through until 13 May 2025. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 14 Mar 2023 at 17:16.

Southern Gas Networks logo

LONG TERM
Between
6 May and 10 Jun 2024
Details
View Map
Share
Valentine Avenue

Southern Gas Networks are proposing to carry out Utility repair and maintenance works on Valentine Avenue, Bexley.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 6 May 2024 and could run through until 10 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Southern Gas Networks on 25 Mar 2024 at 11:04.

London Borough Of Bexley logo

Between
6 and 10 May 2024
Details
View Map
Share
Blackfen Road

London Borough Of Bexley are proposing to carry out Highway improvement works on Blackfen Road, Sidcup.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 6 May 2024 and could run through until 10 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Bexley on 1 Feb 2024 at 15:54.

London Borough Of Lewisham logo

Between
6 and 17 May 2024
Details
View Map
Share
Brockley Road

London Borough Of Lewisham are proposing to carry out Highway repair and maintenance works on Brockley Road, Crofton Park, London.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 6 May 2024 and could run through until 17 May 2024. The works will impact the footway only.

This roadwork event was last updated by London Borough Of Lewisham on 8 Mar 2024 at 15:24.

UK Power Networks Eastern & London logo

LONG TERM
Between
6 May and 21 Jun 2024
Details
View Map
Share
Grove Street

UK Power Networks Eastern & London are proposing to carry out Utility asset works on Grove Street, London.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 6 May 2024 and could run through until 21 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by UK Power Networks Eastern & London on 30 Jan 2024 at 19:31.

Between
6 May and 3 Jun 2024
Details
View Map
Share
Chequers Lane

Last Mile Electricity (formerly Global Utility Connections) are proposing to carry out Utility repair and maintenance works on Chequers Lane, Dagenham.

These works are categorised as Major.

Two-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 6 May 2024 and could run through until 3 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Last Mile Electricity (formerly Global Utility Connections) on 21 Dec 2023 at 12:20.

Thames Water logo

LONG TERM
Between
6 May and 17 Jun 2024
Details
View Map
Share
Barking Road

Thames Water are proposing to carry out Utility asset works on Barking Road, East Ham, London.

These works are categorised as Major.

Two-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 6 May 2024 and could run through until 17 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 12 Feb 2024 at 11:43.

Thames Water logo

Between
6 and 27 May 2024
Details
View Map
Share
Wellington Road

Thames Water are proposing to carry out Utility asset works on Wellington Road, East Ham, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 6 May 2024 and could run through until 27 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 12 Feb 2024 at 11:45.

Thames Water logo

Between
6 and 27 May 2024
Details
View Map
Share
Streatfeild Avenue

Thames Water are proposing to carry out Utility asset works on Streatfeild Avenue, East Ham, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 6 May 2024 and could run through until 27 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 12 Feb 2024 at 11:44.

Thames Water logo

Between
6 and 27 May 2024
Details
View Map
Share
Didsbury Close

Thames Water are proposing to carry out Utility asset works on Didsbury Close, East Ham, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 6 May 2024 and could run through until 27 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 12 Feb 2024 at 11:47.

Thames Water logo

Between
6 and 27 May 2024
Details
View Map
Share
Latimer Avenue

Thames Water are proposing to carry out Utility asset works on Latimer Avenue, East Ham, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 6 May 2024 and could run through until 27 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 12 Feb 2024 at 11:46.

Thames Water logo

Between
6 and 14 May 2024
Details
View Map
Share
Great Eastern Road

Thames Water are proposing to carry out Utility repair and maintenance works on Great Eastern Road, Stratford, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 6 May 2024 and could run through until 14 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 6 Feb 2024 at 14:31.

LONG TERM
Between
7 May and 7 Jun 2024
Details
View Map
Share
Bugsbys Way

Last Mile Electricity (formerly Global Utility Connections) are proposing to carry out Utility repair and maintenance works on Bugsbys Way, Charlton.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 7 May 2024 and could run through until 7 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Last Mile Electricity (formerly Global Utility Connections) on 28 Mar 2024 at 13:47.

BT logo

Between
7 and 9 May 2024
Details
View Map
Share
Woodlands Road

BT are proposing to carry out Utility asset works on Woodlands Road, Ilford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 7 May 2024 and could run through until 9 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by BT on 7 Feb 2024 at 12:53.

Thames Water logo

Between
12 and 15 May 2024
Details
View Map
Share
Cambria Close

Thames Water are proposing to carry out New service connection on Cambria Close, Sidcup.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 12 May 2024 and could run through until 15 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 20 Mar 2024 at 14:08.

UK Power Networks Eastern & London logo

LONG TERM
Between
12 May and 13 Jun 2024
Details
View Map
Share
Belvedere Road

UK Power Networks Eastern & London are proposing to carry out New service connection on Belvedere Road, Bexleyheath.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 12 May 2024 and could run through until 13 June 2024. The works will impact the carriageway only.

This roadwork event was last updated by UK Power Networks Eastern & London on 18 Mar 2024 at 10:50.

Thames Water logo

Between
12 and 16 May 2024
Details
View Map
Share
Lovel Avenue

Thames Water are proposing to carry out Utility repair and maintenance works on Lovel Avenue, Welling.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 12 May 2024 and could run through until 16 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 19 Feb 2024 at 15:45.

Between
12 and 27 May 2024
Details
View Map
Share
Queens Road

Riverside Energy Park are proposing to carry out Utility asset works on Queens Road, Erith.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 12 May 2024 and could run through until 27 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by Riverside Energy Park on 25 Oct 2023 at 13:00.

Thames Water logo

Between
12 and 26 May 2024
Details
View Map
Share
West Ham Lane

Thames Water are proposing to carry out Utility asset works on West Ham Lane, Stratford, London.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 12 May 2024 and could run through until 26 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 27 Feb 2024 at 15:59.

Thames Water logo

LONG TERM
Between
12 May and 15 Jun 2024
Details
View Map
Share
Aldworth Road

Thames Water are proposing to carry out Utility asset works on Aldworth Road, Stratford, London.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 12 May 2024 and could run through until 15 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 27 Feb 2024 at 15:47.

Transport for London (TfL) logo

LONG TERM
Between
13 May and 28 Jun 2024
Details
View Map
Share
White Horse Hill

Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on White Horse Hill, Chislehurst.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 13 May 2024 and could run through until 28 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Transport for London (TfL) on 19 Feb 2024 at 09:49.

Transport for London (TfL) logo

LONG TERM
Between
13 May and 28 Jun 2024
Details
View Map
Share
Elmstead Lane

Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Elmstead Lane, Chislehurst.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 13 May 2024 and could run through until 28 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Transport for London (TfL) on 19 Feb 2024 at 09:32.

Transport for London (TfL) logo

LONG TERM
Between
13 May and 28 Jun 2024
Details
View Map
Share
William Barefoot Drive

Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on William Barefoot Drive, Eltham.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 13 May 2024 and could run through until 28 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Transport for London (TfL) on 12 Feb 2024 at 18:29.

Transport for London (TfL) logo

LONG TERM
Between
13 May and 28 Jun 2024
Details
View Map
Share
Mottingham Road

Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Mottingham Road, Mottingham.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 13 May 2024 and could run through until 28 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Transport for London (TfL) on 19 Feb 2024 at 09:32.

Murphy Power Distribution logo

LONG TERM
Between
13 May and 21 Jun 2024
Details
View Map
Share
Mastmaker Road

Murphy Power Distribution are proposing to carry out Utility asset works on Mastmaker Road, London.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 13 May 2024 and could run through until 21 June 2024. The works will impact the carriageway only.

This roadwork event was last updated by Murphy Power Distribution on 12 Feb 2024 at 13:39.

BT logo

Between
13 and 15 May 2024
Details
View Map
Share
South Esk Road

BT are proposing to carry out Utility asset works on South Esk Road, Forest Gate, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 13 May 2024 and could run through until 15 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by BT on 31 Jan 2024 at 16:11.

LONG TERM
Between
13 May and 13 Jul 2024
Details
View Map
Share
Eighth Avenue

London Borough Of Newham are proposing to carry out Works for road purposes on Eighth Avenue, Manor Park, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 13 May 2024 and could run through until 13 July 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Newham on 19 Mar 2024 at 12:12.

Thames Water logo

Between
13 and 24 May 2024
Details
View Map
Share
Barwick Road

Thames Water are proposing to carry out Disconnection or alteration of supply on Barwick Road, Forest Gate, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 13 May 2024 and could run through until 24 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 31 Jan 2024 at 16:09.

Thames Water logo

Between
14 and 16 May 2024
Details
View Map
Share
Laurie Grove

Thames Water are proposing to carry out New service connection on Laurie Grove, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 14 May 2024 and could run through until 16 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 20 Feb 2024 at 09:22.

Transport for London (TfL) logo

Between
17 and 20 May 2024
Details
View Map
Share
Blackwall Tunnel

Transport for London (TfL) are proposing to carry out Highway improvement works on Blackwall Tunnel, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 17 May 2024 and could run through until 20 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 25 Mar 2024 at 11:43.

Transport for London (TfL) logo

Between
17 and 20 May 2024
Details
View Map
Share
Blackwall Tunnel Approach

Transport for London (TfL) are proposing to carry out Highway improvement works on Blackwall Tunnel Approach, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 17 May 2024 and could run through until 20 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 25 Mar 2024 at 11:42.

Transport for London (TfL) logo

Between
17 and 20 May 2024
Details
View Map
Share
Blackwall Tunnel Northern Approach

Transport for London (TfL) are proposing to carry out Highway improvement works on Blackwall Tunnel Northern Approach, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 17 May 2024 and could run through until 20 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 25 Mar 2024 at 13:09.

Southern Gas Networks logo

Between
19 and 23 May 2024
Details
View Map
Share
Durham Road

Southern Gas Networks are proposing to carry out New service connection on Durham Road, Sidcup.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 19 May 2024 and could run through until 23 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Southern Gas Networks on 23 Nov 2023 at 14:50.

Thames Water logo

Between
19 and 21 May 2024
Details
View Map
Share
Faraday Avenue

Thames Water are proposing to carry out Utility repair and maintenance works on Faraday Avenue, Sidcup.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 19 May 2024 and could run through until 21 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 14 Mar 2024 at 15:37.

Thames Water logo

Between
19 May and 8 Jun 2024
Details
View Map
Share
Olven Road

Thames Water are proposing to carry out Utility asset works on Olven Road, Plumstead.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 19 May 2024 and could run through until 8 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 7 Mar 2024 at 11:03.

Cadent Gas logo

Between
19 and 23 May 2024
Details
View Map
Share
Tidworth Road

Cadent Gas are proposing to carry out Utility asset works on Tidworth Road, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 19 May 2024 and could run through until 23 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by Cadent Gas on 5 Mar 2024 at 13:08.

Thames Water logo

Between
20 and 22 May 2024
Details
View Map
Share
Combedale Road

Thames Water are proposing to carry out Remedial works on Combedale Road, Greenwich.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 20 May 2024 and could run through until 22 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 15 Feb 2024 at 09:55.

London Borough Of Bexley logo

Between
20 and 25 May 2024
Details
View Map
Share
Eastern Way

London Borough Of Bexley are proposing to carry out Highway repair and maintenance works on Eastern Way, Thamesmead.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 20 May 2024 and could run through until 25 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Bexley on 22 Mar 2024 at 09:22.

Electricity Network Company logo

Between
20 and 24 May 2024
Details
View Map
Share
New Road

Electricity Network Company are proposing to carry out Utility asset works on New Road, Dagenham.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 20 May 2024 and could run through until 24 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Electricity Network Company on 27 Feb 2024 at 12:48.

Thames Water logo

Between
20 and 23 May 2024
Details
View Map
Share
Windmill Lane

Thames Water are proposing to carry out Utility repair and maintenance works on Windmill Lane, Stratford, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 20 May 2024 and could run through until 23 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 19 Feb 2024 at 15:45.

Between
24 and 30 May 2024
Details
View Map
Share
Queens Road

Riverside Energy Park are proposing to carry out Utility asset works on Queens Road, Erith.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 24 May 2024 and could run through until 30 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by Riverside Energy Park on 25 Oct 2023 at 13:01.

BT logo

Between
24 and 31 May 2024
Details
View Map
Share
Plumstead High Street

BT are proposing to carry out Utility asset works on Plumstead High Street, Plumstead.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 24 May 2024 and could run through until 31 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by BT on 15 Mar 2024 at 09:13.

BT logo

Between
24 and 31 May 2024
Details
View Map
Share
Kentmere Road

BT are proposing to carry out Utility asset works on Kentmere Road, Plumstead.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 24 May 2024 and could run through until 31 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by BT on 15 Mar 2024 at 09:12.

Southern Gas Networks logo

Between
26 May and 16 Jun 2024
Details
View Map
Share
Iris Avenue

Southern Gas Networks are proposing to carry out Utility repair and maintenance works on Iris Avenue, Bexley.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 26 May 2024 and could run through until 16 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Southern Gas Networks on 27 Mar 2024 at 13:23.

Thames Water logo

Between
27 and 30 May 2024
Details
View Map
Share
Belmont Lane

Thames Water are proposing to carry out Utility repair and maintenance works on Belmont Lane, Chislehurst.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 27 May 2024 and could run through until 30 May 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 17 Jan 2024 at 15:10.

Thames Water logo

Between
27 May and 2 Jun 2024
Details
View Map
Share
Gourock Road

Thames Water are proposing to carry out Utility repair and maintenance works on Gourock Road, Eltham.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 27 May 2024 and could run through until 2 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 14 Mar 2024 at 15:02.

London Borough Of Bexley logo

Between
27 and 30 May 2024
Details
View Map
Share
Hook Lane

London Borough Of Bexley are proposing to carry out Highway improvement works on Hook Lane, Welling.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 27 May 2024 and could run through until 30 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Bexley on 10 Jan 2024 at 08:57.

London Borough Of Bexley logo

Between
27 and 30 May 2024
Details
View Map
Share
Hook Lane

London Borough Of Bexley are proposing to carry out Highway improvement works on Hook Lane, Welling.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 27 May 2024 and could run through until 30 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Bexley on 12 Mar 2024 at 13:37.

Network Rail logo

LONG TERM
Between
27 May and 16 Aug 2024
Details
View Map
Share
St Germans Place

Network Rail are proposing to carry out Works for Rail Purposes on St Germans Place, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 27 May 2024 and could run through until 16 August 2024. The works will impact the carriageway only.

This roadwork event was last updated by Network Rail on 8 Mar 2024 at 15:46.

Thames Water logo

Between
27 May and 2 Jun 2024
Details
View Map
Share
Nithdale Road

Thames Water are proposing to carry out Utility repair and maintenance works on Nithdale Road, Plumstead.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 27 May 2024 and could run through until 2 June 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 20 Mar 2024 at 09:22.

Thames Water logo

Between
28 May and 16 Jun 2024
Details
View Map
Share
Chinbrook Road

Thames Water are proposing to carry out Disconnection or alteration of supply on Chinbrook Road, Grove Park, London.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 28 May 2024 and could run through until 16 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 7 Mar 2024 at 09:37.

Thames Water logo

Between
28 May and 16 Jun 2024
Details
View Map
Share
Amblecote Road

Thames Water are proposing to carry out Disconnection or alteration of supply on Amblecote Road, Grove Park, London.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 28 May 2024 and could run through until 16 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 7 Mar 2024 at 09:38.

Thames Water logo

Between
28 May and 16 Jun 2024
Details
View Map
Share
Marbrook Court

Thames Water are proposing to carry out Disconnection or alteration of supply on Marbrook Court, Grove Park, London.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 28 May 2024 and could run through until 16 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 7 Mar 2024 at 09:40.

Transport for London (TfL) logo

LONG TERM
Between
28 May and 13 Jul 2024
Details
View Map
Share
Talehangers Close

Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Talehangers Close, Bexleyheath.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 28 May 2024 and could run through until 13 July 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 26 Mar 2024 at 12:19.

Transport for London (TfL) logo

LONG TERM
Between
28 May and 13 Jul 2024
Details
View Map
Share
Crook Log

Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Crook Log, Bexleyheath.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 28 May 2024 and could run through until 13 July 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 26 Mar 2024 at 12:18.

Transport for London (TfL) logo

LONG TERM
Between
28 May and 13 Jul 2024
Details
View Map
Share
Danson Road

Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Danson Road, Bexleyheath.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 28 May 2024 and could run through until 13 July 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 26 Mar 2024 at 12:18.

Transport for London (TfL) logo

LONG TERM
Between
28 May and 13 Jul 2024
Details
View Map
Share
Brampton Road

Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Brampton Road, Bexleyheath.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 28 May 2024 and could run through until 13 July 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 26 Mar 2024 at 12:18.

Transport for London (TfL) logo

LONG TERM
Between
28 May and 13 Jul 2024
Details
View Map
Share
Park View Road

Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Park View Road, Welling.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 28 May 2024 and could run through until 13 July 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 26 Mar 2024 at 12:17.

London Borough Of Bexley logo

Between
28 and 31 May 2024
Details
View Map
Share
Hook Lane

London Borough Of Bexley are proposing to carry out Highway improvement works on Hook Lane, Welling.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 28 May 2024 and could run through until 31 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Bexley on 12 Mar 2024 at 12:24.

Thames Water logo

Between
28 May and 3 Jun 2024
Details
View Map
Share
Millmark Grove

Thames Water are proposing to carry out Utility repair and maintenance works on Millmark Grove, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 28 May 2024 and could run through until 3 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 12 Mar 2024 at 13:07.

LONG TERM
Between
28 May and 4 Jul 2024
Details
View Map
Share
Queens Road

Riverside Energy Park are proposing to carry out Utility asset works on Queens Road, Erith.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 28 May 2024 and could run through until 4 July 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Riverside Energy Park on 19 Oct 2023 at 13:16.

London Borough Of Bexley logo

Between
29 and 31 May 2024
Details
View Map
Share
Waldrist Way

London Borough Of Bexley are proposing to carry out Highway improvement works on Waldrist Way, Erith.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 29 May 2024 and could run through until 31 May 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Bexley on 13 Mar 2024 at 07:49.

Transport for London (TfL) logo

Between
31 May and 3 Jun 2024
Details
View Map
Share
Blackwall Tunnel

Transport for London (TfL) are proposing to carry out Highway improvement works on Blackwall Tunnel, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 31 May 2024 and could run through until 3 June 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 25 Mar 2024 at 13:13.

Transport for London (TfL) logo

Between
31 May and 3 Jun 2024
Details
View Map
Share
Blackwall Tunnel Approach

Transport for London (TfL) are proposing to carry out Highway improvement works on Blackwall Tunnel Approach, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 31 May 2024 and could run through until 3 June 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 25 Mar 2024 at 11:45.

Transport for London (TfL) logo

Between
31 May and 3 Jun 2024
Details
View Map
Share
Blackwall Tunnel Northern Approach

Transport for London (TfL) are proposing to carry out Highway improvement works on Blackwall Tunnel Northern Approach, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 31 May 2024 and could run through until 3 June 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 25 Mar 2024 at 11:46.

Transport for London (TfL) logo

Between
1 and 30 Jun 2024
Details
View Map
Share
Trafalgar Way

Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Trafalgar Way, London.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 1 June 2024 and could run through until 30 June 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 12 Oct 2023 at 14:38.

Transport for London (TfL) logo

Between
1 and 30 Jun 2024
Details
View Map
Share
Aspen Way

Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Aspen Way, London.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 1 June 2024 and could run through until 30 June 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 12 Oct 2023 at 14:42.

Transport for London (TfL) logo

Between
1 and 30 Jun 2024
Details
View Map
Share
Prestons Road Roundabout

Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Prestons Road Roundabout, London.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 1 June 2024 and could run through until 30 June 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 12 Oct 2023 at 14:27.

Transport for London (TfL) logo

Between
1 and 30 Jun 2024
Details
View Map
Share
Prestons Road

Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Prestons Road, London.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 1 June 2024 and could run through until 30 June 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 12 Oct 2023 at 14:45.

Thames Water logo

Between
2 and 30 Jun 2024
Details
View Map
Share
Wakefield Street

Thames Water are proposing to carry out Utility asset works on Wakefield Street, East Ham, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 2 June 2024 and could run through until 30 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 22 Mar 2024 at 11:54.

Thames Water logo

Between
2 and 16 Jun 2024
Details
View Map
Share
Katherine Road

Thames Water are proposing to carry out Utility asset works on Katherine Road, East Ham, London.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 2 June 2024 and could run through until 16 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 6 Mar 2024 at 12:12.

Thames Water logo

Between
2 and 7 Jun 2024
Details
View Map
Share
Ron Leighton Way

Thames Water are proposing to carry out New service connection on Ron Leighton Way, East Ham, London.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 2 June 2024 and could run through until 7 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 4 Mar 2024 at 10:54.

Thames Water logo

Between
2 and 7 Jun 2024
Details
View Map
Share
Clements Road

Thames Water are proposing to carry out roadworks on Clements Road, East Ham, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 2 June 2024 and could run through until 7 June 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 4 Mar 2024 at 10:02.

Thames Water logo

Between
2 Jun and 2 Jul 2024
Details
View Map
Share
Manbey Grove

Thames Water are proposing to carry out Disconnection or alteration of supply on Manbey Grove, Stratford, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 2 June 2024 and could run through until 2 July 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 4 Jan 2024 at 10:37.

Southern Gas Networks logo

LONG TERM
Between
3 Jun and 8 Jul 2024
Details
View Map
Share
Wickham Street

Southern Gas Networks are proposing to carry out Utility repair and maintenance works on Wickham Street, Welling.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 June 2024 and could run through until 8 July 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Southern Gas Networks on 26 Mar 2024 at 12:40.

Southern Gas Networks logo

LONG TERM
Between
3 Jun and 8 Jul 2024
Details
View Map
Share
Chaucer Road

Southern Gas Networks are proposing to carry out Utility repair and maintenance works on Chaucer Road, Welling.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 June 2024 and could run through until 8 July 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Southern Gas Networks on 26 Mar 2024 at 16:32.

London Borough Of Bexley logo

Between
3 and 6 Jun 2024
Details
View Map
Share
Lessness Park

London Borough Of Bexley are proposing to carry out Highway improvement works on Lessness Park, Belvedere.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 June 2024 and could run through until 6 June 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Bexley on 18 Mar 2024 at 11:41.

UK Power Networks Eastern & London logo

LONG TERM
Between
3 Jun and 12 Jul 2024
Details
View Map
Share
Grove Street

UK Power Networks Eastern & London are proposing to carry out Utility asset works on Grove Street, London.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 3 June 2024 and could run through until 12 July 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by UK Power Networks Eastern & London on 31 Jan 2024 at 03:27.

UK Power Networks Eastern & London logo

LONG TERM
Between
3 Jun and 6 Jul 2024
Details
View Map
Share
Trafalgar Way

UK Power Networks Eastern & London are proposing to carry out Utility asset works on Trafalgar Way, London.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 June 2024 and could run through until 6 July 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by UK Power Networks Eastern & London on 15 Mar 2024 at 10:49.

UK Power Networks Eastern & London logo

LONG TERM
Between
3 Jun and 13 Jul 2024
Details
View Map
Share
Blackwall Way

UK Power Networks Eastern & London are proposing to carry out Utility asset works on Blackwall Way, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 June 2024 and could run through until 13 July 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by UK Power Networks Eastern & London on 15 Mar 2024 at 10:17.

Network Rail logo

Between
3 and 28 Jun 2024
Details
View Map
Share
Montfichet Road

Network Rail are proposing to carry out Works for Rail Purposes on Montfichet Road, Stratford, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 June 2024 and could run through until 28 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Network Rail on 12 Feb 2024 at 12:33.

Transport for London (TfL) logo

Between
7 and 10 Jun 2024
Details
View Map
Share
Blackwall Tunnel

Transport for London (TfL) are proposing to carry out Highway improvement works on Blackwall Tunnel, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 7 June 2024 and could run through until 10 June 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 25 Mar 2024 at 11:51.

Transport for London (TfL) logo

Between
7 and 10 Jun 2024
Details
View Map
Share
Blackwall Tunnel Approach

Transport for London (TfL) are proposing to carry out Highway improvement works on Blackwall Tunnel Approach, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 7 June 2024 and could run through until 10 June 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 25 Mar 2024 at 11:51.

Transport for London (TfL) logo

Between
7 and 10 Jun 2024
Details
View Map
Share
Blackwall Tunnel Northern Approach

Transport for London (TfL) are proposing to carry out Highway improvement works on Blackwall Tunnel Northern Approach, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 7 June 2024 and could run through until 10 June 2024. The works will impact the carriageway only.

This roadwork event was last updated by Transport for London (TfL) on 25 Mar 2024 at 13:10.

Southern Gas Networks logo

Between
9 Jun and 7 Jul 2024
Details
View Map
Share
Wellington Road

Southern Gas Networks are proposing to carry out Utility repair and maintenance works on Wellington Road, Bexley.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 9 June 2024 and could run through until 7 July 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Southern Gas Networks on 27 Mar 2024 at 13:12.

Thames Water logo

Between
9 and 13 Jun 2024
Details
View Map
Share
Gourock Road

Thames Water are proposing to carry out Utility repair and maintenance works on Gourock Road, Eltham.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 9 June 2024 and could run through until 13 June 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 14 Mar 2024 at 11:29.

Thames Water logo

Between
9 and 29 Jun 2024
Details
View Map
Share
Upton Road

Thames Water are proposing to carry out Utility asset works on Upton Road, Plumstead.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 9 June 2024 and could run through until 29 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 5 Mar 2024 at 10:40.

Thames Water logo

Between
9 and 12 Jun 2024
Details
View Map
Share
Francis Street

Thames Water are proposing to carry out New service connection on Francis Street, Stratford, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 9 June 2024 and could run through until 12 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 14 Mar 2024 at 10:12.

Cadent Gas logo

Between
10 and 24 Jun 2024
Details
View Map
Share
Saxon Road

Cadent Gas are proposing to carry out Utility asset works on Saxon Road, Ilford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 10 June 2024 and could run through until 24 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 20 Mar 2024 at 13:50.

Cadent Gas logo

Between
10 and 24 Jun 2024
Details
View Map
Share
Norman Road

Cadent Gas are proposing to carry out Utility asset works on Norman Road, Ilford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 10 June 2024 and could run through until 24 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 20 Mar 2024 at 13:50.

Cadent Gas logo

Between
10 and 24 Jun 2024
Details
View Map
Share
Baden Road

Cadent Gas are proposing to carry out Utility asset works on Baden Road, Ilford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 10 June 2024 and could run through until 24 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 20 Mar 2024 at 13:50.

Cadent Gas logo

Between
10 and 24 Jun 2024
Details
View Map
Share
Hickling Road

Cadent Gas are proposing to carry out Utility asset works on Hickling Road, Ilford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 10 June 2024 and could run through until 24 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 20 Mar 2024 at 13:50.

Cadent Gas logo

LONG TERM
Between
10 Jun and 15 Jul 2024
Details
View Map
Share
Mayville Road

Cadent Gas are proposing to carry out Utility asset works on Mayville Road, Ilford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 10 June 2024 and could run through until 15 July 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 20 Mar 2024 at 13:50.

Southern Gas Networks logo

Between
11 and 25 Jun 2024
Details
View Map
Share
Woodside Lane

Southern Gas Networks are proposing to carry out Utility repair and maintenance works on Woodside Lane, Bexley.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 11 June 2024 and could run through until 25 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Southern Gas Networks on 12 Mar 2024 at 15:40.

Thames Water logo

Between
11 and 17 Jun 2024
Details
View Map
Share
Wilmount Street

Thames Water are proposing to carry out Utility repair and maintenance works on Wilmount Street, Woolwich.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 11 June 2024 and could run through until 17 June 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 15 Mar 2024 at 10:33.

Cadent Gas logo

Between
11 and 25 Jun 2024
Details
View Map
Share
Roman Road

Cadent Gas are proposing to carry out Utility asset works on Roman Road, Ilford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 11 June 2024 and could run through until 25 June 2024. The works will impact the carriageway only.

This roadwork event was last updated by Cadent Gas on 20 Mar 2024 at 10:56.

Southern Gas Networks logo

LONG TERM
Between
12 Jun and 22 Aug 2024
Details
View Map
Share
Elmwood Drive

Southern Gas Networks are proposing to carry out Utility repair and maintenance works on Elmwood Drive, Bexley.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 12 June 2024 and could run through until 22 August 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Southern Gas Networks on 12 Mar 2024 at 15:53.

UK Power Networks Eastern & London logo

LONG TERM
Between
14 Jun and 26 Jul 2024
Details
View Map
Share
Belvedere Road

UK Power Networks Eastern & London are proposing to carry out New service connection on Belvedere Road, Bexleyheath.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 14 June 2024 and could run through until 26 July 2024. The works will impact the carriageway only.

This roadwork event was last updated by UK Power Networks Eastern & London on 18 Mar 2024 at 15:38.

Network Rail logo

Between
14 and 17 Jun 2024
Details
View Map
Share
Trundleys Road

Network Rail are proposing to carry out Works for Rail Purposes on Trundleys Road, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 14 June 2024 and could run through until 17 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Network Rail on 21 Mar 2024 at 15:57.

Thames Water logo

Between
15 Jun and 13 Jul 2024
Details
View Map
Share
Faringford Road

Thames Water are proposing to carry out Utility asset works on Faringford Road, Stratford, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 15 June 2024 and could run through until 13 July 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 27 Feb 2024 at 16:03.

Thames Water logo

Between
16 and 20 Jun 2024
Details
View Map
Share
Regeneration Road

Thames Water are proposing to carry out Utility repair and maintenance works on Regeneration Road, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 16 June 2024 and could run through until 20 June 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 22 Mar 2024 at 09:34.

Thames Water logo

LONG TERM
Between
16 Jun 2024 and 31 Jan 2025
Details
View Map
Share
Manchester Road

Thames Water are proposing to carry out Utility asset works on Manchester Road, London.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 16 June 2024 and could run through until 31 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 20 Mar 2024 at 14:29.

Thames Water logo

Between
16 and 22 Jun 2024
Details
View Map
Share
Tant Avenue

Thames Water are proposing to carry out roadworks on Tant Avenue, Canning Town, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 16 June 2024 and could run through until 22 June 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 19 Mar 2024 at 14:02.

Thames Water logo

Between
16 and 20 Jun 2024
Details
View Map
Share
Stokes Road

Thames Water are proposing to carry out New service connection on Stokes Road, East Ham, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 16 June 2024 and could run through until 20 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 28 Mar 2024 at 15:15.

Thames Water logo

Between
16 Jun and 7 Jul 2024
Details
View Map
Share
Kempton Road

Thames Water are proposing to carry out Utility asset works on Kempton Road, East Ham, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 16 June 2024 and could run through until 7 July 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 22 Mar 2024 at 11:55.

Thames Water logo

Between
16 Jun and 7 Jul 2024
Details
View Map
Share
Skeffington Road

Thames Water are proposing to carry out Utility asset works on Skeffington Road, East Ham, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 16 June 2024 and could run through until 7 July 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 22 Mar 2024 at 11:51.

Thames Water logo

Between
16 Jun and 7 Jul 2024
Details
View Map
Share
Caledon Road

Thames Water are proposing to carry out Utility asset works on Caledon Road, East Ham, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 16 June 2024 and could run through until 7 July 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 22 Mar 2024 at 11:51.

Thames Water logo

Between
16 Jun and 7 Jul 2024
Details
View Map
Share
Caulfield Road

Thames Water are proposing to carry out Utility repair and maintenance works on Caulfield Road, East Ham, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 16 June 2024 and could run through until 7 July 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 22 Mar 2024 at 11:53.

London Borough Of Bexley logo

Between
17 and 27 Jun 2024
Details
View Map
Share
Parsonage Manorway

London Borough Of Bexley are proposing to carry out Highway improvement works on Parsonage Manorway, Belvedere.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 17 June 2024 and could run through until 27 June 2024. The works will impact the carriageway only.

This roadwork event was last updated by London Borough Of Bexley on 15 Jan 2024 at 10:18.

Electricity Network Company logo

Between
17 Jun and 12 Jul 2024
Details
View Map
Share
West Street

Electricity Network Company are proposing to carry out Utility asset works on West Street, Erith.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 17 June 2024 and could run through until 12 July 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Electricity Network Company on 22 Mar 2024 at 14:37.

UK Power Networks Eastern & London logo

Between
21 Jun and 1 Jul 2024
Details
View Map
Share
Hythe Avenue

UK Power Networks Eastern & London are proposing to carry out New service connection on Hythe Avenue, Bexleyheath.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 21 June 2024 and could run through until 1 July 2024. The works will impact the carriageway only.

This roadwork event was last updated by UK Power Networks Eastern & London on 27 Mar 2024 at 07:37.

Thames Water logo

Between
23 and 27 Jun 2024
Details
View Map
Share
Plymouth Road

Thames Water are proposing to carry out Utility repair and maintenance works on Plymouth Road, Canning Town, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 23 June 2024 and could run through until 27 June 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 27 Mar 2024 at 14:04.

Thames Water logo

Between
23 and 27 Jun 2024
Details
View Map
Share
Sprowston Road

Thames Water are proposing to carry out Utility repair and maintenance works on Sprowston Road, Forest Gate, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 23 June 2024 and could run through until 27 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 25 Mar 2024 at 09:41.

Thames Water logo

Between
23 and 30 Jun 2024
Details
View Map
Share
Church Road

Thames Water are proposing to carry out New service connection on Church Road, Manor Park, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 23 June 2024 and could run through until 30 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 25 Mar 2024 at 13:36.

Thames Water logo

Between
23 and 30 Jun 2024
Details
View Map
Share
Osborne Road

Thames Water are proposing to carry out roadworks on Osborne Road, Forest Gate, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 23 June 2024 and could run through until 30 June 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 26 Mar 2024 at 15:36.

Thames Water logo

Between
23 and 30 Jun 2024
Details
View Map
Share
Woodgrange Road

Thames Water are proposing to carry out New service connection on Woodgrange Road, Forest Gate, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 23 June 2024 and could run through until 30 June 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 25 Mar 2024 at 14:10.

Southern Gas Networks logo

LONG TERM
Between
24 Jun and 29 Sep 2024
Details
View Map
Share
Hurst Road

Southern Gas Networks are proposing to carry out Utility repair and maintenance works on Hurst Road, Bexley.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 24 June 2024 and could run through until 29 September 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Southern Gas Networks on 27 Mar 2024 at 13:33.

Thames Tideway Tunnel logo

LONG TERM
Between
24 Jun and 30 Sep 2024
Details
View Map
Share
Deptford Church Street

Thames Tideway Tunnel are proposing to carry out Highway improvement works on Deptford Church Street, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 24 June 2024 and could run through until 30 September 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Tideway Tunnel on 13 Mar 2024 at 16:21.

Thames Tideway Tunnel logo

LONG TERM
Between
24 Jun and 30 Sep 2024
Details
View Map
Share
Creek Road

Thames Tideway Tunnel are proposing to carry out roadworks on Creek Road, Deptford.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 24 June 2024 and could run through until 30 September 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Tideway Tunnel on 15 Mar 2024 at 06:58.

Thames Water logo

LONG TERM
Between
24 Jun and 23 Sep 2024
Details
View Map
Share
Ripley Road

Thames Water are proposing to carry out Disconnection or alteration of supply on Ripley Road, Belvedere.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 24 June 2024 and could run through until 23 September 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 26 Mar 2024 at 10:15.

Thames Water logo

LONG TERM
Between
24 Jun and 23 Aug 2024
Details
View Map
Share
Stanmore Road

Thames Water are proposing to carry out Disconnection or alteration of supply on Stanmore Road, Belvedere.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 24 June 2024 and could run through until 23 August 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 26 Mar 2024 at 09:53.

Thames Water logo

LONG TERM
Between
24 Jun and 26 Jul 2024
Details
View Map
Share
Upper Sheridan Road

Thames Water are proposing to carry out Disconnection or alteration of supply on Upper Sheridan Road, Belvedere.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 24 June 2024 and could run through until 26 July 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 26 Mar 2024 at 10:09.

Thames Water logo

LONG TERM
Between
24 Jun and 2 Sep 2024
Details
View Map
Share
Gladeswood Road

Thames Water are proposing to carry out Disconnection or alteration of supply on Gladeswood Road, Belvedere.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 24 June 2024 and could run through until 2 September 2024. The works will impact the carriageway only.

This roadwork event was last updated by Thames Water on 26 Mar 2024 at 10:00.

Thames Water logo

Between
24 Jun and 8 Jul 2024
Details
View Map
Share
Bartle Avenue

Thames Water are proposing to carry out Utility asset works on Bartle Avenue, East Ham, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 24 June 2024 and could run through until 8 July 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Thames Water on 8 Feb 2024 at 15:23.

Southern Gas Networks logo

Between
25 Jun and 11 Jul 2024
Details
View Map
Share
The Avenue

Southern Gas Networks are proposing to carry out Utility repair and maintenance works on The Avenue, Bexley.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 25 June 2024 and could run through until 11 July 2024. The works will impact the footway, carriageway and verge.

This roadwork event was last updated by Southern Gas Networks on 26 Mar 2024 at 15:40.


Roadworks Map near to SE18 9ED

Colour Codes
Planned
In Progress
Completed
Cancelled
Last Updated: 28 Mar 2024 21:59
Notes

  • Any red lines indicate the extent of the works.
  • Clicking on the map will re-centre to the selected point.
  • Within 1 mile, all roadworks are displayed.
  • Within 2-3 miles, standard, urgent and major roadworks are displayed.
  • For 3-5 miles, only major roadworks are shown.
  • The higher the marker number, the further away the roadworks are from the centre of the postcode.

Roadworks Listing near to SE18 9ED (30 Events)

  • ...
Works Location and Details
Actual Work Date
(Scheduled Dates)
Status
Distance
(miles)
1
Southern Gas Networks logo
MAJOR
  
WILMOUNT STREET (0.1 miles)
Southern Gas Networks
New service connection - Footway, Carriageway - Road closure
Planned
Scheduled: 25 Mar 2024 - 8 Apr 2024
0.1
Share
2
Southern Gas Networks logo
MAJOR
  
CALDERWOOD STREET (0.1 miles)
Southern Gas Networks
Utility repair and maintenance works - Footway, Carriageway - Road closure
Planned
Scheduled: 4 Mar 2024 - 14 Apr 2024
0.1
Share
3
Southern Gas Networks logo
EMERGENCY
  
WOOLWICH NEW ROAD (0.2 miles)
Southern Gas Networks
Utility repair and maintenance works - Carriageway - Two-way signals
In Progress
Since: 28 Mar 2024 13:15
(Scheduled: 28 Mar 2024 - 7 Apr 2024)
0.2
Share
4
Royal Borough Of Greenwich logo
MAJOR
  
BERESFORD STREET (0.2 miles)
Royal Borough Of Greenwich
Highway repair and maintenance works - Footway - Lane closure
Planned
Scheduled: 1 Jan 2024 - 31 Dec 2024
0.2
Share
5
Southern Gas Networks logo
EMERGENCY
  
FOOTPATH FROM FRONT OF 54 TO OUTSIDE 82 ARTHUR GROVE (0.3 miles)
Southern Gas Networks
Utility repair and maintenance works - Footway - No carriageway incursion
In Progress
Since: 25 Mar 2024 13:30
(Scheduled: 25 Mar 2024 - 2 Apr 2024)
0.3
Share
6
UK Power Networks Eastern & London logo
BELSON ROAD (0.4 miles)
UK Power Networks Eastern & London
Disconnection or alteration of supply - Footway - No carriageway incursion
Complete
25 Mar 2024 10:00 - 28 Mar 2024 12:51
0.4
Share
7
UK Power Networks Eastern & London logo
BELSON ROAD (0.5 miles)
UK Power Networks Eastern & London
Disconnection or alteration of supply - Footway - Some carriageway incursion
Complete
25 Mar 2024 10:44 - 28 Mar 2024 12:27
0.5
Share
8
BT logo
BURRAGE ROAD (0.5 miles)
BT
New service connection - Footway - No carriageway incursion
Planned
Scheduled: 29 Mar 2024
0.5
Share
9
Its Technology Group logo
OGILBY STREET (0.6 miles)
Its Technology Group
Permanent reinstatement - Footway, Carriageway - Some carriageway incursion
Complete
28 Mar 2024 10:05 - 12:56
0.6
Share
10
Hyperoptic logo
GLYNDON ROAD (0.6 miles)
Hyperoptic
New service connection - Carriageway - Stop/go boards
Planned
Scheduled: 28 Mar 2024
0.6
Share
  • ...

Contains public sector information licensed under the Open Government Licence v3.0.
Traffic camera information is Powered by TfL Open Data