PARLIAMENTARY WRITTEN QUESTION
Sizewell C Power Station: Finance (16 October 2024)
Question Asked
Asked by:
Wera Hobhouse (Liberal Democrat)
Answer
Sizewell C’s spending plans are agreed by shareholders, including Government. The public disclosure of detailed spending plans whilst the project is engaged in live commercial negotiations could have a negative impact on the project’s negotiating position and undermine the project’s value for money.
Sizewell C Ltd publishes an annual report and accounts, which are available to view at Companies House. This sets out expenditure and income for each financial year.
The Department also includes information about amounts invested into the project via its annual report and accounts, which are published and laid before Parliament.
Answered by:
Michael Shanks (Labour)
25 October 2024
Contains Parliamentary information licensed under the Open Parliament Licence v3.0.